What is Queue Management?

To support the connection of projects to the electricity network to achieve targets for Net Zero, on 13 November 2023, Ofgem approved the Connection and Use of System Code (CUSC) Modification ‘CMP376: Inclusion of Queue Management process within the CUSC’

This means from 27 November 2023, Transmission Connection Offers will have queue milestones added to their contracts to ensure projects are actively progressing towards their connection to the network. This addition will provide National Grid Electricity System Operator (NGESO) the ability to terminate projects which are not progressing against the milestones and remove them from the connections queue.

If a Customer still requires a Transmission connection following termination, they must reapply for their connection capacity.

Steel Tower

How will Queue Management impact our customers?

Queue Management will apply to all new applications, any new modification applications and new agreements to vary for parties with a CUSC Construction Agreement.*

*except BEGAs, DNOs associated with Distributed Generation (DG) or demand customer connections; and shared works for non-radical offshore connections and any Offshore Transmission System User Development Works (OTSDUW).

Customers with a contracted Completion Date of 2 years or more, or projects not progressing with a Completion Date of less than 2 years, will receive a letter from the NESO, outlining two options: 

Option 1:

Customer may submit a Modification Application for a new Completion Date

➢ Queue Management milestones will be added to their agreement, aligned to the new allocated Completion Date in a forward-looking manner.

➢ A revised Completion Date will be provided by the Transmission Operator (TO) to the NESO who will update the agreement with the Customer.

➢ A standard Modification Application fee would be charged for this option.

Option 2:

NESO will issue an Agreement To Vary (ATV) to modify Construction Agreement and add Queue Management milestones aligned to their existing Completion Date.

➢ Milestones will be added in a forward-looking manner.

Customers will need to decide which option to follow within 6 months of the Queue Management Implementation Date and TOs and NESO will ensure these changes are managed efficiently. Where the customer does not submit a Modification Application within 6 months of the Implementation Date or does not accept the Modification Offer made in response to this, NESO will issue an ATV as soon as practicable after the 6 months or failure to accept.

Useful Information

  • Ofgem Decision

    Ofgem are the energy regulator for Great Britain and have announced the changes to the customer connection process, if you would like more information please read their Queue Management decision announcement.


  • NESO Overview of Queue Management

    Please read the NESO Queue Management information page to find out more about the decision.


  • NESO QM Customer Guide

    NESO, is the electricity system operator for Great Britain and you can read their Customer Guide for more information on the Queue Management process.


Milestones

Milestones will be added to the Customer’s construction agreement and will be dated, counting back from the contracted Completion Date provided by NESO.

Milestones will be applied to track the Customer’s progress towards completion. If you’re a customer in the connections queue, you can use the NESO milestone calculator to identify key dates your project needs to meet to keep your place in the connections queue.

Further information on Milestones can be found on the
NESO website.

Exceptions

It has been agreed that there may be exceptional circumstances that are beyond Customers' control which may lead to projects delays. If a Customer believes this applies to them, they must contact NESO and provide evidence than an exception applies.

 

Terminations

Customer's must provide evidence that they have met their Queue Management milestones to NESO prior to reaching their milestone date.

For Milestones 1 – 3, failure to provide the requested documentation will result in the NESO terminating the Customer’s Construction Agreement.

For Milestones 5 – 8, NESO have the right to terminate the Customer’s construction agreement. This will be determined by an internal NESO escalation process. More information of which can be found in NESOs Queue Management Customer Guide.

Appeals

For any queries relating to appeals and disputes, please consult section 7 of the CUSC.

For disputes on specified items within the Construction Agreement, please consult Clause 6 of the Construction agreement.

Appeals/Disputes should be treated as a last resort and any grounds for appeal must be clearly linked to the Milestone evidence.

SSEN Transmission Beauly

Contact Information

If you have any questions on what this means for you, or you would like any extra information, please contact your Contract Manager at NESO or visit their website.