Project Type: Transmission reinforcement
Location: Perth & Kinross, Highland, Stirling

Contact Details

Liaison Manager

Neil Anderson
Title: Community Team Manager
Telephone: 01738 516529
Mobile: 07500 912506
Address: Inveralmond House, 200 Dunkeld Road, Perth, PH1 3AQ

Land Manager

Robin Cameron
Title: Land Manager
Mobile: 07500 912921
Address: Inveralmond House, 200 Dunkeld Perth, PH1 3AQ
Status: Operational

About the Beauly-Denny project

The full length of the Beauly-Denny line has been successfully energised and is now operating at up to 400 kilovolts.

The 220km replacement overhead line was developed jointly by Scottish Hydro Electric Transmission plc and SP Energy Networks, which own and invest in the high voltage electricity networks in the north and south of Scotland respectively.

The new line is supported by 615 steel towers, replacing over 800 pre-existing 132 kilovolt towers that were built in the early 1950s. The renewal of the north-south spine of Scotland’s electricity network has supported more than 2000 jobs over a 7 year period. It is the longest transmission line to be built anywhere in the UK in recent times and crosses the highest and most inaccessible terrain on the Great Britain transmission system at the 2526ft summit of the Corrieyairack Pass.

Find out more

We have created five short films which explain what is involved in a project that benefits an entire country. Whilst the Beauly-Denny project was impressive in its size and complexity, the methods of development and execution detailed in the films apply to all major overhead line projects undertaken by Scottish and Southern Electricity Networks.

Preparing for a major overhead line project

This film describes the steps required to be undertaken before an overhead line can proceed into construction. Development teams will regularly develop a project over months and years before submitting a planning application. Following a successful planning application being received, a significant amount of preparation work is required to be completed in advance of the construction phases.

Groundworks

This film helps explain the enormous efforts required to be undertaken before any new electricity structures can be erected. Teams of tree cutters and civil engineers will lead the way to ensure safe access can be made to multiple construction sites. During these initial stages, the teams focus on how to minimise potential impacts on communities and the environment. Completion of safe access then allows skilled engineers access to begin construction of the tower foundations, some would argue these are the most important part of an overhead line.

Tower Construction

This film provides an insight into what is involved in erecting steel towers that are capable of transporting 400,000 volts. The constructions team faced severe weather whilst working in some of Scotland's most challenging environments. The Beauly-Denny project has claim to the highest located transmission tower in the UK, located over 2,500ft up a mountain. Engineers had to coordinate works with weather windows and also with members of the public which has led to the use of ingenious construction methods.

Rationalisation and Dismantling

The Beauly-Denny project had unique conditions associated to its Section 37 consent that required the undergrounding or complete removal of lower voltage overhead. These conditions were imposed upon the project to help reduce the overall visual impact of overhead lines in specific areas including the Cairngorms National Park. The final stages of the Beauly-Denny project required the dismantling of over 600 old towers and reinstatement of access tracks created at the beginning of the project, a significant undertaking which required care and attention.

Substation Development

This film highlights the importance of substations within the electrical network. Without substations, energy could not be transported safely around the country to those who require it. They require a large amount of civil works ahead of the construction and delivery of equipment that can weigh up to 180 tonnes.

The data in this map is provided for indicative purposes only and may be subject to change. Scottish Hydro Electric Transmission plc do not accept responsibility for its accuracy, completeness or validity. The data should not be copied, reproduced or utilised externally without permission.

Who is Scottish and Southern Electricity Networks?

Scottish and Southern Electricity Networks is the trading name of Scottish and Southern Energy Power Distribution Limited, Scottish Hydro Electric Transmission plc, Scottish Hydro Electric Power Distribution plc and Southern Electric Power Distribution plc.

How are Transmission network upgrades paid for?

Investments in projects are made by SHE Transmission plc. Electricity transmission companies are authorised to recover the costs of such investments through 'use of system' charges which are levied by National Grid Electricity Transmission plc on generators and suppliers of electricity. Suppliers recover their costs from all electricity customers. In order to protect the interests of customers, the transmission companies have to demonstrate to the energy regulator, Ofgem (Office for Gas and Electricity Markets) that proposed investments are necessary, are efficient and are economical so that the charges which are ultimately levied on all electricity customers are justified.
This means SHE Transmission is subject to a funding mechanism established by Parliament and regulated by Ofgem. Cross subsidies between different businesses in the SSE group is not permitted.

How are our proposals scrutinised?

The Scottish Ministers are responsible for determination of applications submitted under Section 37 of the Electricity Act 1989. Both statutory consultees and members of the public have the right to submit their representations on the application. All representations will be considered by Scottish Ministers in their determination of the application.
The Office for Gas and Electricity Markets (Ofgem), as the regulator, has to approve all investment so project proposals are developed under license conditions.
Preferred route corridors chosen will comply with revised ‘Holford Rules’ which are the recognised industry approach to routeing overhead lines amended to reflect Scottish circumstances.

What are The Holford Rules?

The Holford Rules originated in 1959 as the result of work by Lord Holford, a part-time member of the Central Electricity Generating Board (National Grid's predecessor). The Holford Rules have been augmented by both National Grid and SHE Transmission plc to reflect environmental legislation and best practice in recent years. We have continued to use them as a valuable set of guidelines for reducing the impact of our assets on landscapes.
The guidance recommends appropriate application of the Holford Rules to inform routeing. These rules advocate the application of a hierarchical approach to routeing which first avoids major areas of highest amenity, then smaller areas of high amenity, and finally considers factors such as backdrop, woodland and orientation. The Holford Rules apply the term ‘amenity’ to refer to environmental designations and classifications such as Natura 2000 sites, Sites of Special Scientific Interest (SSSI), Scheduled Monuments, Listed Buildings, National Parks.
The guidance also recognises that the key effect of overhead lines is visual and it advises that the routeing of overhead lines should consider the types of mitigation (screening) that could offset any visual effects.
In their National Policy Statement EN-5, the Government has stated that the Holford Rules “should be followed by developers when designing their proposals.” Their use is therefore Government policy, rather than a voluntary choice of SHE Transmission plc.

How and to what extent are electricity consumers' interests considered?

We are regulated by the Office for Gas and Electricity Markets (Ofgem), the regulator responsible for representing consumers' interests. Electricity consumer interests are therefore one of our key drivers and this is enshrined in our statutory duties under the Electricity Act.
In particular we have a statutory duty to develop, maintain and operate an efficient, economic and co-ordinated transmission system. Since the costs of these projects will ultimately be paid for by electricity consumers, we have a responsibility to take cost into account with due weighting in a comparison against other important factors.

What is the transmission network?

It’s the highest voltage electricity network in the UK – the ‘motorway network’ of the energy world. It transmits large quantities of electricity over long distances via wires carried on a system of mainly metal towers (pylons) and large substations. Transmission voltages in Scotland are 132kV, 275kV and 400kV. Larger generation schemes usually connect to the Transmission system.

The lower voltage parts of the system are called distribution networks. In Scotland, these local networks operate below 132kV whereas in England the distribution network includes 132kV. 

Transformer.jpg

New transformer energised at Fort Augustus Substation

A 400kV Supergrid Transformer (SGT) and Reactor were successfully energised at SSEN’s Fort Augustus Substation this week enabling additional renewable generation to connect to the transmission network. SSEN Project Manager, Johannes Smit, said of the milestone: “The transformer was delivered in late October with final installation and commissioning taking place at the beginning of December. We have been in close contact with local residents to ensure that they are kept up to date during every stage of the process. To minimise any noise, we have increased the wall thickness of the transformer tanks for both the transformer and the reactor. Initial test results indicate that these measures have been effective.” Lead Project Manager, Archie Munro, said: “The Fort Augustus Substation was originally developed as part of the Beauly-Denny project. Since construction works commenced on the Beauly-Denny project there has been a significant increase in wind farm developments in the area. These additional reinforcements reflect our ongoing commitment to constantly upgrade and strengthen our network based on the needs of generators and our customers.”
BDSamplePictures-040 (2).jpg

Fully energised

The Beauly to Denny reinforcement has been "energised" and is now fully operational along its entire length.

Document downloads

Community liaison scheme
1241

Related Projects: Beauly - Denny

File Type: pdf
Published: 18 Aug 2016
Beauly-Denny Connecting Scotland's sustainable future
1242

Related Projects: Beauly - Denny

File Type: pdf
Published: 18 Aug 2016
NTS2-C Typical tower images
1243

Related Projects: Beauly - Denny

File Type: pdf
Published: 18 Aug 2016
Non-technical summary (NTS) text
1244

Related Projects: Beauly - Denny

File Type: pdf
Published: 18 Aug 2016
NTS1-A Project context plan
1245

Related Projects: Beauly - Denny

File Type: pdf
Published: 18 Aug 2016
NTS1-B Project context plan
1246

Related Projects: Beauly - Denny

File Type: pdf
Published: 18 Aug 2016
NTS2-A Photograph showing typical construction techniques
1247

Related Projects: Beauly - Denny

File Type: pdf
Published: 18 Aug 2016
NTS2-B Photograph showing typical construction techniques
1248

Related Projects: Beauly - Denny

File Type: pdf
Published: 18 Aug 2016
ELG - Joint Meeting Minutes - 16 August 2012
1249

Related Projects: Beauly - Denny

File Type: pdf
Published: 18 Aug 2016
ELG - Joint Meeting Minutes - 17 May 2012
1250

Related Projects: Beauly - Denny

File Type: pdf
Published: 18 Aug 2016
ELG Meeting - 23 February 2012
1251

Related Projects: Beauly - Denny

File Type: pdf
Published: 18 Aug 2016
ELG - Joint Meeting Minutes - 23 February 20112
1252

Related Projects: Beauly - Denny

File Type: pdf
Published: 18 Aug 2016
ELG Meeting - 17 November 2011
1253

Related Projects: Beauly - Denny

File Type: pdf
Published: 18 Aug 2016
ELG Meeting - 18 August 2011
1254

Related Projects: Beauly - Denny

File Type: pdf
Published: 18 Aug 2016
ELG Meeting - 16 June 2011
1255

Related Projects: Beauly - Denny

File Type: pdf
Published: 18 Aug 2016
ELG Meeting - 21 April 2011
1256

Related Projects: Beauly - Denny

File Type: pdf
Published: 18 Aug 2016
Terms of reference
1257

Related Projects: Beauly - Denny

File Type: pdf
Published: 18 Aug 2016
ELG Meeting - 19 August 2010
1258

Related Projects: Beauly - Denny

File Type: pdf
Published: 18 Aug 2016
ELG Meeting - 23 June 2010
1259

Related Projects: Beauly - Denny

File Type: pdf
Published: 18 Aug 2016
ELG Meeting - 28 April 2010
1260

Related Projects: Beauly - Denny

File Type: pdf
Published: 18 Aug 2016
ELG Meeting - 19 March 2010
1261

Related Projects: Beauly - Denny

File Type: pdf
Published: 18 Aug 2016
ELG Meeting - 27 January 2010
1262

Related Projects: Beauly - Denny

File Type: pdf
Published: 18 Aug 2016
Progress reports - July 2011
1263

Related Projects: Beauly - Denny

File Type: pdf
Published: 18 Aug 2016
Progress reports - June 2011
1264

Related Projects: Beauly - Denny

File Type: pdf
Published: 18 Aug 2016
Progress reports - April 2011
1265

Related Projects: Beauly - Denny

File Type: pdf
Published: 18 Aug 2016
Progress reports - February 2011
1266

Related Projects: Beauly - Denny

File Type: pdf
Published: 18 Aug 2016
Tummel Bridge CLG Note of Meeting 29 November 2013
File Type: pdf
Published: 03 Sep 2016
Tummel Bridge CLG Note of Meeting 25 October 2013
File Type: pdf
Published: 03 Sep 2016
Tummel Bridge CLG Note of Meeting 31 January 2014
File Type: pdf
Published: 03 Sep 2016
Tummel Bridge CLG Note of Meeting 28 March 2014
File Type: pdf
Published: 03 Sep 2016
Tummel Bridge CLG Note of Meeting 16 May 2014
File Type: pdf
Published: 03 Sep 2016
Tummel Residents Liaison Meeting Minutes 27 June 2014
File Type: pdf
Published: 03 Sep 2016
Tummel Residents Liaison Meeting Minutes 01 August 2014
File Type: pdf
Published: 03 Sep 2016
Tummel Bridge CLG Note of Meeting 29 August 2014
File Type: pdf
Published: 03 Sep 2016
Fort Augustus CLG Note of Meeting 01 April 14
File Type: pdf
Published: 03 Sep 2016
Fort Augustus CLG Note of Meeting 13 May 14
File Type: pdf
Published: 03 Sep 2016
Fort Augustus CLG Note of Meeting 13 July 14
File Type: pdf
Published: 03 Sep 2016
Fort Augustus CLG Note of Meeting 19 August 14
File Type: pdf
Published: 03 Sep 2016
Fort Augustus CLG Note of Meeting 08 October 14
File Type: pdf
Published: 03 Sep 2016
Fort Augustus CLG Note of Meeting 4 December 14
File Type: pdf
Published: 03 Sep 2016
Fort Augustus CLG Note of Meeting 05 March 2015
File Type: pdf
Published: 03 Sep 2016
Fort Augustus CLG Note of Meeting 07 May 2015
File Type: pdf
Published: 03 Sep 2016
Note of Meeting - FA CLG - 16 July 2015
File Type: pdf
Published: 03 Sep 2016
Note of Meeting - FA CLG - 17 September 2015
File Type: pdf
Published: 03 Sep 2016
Beauly CLG Note of Meeting February 14
File Type: pdf
Published: 03 Sep 2016
Beauly CLG Note of Meeting May 14
File Type: pdf
Published: 03 Sep 2016
Beauly CLG Note of Meeting June 14
File Type: pdf
Published: 03 Sep 2016
Beauly CLG Note of Meeting August 14
File Type: pdf
Published: 03 Sep 2016
Beauly CLG Note of Meeting December 14
File Type: pdf
Published: 03 Sep 2016
Beauly CLG Note of Meeting March 15
File Type: pdf
Published: 03 Sep 2016
Beauly CLG Note of Meeting January 15
File Type: pdf
Published: 03 Sep 2016
Beauly CLG Note of Meeting May 15
File Type: pdf
Published: 03 Sep 2016
Beauly CLG Note of Meeting July 15
File Type: pdf
Published: 03 Sep 2016
Beauly CLG Note of Meeting October 15
File Type: pdf
Published: 03 Sep 2016
Beauly CLG Note of Meeting November 15
File Type: pdf
Published: 03 Sep 2016
Beauly CLG Note of Meeting August 15
File Type: pdf
Published: 03 Sep 2016
Beauly CLG Note of Meeting March 16
File Type: pdf
Published: 03 Sep 2016

Local People

Neil Anderson
  • Title: Community Team Manager
  • Email: neil.anderson@sse.com
  • Telephone: 01738 516529
  • Mobile: 07500 912506
  • Address: Inveralmond House, 200 Dunkeld Road, Perth, PH1 3AQ
Robin Cameron
  • Title: Land Manager
  • Email: robin.cameron@sse.com
  • Mobile: 07500 912921
  • Address: Inveralmond House, 200 Dunkeld Perth, PH1 3AQ

Local Businesses

SP Energy Networks
  • Scottish Power Energy Networks (SPEN) is the distribution network operator for central and southern Scotland, Merseyside and North Wales. It is also the Transmission Owner for the south of Scotland.
  • Address: www.spenergynetworks.co.uk
Balfour Beatty
  • Balfour Beatty’s power transmission and distribution teams work with regional, national and international electricity network owners and operators to provide technical engineering solutions.
  • Address: www.balfourbeatty.com

Sign up for project updates

Keep informed with all that's happening on this project