Beyond 2030: Powering Scotland's Future
Investing in the next generation of transmission infrastructure
The independent National Energy System Operator’s (NESO) ‘Pathway to 2030’ published in 2022 (and then refreshed in 2023) outlined an electricity network design called the Pathway to 2030 Holistic Network Design (HND). The HND outlined the network needed to connect some 23 GW of offshore wind power by 2030. The HND programme only gets Great Britain so far in its journey towards net zero, including the target outlined in the British Energy Security Strategy of 50 GW of offshore wind by 2030.
In March 2024, NESO published its 'Beyond 2030' report, responding to the government’s request to build on the HND design to connect more offshore wind. The resulting so-called HND ‘follow-up exercise’ in Beyond 2030 includes additional network upgrades and new capacity to connect a further 21 GW of offshore wind.
For the north of Scotland, Beyond 2030 included the next phase of ScotWind and confirmed the need for several new, replacement and upgraded transmission projects to be delivered by 2035, representing a potential investment of over £5 billion.
These projects are essential to:
- Enable additional ScotWind connections.
- Support the deployment of homegrown, low-carbon electricity.
- Strengthen the UK’s energy security and progress toward net zero.

New Deer
We’re extending the New Deer substation to increase capacity and enable more renewable power to enter the network.
This project will deliver:
- an extension of the substation at New Deer
- approx 3km of new 400kV underground cable between New Deer and Greens
Expected completion date: 2030
There are 2 parts to this project:
Peterhead, Persley to Kintore
We’re strengthening the grid in Scotland's Northeast and around Aberdeen by increasing capacity of existing transmission linesfrom 275kV to 400kV. This upgrade will help ensure security of supply of power to Aberdeen grid and helps support delivery of renewable energy generated by windfarms.
This project will deliver:
- 51km of re-conductoring and re-insulating of the overhead line between Persley to Kintore
- a new 400kV substation at Newmachar
- extension and tie-in of the network at Kintore
Expected completion date: 2029 - 2033
Shetland HVDC
Connecting the power generated off the east coast of Shetland to the mainland network to strengthen the grid
This project will deliver:
- a new HVDC converter station on Shetland
- approx 350km of HVCD subsea cable
- approx 35km of onshore cables
- a new HVDC converter station in Aberdeenshire
Expected completion date: 2034
Longside to Peterhead Upgrade
We’re increasing the capacity on existing 400kV transmission line between our Longside and Peterhead substations, allowing integration of the new substation as well as power sharing between east and west of our network.
This project will deliver:
- approx 11km of 400kV overhead line
Expected completion date: 2032
Dounreay to Spittal
We’re building a new 400kV line between Dounreay and Spittal to connect renewable energy generated from the N3 wind farm.
This project will deliver:
- a new 400kV substation in Dounreay
- approx 21km of 400kV overhead line
Expected completion date: 2034
Project page coming soon
Blackhillock, Cairnford to Kintore
We’re upgrading the line from 275kV to 400kV to allow more power to flow and relieve a bottleneck toward Kintore.
This project will deliver:
- a substation extension at Blackhillock
- a substation extension at Kintore
- a new 400kV substation at Cairnford
- approx 51km of new 400kV overhead line between Blackhillock and Kintore
Expected completion date: 2034
Project page coming soon
