Overview
About the Project
We are proposing to construct and operate a new 132kV connection between the proposed Carn Fearna Wind Farm – located east of Garve in the northwest Highlands – and a proposed extension at our existing Corriemoillie substation. This consists of an approximately 7.5km single circuit overhead line supported by wooden poles and an approximately 3km underground cable.
Under our Network Operators Licence, this connection should be efficient, coordinated, and economic, whilst having the least possible impact on the environment.
Carn Fearna Wind Farm
We are required to connect the proposed Carn Fearna Wind Farm to the electricity transmission network by the contracted connection date, in accordance with Schedule 9 of the Electricity Act 1989.
The proposed 85-megawatt onshore wind farm will have a maximum of 9 turbines. Further information is available on the developer's website:
Find out more about Carn Fearna Wind Farm
Community Engagement
Throughout the life of our projects, we aim to work positively with local communities and keep people informed about what we are doing. This is particularly important when we are developing a proposal and we want to understand what local people think about our plans.
We endeavour to take the time to discuss proposals with local community councils, encourage engagement from the wider community and listen to the feedback we receive.
We will do our best to answer any questions and address issues or concerns that are raised with us.
When our project progresses into construction, we will continue working closely with the local community to ensure that our work has as little impact on the lives of those living and working in the area and as many long term positive effects as possible.
How we’re embracing artificial intelligence (AI)
We intend to use AI to assist our experienced teams in the analysis of your feedback, so we can categorise key points raised more quickly. You can learn more about how we’re utilising AI on this dedicated web page.
Project Updates
Featured updates
Featured updates for this project

Carn Fearna Wind Farm Connection Alignment Consultation Event
Project updates
Documents
Alignment Selection Documents
-
Carn Fearna Alignment Consultation Document.pdf
- Type:
- Date:
- 04 June 2025
- Size:
- 16.1 MB
This Alignment Consultation Document (and associated appendices/maps) explains the project need and summarises the process which has been followed to arrive at the optimal alignment. It forms part of the consultation exercise which provides all interested parties with the opportunity to provide feedback.
-
Carn-Fearna-Poster.pdf
- Type:
- Date:
- 02 June 2025
- Size:
- 485.3 KB
This material provides information to our stakeholders about the project and/or consultation events.
-
CARN-FEARNA-Consultation Booklet.pdf
- Type:
- Date:
- 02 June 2025
- Size:
- 24.5 MB
This document provides information to our stakeholders about the project and was provided during our consultation in June 2025.
Route Selection Documents
FAQs
FAQs