Project Type: Transmission reinforcement
Location: Highland

Contact Details

Liaison Manager

Lisa Marchi-Grey
Title: Community Liaison Manager
Telephone: 01463 728072
Mobile: 07825 015507
Address: 10 Henderson Road, Inverness, IV1 1SN

Land Manager

Chris Mangnall
Title: Wayleaves Officer
Mobile: 07285 015239
Address: 10 Henderson Road, Inverness, IV1 1SN
Status: Construction Phase

Existing Network

The existing Beauly to Dounreay 275kV overhead transmission circuit runs for a distance of approx. 153km from Beauly substation in the South to Dounreay substation in the North and comprises a Western circuit which runs the full length from Beauly to Dounreay; and an Eastern circuit which originally ran from Beauly as far as the former tapping compound to Invergordon Smelter at Ardross.

 

Phase 1 Transmission Reinforcements

The Beauly-Dounreay Phase 1 Project commenced on site in October 2010 and involved the re-conductoring of the existing 275kV conductor between Beauly and Ardross; and installation of new conductors on the east side of the existing double circuit 275kV tower line from Ardross to Dounreay. This second circuit, running the full distance from Dounreay to Beauly, was completed early in 2013 and the project as a whole is expected to be complete by the end of the year.

Phase 2 Transmission Reinforcements

The Beauly-Dounreay Phase 2 reinforcements comprise:-

  • a new 275/132kV substation at Loch Buidhe;
  • a new 275/132kV substation at Fyrish; and
  • replacement of the existing 275kV conductor between Beauly and Loch Buidhe. 

The voltage of the line will remain unchanged. In relation to the overhead line re-conductoring works no additional towers will be erected, there will be no increase in the height of existing towers and the new conductors will look the same as the existing ones from ground level.

The new substations will house switchgear and transformers to support the upgraded overhead line and to allow capacity for future renewable energy projects to be connected between Beauly and Dounreay. Connection of these new substations to the existing overhead lines will require some localised amendments to overhead tower arrangements in the vicinity of the Fyrish and Loch Buidhe substations.

The data in this map is provided for indicative purposes only and may be subject to change. Scottish Hydro Electric Transmission plc do not accept responsibility for its accuracy, completeness or validity. The data should not be copied, reproduced or utilised externally without permission.

Who is Scottish and Southern Electricity Networks?

Scottish and Southern Electricity Networks is the trading name of Scottish and Southern Energy Power Distribution Limited, Scottish Hydro Electric Transmission plc, Scottish Hydro Electric Power Distribution plc and Southern Electric Power Distribution plc.

How are Transmission network upgrades paid for?

Investments in projects are made by SHE Transmission plc. Electricity transmission companies are authorised to recover the costs of such investments through 'use of system' charges which are levied by National Grid Electricity Transmission plc on generators and suppliers of electricity. Suppliers recover their costs from all electricity customers. In order to protect the interests of customers, the transmission companies have to demonstrate to the energy regulator, Ofgem (Office for Gas and Electricity Markets) that proposed investments are necessary, are efficient and are economical so that the charges which are ultimately levied on all electricity customers are justified.
This means SHE Transmission is subject to a funding mechanism established by Parliament and regulated by Ofgem. Cross subsidies between different businesses in the SSE group is not permitted.

How are our proposals scrutinised?

The Scottish Ministers are responsible for determination of applications submitted under Section 37 of the Electricity Act 1989. Both statutory consultees and members of the public have the right to submit their representations on the application. All representations will be considered by Scottish Ministers in their determination of the application.
The Office for Gas and Electricity Markets (Ofgem), as the regulator, has to approve all investment so project proposals are developed under license conditions.
Preferred route corridors chosen will comply with revised ‘Holford Rules’ which are the recognised industry approach to routeing overhead lines amended to reflect Scottish circumstances.

What are The Holford Rules?

The Holford Rules originated in 1959 as the result of work by Lord Holford, a part-time member of the Central Electricity Generating Board (National Grid's predecessor). The Holford Rules have been augmented by both National Grid and SHE Transmission plc to reflect environmental legislation and best practice in recent years. We have continued to use them as a valuable set of guidelines for reducing the impact of our assets on landscapes.
The guidance recommends appropriate application of the Holford Rules to inform routeing. These rules advocate the application of a hierarchical approach to routeing which first avoids major areas of highest amenity, then smaller areas of high amenity, and finally considers factors such as backdrop, woodland and orientation. The Holford Rules apply the term ‘amenity’ to refer to environmental designations and classifications such as Natura 2000 sites, Sites of Special Scientific Interest (SSSI), Scheduled Monuments, Listed Buildings, National Parks.
The guidance also recognises that the key effect of overhead lines is visual and it advises that the routeing of overhead lines should consider the types of mitigation (screening) that could offset any visual effects.
In their National Policy Statement EN-5, the Government has stated that the Holford Rules “should be followed by developers when designing their proposals.” Their use is therefore Government policy, rather than a voluntary choice of SHE Transmission plc.

How and to what extent are electricity consumers' interests considered?

We are regulated by the Office for Gas and Electricity Markets (Ofgem), the regulator responsible for representing consumers' interests. Electricity consumer interests are therefore one of our key drivers and this is enshrined in our statutory duties under the Electricity Act.
In particular we have a statutory duty to develop, maintain and operate an efficient, economic and co-ordinated transmission system. Since the costs of these projects will ultimately be paid for by electricity consumers, we have a responsibility to take cost into account with due weighting in a comparison against other important factors.

What is the transmission network?

It’s the highest voltage electricity network in the UK – the ‘motorway network’ of the energy world. It transmits large quantities of electricity over long distances via wires carried on a system of mainly metal towers (pylons) and large substations. Transmission voltages in Scotland are 132kV, 275kV and 400kV. Larger generation schemes usually connect to the Transmission system.

The lower voltage parts of the system are called distribution networks. In Scotland, these local networks operate below 132kV whereas in England the distribution network includes 132kV. 

Sign up for project updates

Keep informed with all that's happening on this project