First step for Caithness electricity project upgrade
The first element of the northern part of the Caithness-Moray transmission reinforcement has been energised successfully at Dounreay Substation.
-
SSEN commit to review options for Beauly-Blackhillock-Kintore reinforcement if project returns in future years
Following the publication of National Grid’s Networks Options Assessment report, which included a change to the recommendation for the proposed...
-
Ploughing on with Caithness-Moray cable
A key milestone for the Caithness-Moray transmission project was reached this week following the successful clearance of rocks and boulders along the proposed route for the subsea cable.
-
“On your sparks, car kit, charge!”
- Working with Communities
SSEN team helps local schools tackle electric car challenge
-
Record year for connections increases total renewable capacity in the north of Scotland to over 4.5GW
- Connections
The electricity transmission network in the north of Scotland is now supporting over 4.5GW of renewable electricity following the recent successful connections of Bienneun (Blue Energy, 108.8MW) and Bhlaraidh (SSE Renewables, 108MW) wind farms...
Page 145 of 156