Gremista GSP (Grid Supply Point) and 132kV Connection

Type:
New GSP (Grid Supply Point)
Location:
Shetland
Rating:
132kV

Building a new grid supply point at Gremista and connecting to Kergord substation, delivering secure power and supporting future growth.

Register for Project Updates

Overview

Status: Construction Phase

Stage 4 of 5

5 joined together arrow shapes in a row each labelled with the stage number. The first 4 arrows are highlighted in filled green shades to indicate the project is at stage 4 of 5
  • Stage 1: Project Assessment: (Completed)

    During the Project Assessment stage, we’re committed to evaluating potential project strategies. At this stage, we provide information about the proposed project plans on our website for stakeholders to review and provide feedback on, as well as holding in-person events within the local community demonstrating our collaborative approach to the project's development.

  • Stage 2: Early Development: (Completed)

    During Early Development, we concentrate on refining the project details, based on our initial assessment of key environmental, technical, and economic factors to identify the best performing approach. We would like to gain further input from communities through accessible in-person and in some cases online consultations, which are crucial in refining our plans and strategies before advancing to the application stage.

  • Stage 3: Project Refinement: (Completed)

    The Project Refinement stage is where we finalise project plans and submit the required planning applications to the relevant planning authorities. Communities and other key stakeholders can provide feedback directly to the appropriate body such as their local council and constituent representatives.

  • Stage 4: Construction Phase: (In progress)

    Within the construction phase we mobilise our workforce, contractors, and necessary equipment to begin construction. We maintain open channels of communication, allowing communities and stakeholders to submit feedback on the construction activities to our dedicated Community Liaison Managers, ensuring ongoing engagement to any thoughts or concerns while we carry out work in the area.

  • Stage 5: Operational Phase:

    At this final stage, the project successfully moves into the operational phase, with the surrounding environment restored to its original state or better. Our Community Liaison Mangers continue to be available to address any questions or concerns, ensuring a lasting positive impact and strong community relations even after the construction activities conclude.

About the Project

The project consists of:

  • A new 132/33kV Grid Supply Point (GSP) at Gremista with a 22km double circuit 132kV connection, which will be a combination of both underground cable and overhead line, between Gremista GSP and Kergord substation.

Find Out More About Kergord HVDC Station

Why is the Project Required?

The Gremista GSP, and the 132kV connection to the Kergord substation will connect Shetland to the GB electricity network for the first time. The GSP will also provide the connection point for a new battery to help support Shetland’s ongoing energy requirements and enable Lerwick Power Station to move to standby mode, further supporting the decarbonisation of Shetland.

 

Community Engagement

Throughout the life of our projects, we aim to work positively with local communities and keep people informed about what we are doing. This is particularly important when we are developing a proposal and we want to understand what local people think about our plans.

We endeavour to take the time to discuss proposals with local community councils, encourage engagement from the wider community and listen to the feedback we receive.

We will do our best to answer any questions and address issues or concerns that are raised with us.

When our project progresses into construction, we will continue working closely with the local community to ensure that our work has as little impact on the lives of those living and working in the area and as many long term positive effects as possible.

p3912257_2041092836_4.jpg

How we’re embracing artificial intelligence (AI)
We intend to use AI to assist our experienced teams in the analysis of your feedback, so we can categorise key points raised more quickly. You can learn more about how we’re utilising AI on this dedicated web page.

Back to top

Project Contacts

Recite me

To support everyone online, we provide accessibility and language options on our website through ‘Recite me’. The accessibility and language support options provided by ‘Recite me’ include text-to-speech functionality, fully customisable styling features, reading aids, and a translation tool with over 100 languages, including 35 text-to-speech. Please select “Accessibility” on our website to try out our inclusive toolbar.

To make use of this function please click on the 3 'A's' button at the bottom left of the website.
Recite me logo.