Location: Highland

Contact Details

Liaison Manager

Neil Anderson
Title: Community Team Manager
Telephone: 01738 516529
Mobile: 07500 912506
Address: Inveralmond House, 200 Dunkeld Road, Perth, PH1 3AQ

Land Manager

Kenneth Morton
Title: Land Manager
Telephone: 01463 728381
Address: 10 Henderson Road, Inverness, IV1 1SN
Status: Early Development

Latest

About the project

The aim of the project is to reinforce the existing Fort Augustus Substation through the installation of new buildings and equipment.

The project comprises of the following key elements:

  • Expansion of the existing substation footprint
  • Construction of three new buildings that will house electrical switchgear
  • The construction and connection of four new transformers and reactor units
  • Construction of new, overhead aluminium structures (busbars) and underground connections within the expanded substation footprint; and
  • The relocation and removal of existing substation equipment

Why is the project required?

The requirement to reinforce the Fort Augustus Substation has been triggered following an increased demand of electrical generators requesting to join the transmission network.

As the transmission licence holder in the north of Scotland we have a duty under Section 9 of the Electricity Act 1989 to facilitate competition in the generation and supply of electricity. We have obligations to offer non-discriminatory terms for connection to the transmission system, both for new generation and for new sources of electricity demand.

The data in this map is provided for indicative purposes only and may be subject to change. Scottish Hydro Electric Transmission plc do not accept responsibility for its accuracy, completeness or validity. The data should not be copied, reproduced or utilised externally without permission.

Who is Scottish and Southern Electricity Networks?

Scottish and Southern Electricity Networks is the trading name of Scottish and Southern Energy Power Distribution Limited, Scottish Hydro Electric Transmission plc, Scottish Hydro Electric Power Distribution plc and Southern Electric Power Distribution plc.

How are Transmission network upgrades paid for?

Investments in projects are made by SHE Transmission plc. Electricity transmission companies are authorised to recover the costs of such investments through 'use of system' charges which are levied by National Grid Electricity Transmission plc on generators and suppliers of electricity. Suppliers recover their costs from all electricity customers. In order to protect the interests of customers, the transmission companies have to demonstrate to the energy regulator, Ofgem (Office for Gas and Electricity Markets) that proposed investments are necessary, are efficient and are economical so that the charges which are ultimately levied on all electricity customers are justified.
This means SHE Transmission is subject to a funding mechanism established by Parliament and regulated by Ofgem. Cross subsidies between different businesses in the SSE group is not permitted.

How are our proposals scrutinised?

The Scottish Ministers are responsible for determination of applications submitted under Section 37 of the Electricity Act 1989. Both statutory consultees and members of the public have the right to submit their representations on the application. All representations will be considered by Scottish Ministers in their determination of the application.
The Office for Gas and Electricity Markets (Ofgem), as the regulator, has to approve all investment so project proposals are developed under license conditions.
Preferred route corridors chosen will comply with revised ‘Holford Rules’ which are the recognised industry approach to routeing overhead lines amended to reflect Scottish circumstances.

How and to what extent are electricity consumers' interests considered?

We are regulated by the Office for Gas and Electricity Markets (Ofgem), the regulator responsible for representing consumers' interests. Electricity consumer interests are therefore one of our key drivers and this is enshrined in our statutory duties under the Electricity Act.
In particular we have a statutory duty to develop, maintain and operate an efficient, economic and co-ordinated transmission system. Since the costs of these projects will ultimately be paid for by electricity consumers, we have a responsibility to take cost into account with due weighting in a comparison against other important factors.

What is the transmission network?

It’s the highest voltage electricity network in the UK – the ‘motorway network’ of the energy world. It transmits large quantities of electricity over long distances via wires carried on a system of mainly metal towers (pylons) and large substations. Transmission voltages in Scotland are 132kV, 275kV and 400kV. Larger generation schemes usually connect to the Transmission system.

The lower voltage parts of the system are called distribution networks. In Scotland, these local networks operate below 132kV whereas in England the distribution network includes 132kV. 

Proposal of Application Notice

SSEN Project Development Manager, Joyce Wilson, said: “We are developing proposals to reinforce the electricity transmission infrastructure in Fort Augustus substation. Following on from our consultation events last year, we have now submitted a Proposal of Application Notice to The Highland Council. We are hosting a further public consultation event on 19th July and would encourage all interested stakeholders to come along and provide their feedback before a full planning application is submitted.”

Document downloads

Information Boards - September 2016

Related Projects: Fort Augustus - Skye, Fort Augustus Substation Reinforcement

File Type: pdf
Published: 15 Sep 2016
Fort Augustus Substation Brochure

Related Projects: Fort Augustus - Skye, Fort Augustus Substation Reinforcement

File Type: pdf
Published: 15 Sep 2016

Local People

Neil Anderson
  • Title: Community Team Manager
  • Email: neil.anderson@sse.com
  • Telephone: 01738 516529
  • Mobile: 07500 912506
  • Address: Inveralmond House, 200 Dunkeld Road, Perth, PH1 3AQ
Kenneth Morton
  • Title: Land Manager
  • Email: kenneth.morton@sse.com
  • Telephone: 01463 728381
  • Address: 10 Henderson Road, Inverness, IV1 1SN

Sign up for project updates

Keep informed with all that's happening on this project