Overview
Overview
We’re rebuilding a section of the existing New Deer-Peterhead 400kV overhead line to increase its capacity and enable the connection of offshore wind generation.
About the Project
We’re leading on the delivery of critical infrastructure projects to power change in the UK and Scotland. To support the delivery of 2030 offshore wind targets set by the UK and Scottish governments, and to power local communities, we need to upgrade our existing network. In some key areas, we need to develop entirely new infrastructure.
The Netherton Hub is a strategic development proposed for a site located near Longside to the west of Peterhead.
During the consultation for the Netherton Hub in February and May 2024, we outlined that the proposed 400kV substation at Netherton Hub would need to be connected to other parts of our transmission network.
Following publication of “Beyond 2030” report, we have now reviewed how the overhead line connection will be developed and built to maximise energy transfer between the proposed 400kV substation in Netherton Hub and Peterhead substation. This will now be facilitated by this overhead line rebuild project. The components include:
- Rebuild a section of the existing New Deer-Peterhead 400kV overhead line between the chosen tie-in connection point and the Peterhead 400kV substation
- Install a temporary overhead line circuit to facilitate the transfer of the connection from the existing New Deer-Peterhead 400kV overhead line to the newly built section of the line.
- Remove the redundant overhead line towers on the section between the selected tie-in option and the Peterhead 400kV substation.
A separate but related project involves the proposed overhead line tie-in connection of the existing New Deer-Peterhead 400kV line into Netherton Hub.
The overhead line tie-in project is required to connect the proposed 400kV substation within the Hub to the existing transmission network. Follow the link below to find more information about the tie-in project.
Beyond 2030
To deliver energy security and net zero, further additional investment in new low carbon electricity generation and the enabling electricity transmission network infrastructure will be required across Great Britian, including the north of Scotland.
In March 2024, the independent National Energy System Operator’s (NESO) published its ‘Beyond 2030’ report, which confirmed the need for several new, replacement and upgraded transmission infrastructure projects in the north of Scotland. In December 2024, Ofgem approved the next phase of regulatory funding to take these projects through the development phase. This project is part of these additional investments and will soon be subject to extensive public consultation and engagement to help inform the development.
Community Engagement
Throughout the life of our projects, we aim to work positively with local communities and keep people informed about what we are doing. This is particularly important when we are developing a proposal and we want to understand what local people think about our plans.
We endeavour to take the time to discuss proposals with local community councils, encourage engagement from the wider community and listen to the feedback we receive.
We will do our best to answer any questions and address issues or concerns that are raised with us.
When our project progresses into construction, we will continue working closely with the local community to ensure that our work has as little impact on the lives of those living and working in the area and as many long term positive effects as possible.

How we’re embracing artificial intelligence (AI)
We intend to use AI to assist our experienced teams in the analysis of your feedback, so we can categorise key points raised more quickly. You can learn more about how we’re utilising AI on this dedicated web page.
Project Updates
Featured updates
Featured updates for this project
Project updates
Documents
Project Documents
-
All Alignments
- Type:
- Date:
- 28 February 2025
- Size:
- 6.2 MB
These maps provide information to our stakeholders about the alignment options within the project.
-
Potential Alignment Option R2
- Type:
- Date:
- 28 February 2025
- Size:
- 6.3 MB
These maps provide information to our stakeholders about the potential alignment options within the project.
-
Potential Alignment - large scale map
- Type:
- Date:
- 28 February 2025
- Size:
- 13.5 MB
These maps provide information to our stakeholders about the alignment options within the project.
-
Rebuild Consultation booklet - Netherton Hub 400kV OHL
- Type:
- Date:
- 24 February 2025
- Size:
- 5.9 MB
This consultation booklet shows alignment options and our potential alignment for the rebuild component of the Netherton Hub 400kV Overhead Line Connection to New Deer and Peterhead project.
Consultation Documents – Alignment Selection
FAQs
FAQs
Recite me
To make use of this function please click on the 3 'A's' button at the bottom left of the website.