Crarae 275kV Substation
- Type:
- Transmission reinforcement
- Location:
- Argyll & Bute
Building Crarae substation to support renewable energy connections, powering the future and ensuring energy security.
Overview
Status: Construction Phase
Stage 4 of 5
-
Stage 1: Project Assessment: (Completed)
During the Project Assessment stage, we’re committed to evaluating potential project strategies. At this stage, we provide information about the proposed project plans on our website for stakeholders to review and provide feedback on, as well as holding in-person events within the local community demonstrating our collaborative approach to the project's development.
-
Stage 2: Early Development: (Completed)
During Early Development, we concentrate on refining the project details, based on our initial assessment of key environmental, technical, and economic factors to identify the best performing approach. We would like to gain further input from communities through accessible in-person and in some cases online consultations, which are crucial in refining our plans and strategies before advancing to the application stage.
-
Stage 3: Project Refinement: (Completed)
The Project Refinement stage is where we finalise project plans and submit the required planning applications to the relevant planning authorities. Communities and other key stakeholders can provide feedback directly to the appropriate body such as their local council and constituent representatives.
-
Stage 4: Construction Phase: (In progress)
Within the construction phase we mobilise our workforce, contractors, and necessary equipment to begin construction. We maintain open channels of communication, allowing communities and stakeholders to submit feedback on the construction activities to our dedicated Community Liaison Managers, ensuring ongoing engagement to any thoughts or concerns while we carry out work in the area.
-
Stage 5: Operational Phase:
At this final stage, the project successfully moves into the operational phase, with the surrounding environment restored to its original state or better. Our Community Liaison Mangers continue to be available to address any questions or concerns, ensuring a lasting positive impact and strong community relations even after the construction activities conclude.
About the Project
We will be constructing a new 275kV substation at Crarae, located approximately 1.6km north west of Minard and upslope of the existing Crarae 132kV Substation. The project will include the construction of three steel lattice towers to support overhead line conductors, to connect the new Crarae Substation into the recently completed Inveraray to Crossaig 275kV Overhead Line.
The existing substation is now of insufficient size and capacity to accommodate the works required to connect the contracted renewable generation in Argyll, therefore a new substation is required which will operate at 275kV.
Find Out More About Inveraray - Crossaig 275kV Overhead Line
Why is the Project Required?
Due to the projected increase in renewable energy generation in Argyll, a need has been identified for the upgrade and reinforcement of the electricity transmission network on the Argyll peninsula, to ensure security of electricity supply and support the transition to Net Zero.
The replacement Inveraray - Crossaig Overhead Line has been completed at a higher voltage of 275kV. As increased renewable generation requires connection to the electricity network, and the operating voltage is required to increase to 275kV, four 132kV substations along the route need replacing to accommodate this.
Find Out More About Argyll and Kintyre 275kV Substations

Community Engagement
Throughout the life of our projects, we aim to work positively with local communities and keep people informed about what we are doing. This is particularly important when we are developing a proposal and we want to understand what local people think about our plans.
We endeavour to take the time to discuss proposals with local community councils, encourage engagement from the wider community and listen to the feedback we receive.
We will do our best to answer any questions and address issues or concerns that are raised with us.
When our project progresses into construction, we will continue working closely with the local community to ensure that our work has as little impact on the lives of those living and working in the area and as many long term positive effects as possible.

How we’re embracing artificial intelligence (AI)
We intend to use AI to assist our experienced teams in the analysis of your feedback, so we can categorise key points raised more quickly. You can learn more about how we’re utilising AI on this dedicated web page.
Project Updates
Featured updates
Featured updates for this project
Construction Project Update
SSEN Transmission launches first Argyll Community Benefit Fund worth £3.2m
Project updates
-
Construction Project Update
Construction at the new Crarae 275kV Substation continues to progress well, with major milestones achieved in the bulk earthworks programme and peat restoration works. The next phase of the project will see foundation works commence across the site, supporting the continued development of the new substation.
We appreciate the continued support and patience of the local community as we progress with this important infrastructure project, which will help strengthen the electricity transmission network and support the integration of renewable energy across the region. If you have any queries relating to these works please contact our Community Liaison Manager for more information. -
SSEN Transmission publishes new economic analysis highlighting transformative growth potential of £29bn grid investment programme
We have today published a new economic report setting out the significant economic benefits associated with our planned £29bn investment in new and upgraded electricity transmission infrastructure across the north of Scotland.
The report, titled ‘Re‑energising the North: Transforming Scotland’, provides an update on our previously outlined economic analysis on plans to invest billions in mission-critical grid infrastructure, providing further insight into the scale of economic opportunity associated with the investment programme.
The report reaffirms our programme as one of the largest private infrastructure investments in Scotland’s history, with around £29bn of planned investment across the north of Scotland in the next five years, and it details the extent of the economic opportunity across the region.Using advanced economic modelling to analyse the impact of clean power infrastructure investment, the report’s findings conclude that our investment:
- Will support up to 10,000 jobs in the north of Scotland, and 24,000 across Scotland;
- When added to investment by other transmission operators and investment in generation will add around £60bn to UK economic output - with the Scottish economy up to 3% larger over the long term;
- Will deliver long-term improvements in productivity, wages and economic resilience, with employees moving into higher-value roles and key sectors expanding permanently; and
- Will create unique opportunities for Scottish suppliers, businesses and communities across multiple sectors, including forestry, peatland restoration, aggregates and concrete too.
The findings highlight the importance of ensuring that the benefits of investment are felt locally, with thousands of skilled jobs, increased supply chain activity, and investment flowing into communities across the north of Scotland.
Read the full News and Views article to find out more. -
SSEN Transmission launches first Argyll Community Benefit Fund worth £3.2m
We have officially launched our first Community Benefit Fund in Argyll, with £3.2 million available to support communities closest to a major new electricity infrastructure project in the region.
The Argyll and Kintyre Local Fund will focus on communities neighbouring the Argyll and Kintyre 275kV Reinforcement Project – a significant programme of electricity network upgrades designed to strengthen Argyll’s energy infrastructure, improve security of supply and support the transition to clean power.
One of the first funds of its kind to be established under new UK Government guidance, the £3.2m fund has been created to ensure that communities hosting vital new transmission infrastructure benefit directly from this investment. Funding will be available across ten community council areas located closest to the Argyll and Kintyre 275kV project route.
The first Argyll-focused local community benefit fund is now inviting applications from projects and groups based across Argyll, with the closing date for the fund set for Tuesday 4 August.
The launch of the fund follows on from a call out for a local decision-making panel last month, who will play a key role in guiding how the funding will be distributed. The panel, which will be made up of community members from across Argyll alongside one representative from SSEN Transmission, will be in place by the closing of the first round of applications for the first round of community benefit funding.
For more information about the fund and details on how to apply, visit the Argyll and Kintyre 275kV Local Fund page.
-
Festive Site Closure Dates 2025
Construction works will pause for the 2025 festive period with sites closing from 19 December 2025 until 5 January 2026. Although the sites will be closed for all construction workers during this period security will remain in place.
We wish our local communities a safe and happy festive break.
-
Crarae Substation - Project update October 2025
We are pleased to share that earthworks activities at the Crarae Substation site commenced at the end of August 2025. This marks a significant milestone in the construction phase of the project.
The earthworks involve preparing the site platform through cut and fill operations, integrating sustainable drainage systems (SuDS) to support the development of the new 275kV substation. These activities are essential to ensure the site is ready for the next stages of construction, including the installation of steel lattice towers and electrical infrastructure.
We remain committed to working closely with the local community throughout the construction process to minimise disruption and maximise long-term benefits. if you have any questions relating to this update please contact the project community liaison manager
-
Argyll and Kintyre 275kV Local Fund
The Argyll and Kintyre 275kV Strategy is a series of projects aimed at increasing our network capability across Argyll and Kintyre, enabling the exporting of electricity to the wider GB transmission network.
The Community Benefit Fund associated with these projects is aimed specifically at communities who are situated close to the infrastructure and will be developed in partnership with these communities.
To find out more please click here -
We're here to lend a helping hand
We are committed to supporting the communities in the north of Scotland where we operate, both now and in the future. As part of our ongoing efforts to make a difference and have a positive impact on local communities, we are proud to offer volunteering days to local groups and charities, particularly in the areas that host our electricity infrastructure or where our proposed projects are located.
This month, we’re excited to announce the launch of our new Volunteering Webpage, designed to make it easier for local communities to request volunteering support from us. To request our help, simply complete the ‘Volunteering Nomination Form’ linked at the bottom of our new webpage. Please note, as our team works on a voluntary basis, it may take us some time to coordinate our people and match them with opportunities. We kindly ask for your patience as we work to keep up with volunteering demand.
Thank you for considering SSEN Transmission as a partner in your community efforts. Together, we can leave a positive, lasting legacy and help transform communities across the north of Scotland.
-
Project update - Forestry works complete
We recently completely forestry works in December for our Crarae substation project. Balfour Beatty is our Principal Contractor for this project, at present we are working jointly to plan the mobilization activities aiming for spring 2025 and likely that construction will start thereafter. If you have any questions relating to this project please contact the project community liaison manager - Caitlin.quinn@sse.com -
Meet the buyer event - thank you
On behalf our principal contractor Balfour Beatty, the SSEN Transmission project team would like to thank everyone who took the time to visit us at our public event event this week.
Over 30 businesses attended our meet the buyer event with others sending enquries via phone and email. This was really beneficial for us to understand all the local businesses that are available in the local area.
If anyone has any further questions regarding this event please email the community liaison manager for these projects.
Meet the Buyer Event
SSEN Transmission will soon begin construction on the Argyll and Kintyre 275kV substations.
As part of these projects and our ongoing commitment to ensure that where possible, opportunities are advertised locally in the first instance, we are welcoming local businesses to attend an informal drop-in meeting to engage with our principal contractors and to exchange details to discuss the possible opportunities for the local supply chain.
These projects have the potential to create local business and employment opportunities in the following fields: Accommodation, fencing, skip hire, catering, cleaning services, plant hire, general operations workers, groundworkers, electricians and more. We would encourage any relevant local businesses to attend these events and discuss what possible business opportunities there are with our principal contractors.
This drop in event will be held at the following date and location;
An Suidhe, Crarae, Craig Murrail substations:
Wednesday 24 January 2024, 2–6pm
Furnace Village Hall, Furnace,
Inveraray, Argyll, PA32 8XN -
Argyll and Kintyre project - Final Needs Case consultation
The GB electricity regulator Ofgem has provisionally approved SSEN Transmission’s proposals to upgrade the electricity transmission network in Argyll and Kintyre.
In its minded-to approve consultation on SSEN Transmission’s Final Needs Case, Ofgem has recognised the clear need for the Argyll and Kintyre Reinforcement Strategy, which will secure future electricity supplies in the area and enable the connection of new renewable electricity generation in the region. It will support the connection of at least 970MW of new renewable electricity generation, enough to power more than 500,000 homes.
As well as supporting the transition to net zero emissions, the investment will also help secure the country’s future energy independence by removing the country’s dependence and price exposure to volatile, global wholesale gas markets, with the deployment of low carbon, affordable, renewable electricity generation.The project will also unlock hundreds of skilled jobs throughout the construction phase and provide a significant economic boost to local and national economies, all while playing a key role in supporting the transition to net zero emissions and helping secure the country’s future energy independence.
Ofgem’s minded-to decision and consultation on the Argyll and Kintyre Final Needs Case can be found here: https://www.ofgem.gov.uk/publications/argyll-and-kintyre-project-final-needs-case-consultation.
As a stakeholder led business SSEN Transmission would like to encourage all interested and relevant stakeholders to contribute to this important consultation before the closing date on 15th of September 2023. -
Argyll and Kintyre 275kV Substation Town and Country planning consent granted
We recently recieved town planning country planning consent for An Suidhe, Crarae, Craig Murrail and Crossaig North substations . We are currently still awaiting decision on our Section 37 applications for these projects from Scottish ministers. Once we receive notification of their outcome we will provide an update to public stakeholders and also publish this information and next steps on our project webpage. -
Crarae Subsation S37 update to noise assessment and temporary access track layout January 2023
The following chapters and annexes of the Environmental Appraisal have been updated:
- Chapter 8 – Updated noise emission data for proposed plant – no material change to outcome of assessment
- Chapter 10 – To remove reference to replanting at the site (site to be reinstated as bog/mire habitat)
- Annex S – Updated plant noise spectrum and modelling plots
Figures 1b and 2 have also been amended with some minor changes to the proposed temporary access track layout in the vicinity of the existing substation.
-
Crarae Substation Town and Country Planning Application
A planning application has been submitted by Scottish Hydro Electric Transmission plc (operating and known as SSEN Transmission) for detailed planning permission under The Town and Country Planning (Scotland) Act 1997 for the Erection of High Voltage Electricity Substation and Formation of Associated Access, Landscaping, Drainage and Means of Enclosure (the Crarae Substation), approximately 1.6km north west of Minard, Argyll and Bute.
The Proposed substation forms part of SSEN Transmission’s Argyll and Kintyre Strategy and is required to manage the transportation of renewable energy generation from Argyll to the wider electricity network. The substation would connect into the existing 275 kV Overhead Line (OHL) from Inveraray to Crossaig. An Environmental Appraisal (EA) has been carried out as a non-statutory assessment to allow appropriate environmental management and mitigation measures to be identified.
If you wish to view the documents relating to this submission you can do so by clicking on the project documents section of this webpage.Written comments may be made by e-mail: planning.hq@argyll-bute.gov.uk or Argyll and Bute Council, Development Management, Kilmory Castle, Lochgilphead, Argyll, PA31 8RT by 24.02.2023.
-
Crarae Substation Section 37 planning application
SSEN Transmission have submitted their application for consent to the Scottish Ministers for consent under Section 37 of the Electricity Act 1989 1989 to install and keep installed approximately 45m of 275 kV overhead line supported on two new steel towers to connect the proposed 275 kV Crarae Substation via downleads to the existing 275kV Inveraray to Crossaig overhead line and to install and keep installed approximately 285m of realigned 275kV overhead line supported with one new steel tower in the vicinity of the existing 132 kV Crarae Substation. Temporary overhead line diversions with three towers and temporary overhead line diversions with two towers or masts for a period of no more than three years will also be required, approximately 1.6 km north west of Minard in the Argyll and Bute local authority area.
Any representations on the application may be submitted to Scottish Ministers via the Energy Consents Unit website at www.energyconsents.scot using reference ECU00004664. All representations should be made such that they are received by Scottish Ministers not later than 30th January 2023 although Scottish Ministers may consider representations received after this date. As a result of a statutory objection from the relevant planning authority, or where Scottish Ministers decide to exercise their discretion to do so, Scottish Ministers can also cause a Public Inquiry (PI) to be held.
Should you wish to view the documents contained within our Section 37 application in full, these are available within the project documents section of this webpage.
-
Argyll and Bute Information Sharing Webinar 2022
Please click to view our 2022 Argyll and Bute regional webinar where some of the SSEN team have given an overview of ongoing and upcoming projects across the area. -
Submission of our Initial Needs Case for the Argyll and Kintyre 275kV Strategy
We have submitted to the energy regulator, Ofgem, robust proposals to reinforce the Argyll transmission network from 132kV to 275kV operation. At an estimated cost of around £400m, this investment is being taken forward as part of the SSE Group’s Net Zero Acceleration Programme, which will see £12.5bn invested in the five years to 2026, or £7m every day. SSEN Transmission alone expects to invest around £4bn over this period as it delivers a network for net zero emissions. The Argyll 275kV strategy is required to support the connection of several new renewable electricity generation schemes across Argyll and to transport that power to areas of demand across Scotland and beyond. It will support the connection of at least 560MW of new renewable electricity generation, enough to power more than 500,000 homes. -
Pre- Application Consultation Closed
Thank you to those who participated in our Winter 2021 online pre-application consultation and provided feedback on our proposals for the Argyll and Kintyre 275kV Substations project. Our consultation period closed on 10th January and all feedback received will be collated, reviewed and included in the Pre-Application Consultation (PAC) Report which will accompany the Planning Applications submission to Argyll and Bute Council in Spring 2022. As part of our consultation we held a webinar on 14th December 2021, inviting statutory consultees, community council members and local elected members to discuss our proposals ahead of our planning application process. Please see a recording of the webinar adjacent for more information. -
Argyll and Bute Information Sharing Webinar
On Wednesday 17th March 2021, SSEN Transmission hosted an Argyll and Bute Information Sharing Webinar, to provide local stakeholders with an interest in future electricity network plans for Argyll and Bute the chance to join us to hear about our stakeholder-led plans for the future and receive an update on the current construction and operation activities in the region. For those who were unable to attend, we have uploaded a recording of the session which you can view by clicking on the adjacent video.
Documents
Argyll and Kintyre Substations Documents
-
Argyll and Kintyre Mailer
- Type:
- Date:
- 27 October 2023
- Size:
- 161.3 KB
This document provides an update to our stakeholders about the project.
-
Argyll and Kintyre Reinforcement Strategy LOTI Final Needs Case 2023
- Type:
- Date:
- 13 June 2023
- Size:
- 3.4 MB
This is an initial or final needs case submitted to Ofgem, seeking support and approval for the recommended reinforement strategy. Submitted 10 May 2023.
-
Pre_Application Consultation Report
- Type:
- Date:
- 26 January 2023
- Size:
- 6.5 MB
This material provides information to our stakeholders about the project.
-
Planning Statement
- Type:
- Date:
- 26 January 2023
- Size:
- 775.3 KB
This document provides the Planning Statement for the Proposed Development at Crarae Substation produced in November 2022.
-
Appendix-1-figures 1-2
- Type:
- Date:
- 18 September 2022
- Size:
- 7.7 MB
These maps provide information to our stakeholders about the study area and natural heritage present within the project, produced 07 June 2021.
-
Appendix 1- figures-3-4
- Type:
- Date:
- 18 September 2022
- Size:
- 7.4 MB
These maps provide information to our stakeholders about the surface water features and peatland classifications present within the project, produced 07 June 2021.
-
Appendix 1 - figures 5-7
- Type:
- Date:
- 18 September 2022
- Size:
- 6.9 MB
This map provides information to our stakeholders about the Topography and preferred site locations present within the project, produced 07 June 2021.
-
Argyll and Kintyre 275kv Strategy Consultation Brochure 2021
- Type:
- Date:
- 18 September 2022
- Size:
- 10.2 MB
This document provides information to our stakeholders about the project and was provided during our consultation in July 2021.
-
Argyll and Kintyre 275kv Strategy Consultation Poster 2021
- Type:
- Date:
- 18 September 2022
- Size:
- 100.7 KB
This document provides information to our stakeholders about our consultation events in July 2021.
-
Argyll and Kintyre 275kv Substations Pre-application Consultation Booklet
- Type:
- Date:
- 18 September 2022
- Size:
- 23.3 MB
This material provides information to our stakeholders about the project.
-
Report on Consultation Argyll Substations
- Type:
- Date:
- 18 September 2022
- Size:
- 9.4 MB
This Report on Consultation (and associated appendices/maps) documents the consultation process which has been undertaken for the project at substation site selection stage. It describes the key responses received and provides detail on the actions proposed in response to the issues raised.
-
Substation Site Selection Consultation Document
- Type:
- Date:
- 18 September 2022
- Size:
- 6.4 MB
This material provides information to our stakeholders about the project or consultation events in July 2021.
-
Environmental Appraisal Chapter 1 - Contents Introduction and Scope.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 1.3 MB
-
Environmental Appraisal Chapter 10 - Mitigation Summary.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 292.1 KB
-
Environmental Appraisal Chapter 2 - Project Description.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 1 MB
-
Environmental Appraisal Chapter 3 - LVIA.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 366.7 KB
-
Environmental Appraisal Chapter 4 - Ecology.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 4 MB
-
Environmental Appraisal Chapter 5 - Forestry.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 603.1 KB
-
Environmental Appraisal Chapter 6 - Hydrology.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 1.8 MB
-
Environmental Appraisal Chapter 7 - Archaeology.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 1.4 MB
-
Environmental Appraisal Chapter 8 - Noise.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 306 KB
-
Environmental Appraisal Chapter 9 - Traffic.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 343.8 KB
-
Figure 1a - Site Location and Context Plan.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 4 MB
-
Figure 1b Site Location Plan - revised.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 3.9 MB
-
Figure 2 - Site Layout - revised.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 1.5 MB
-
Figure 3 - OHL Tower Elevations.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 499.8 KB
-
Figure 4a - Typical Access Track Sections Sheet 1.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 258.6 KB
-
Figure 4b - Typical Access Track Sections Sheet 2.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 266.1 KB
-
Figure 5 - Site Access Details.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 300.3 KB
-
Environmental Appraisal Annex A - General Environmental Management Plans.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 4.3 MB
-
Environmental Appraisal Annex B - EIA Screening Opinion.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 322 KB
-
Environmental Appraisal Annex C - LVA Methodology.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 280.5 KB
-
Environmental Appraisal Annex D - Landscape Character Sensitivity.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 288.8 KB
-
Environmental Appraisal Annex E - Part 1 Landscape Figures.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 4.2 MB
-
Environmental Appraisal Annex E - Part 2 Photomontages.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 1.4 MB
-
Environmental Appraisal Annex F - Ornithology Consultation.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 896.1 KB
-
Environmental Appraisal Annex G - Extended Phase 1 Survey Report.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 2.3 MB
-
Environmental Appraisal Annex H - Species Protection Plans.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 3.6 MB
-
Environmental Appraisal Annex I - Habitat Regulations Appraisal.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 679.5 KB
-
Environmental Appraisal Annex J - Forestry.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 3.6 MB
-
Environmental Appraisal Annex K - Drainage Strategy and Drainage Plans.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 1.5 MB
-
Environmental Appraisal Annex L - Hydrology Methodology.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 369.5 KB
-
Environmental Appraisal Annex M - Private Water Supply Risk Assessment.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 990.7 KB
-
Environmental Appraisal Annex N - Water Construction Management Plan.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 1.4 MB
-
Environmental Appraisal Annex O - Peat Management Plan.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 4.6 MB
-
Environmental Appraisal Annex P - Peat Slide Risk Assessment.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 3.1 MB
-
Environmental Appraisal Annex Q - Routing Report.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 4 MB
-
Environmental Appraisal Annex R - Cultural Heritage Site Gazetteer and Walkover Survey Report.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 2.5 MB
-
Environmental Appraisal Annex S - Noise and Vibration.pdf
- Type:
- Date:
- 13 October 2023
- Size:
- 1.3 MB
Crarae Substation Town and Country Planning Application
-
Webinar Connections Reform - our role in G2tWQ process 22 July 2025.pdf
- Type:
- Date:
- 25 July 2025
- Size:
- 2 MB
-
Argyll and Kintyre Mailer
- Type:
- Date:
- 27 October 2023
- Size:
- 161.3 KB
This document provides an update to our stakeholders about the project.
-
Argyll and Kintyre Reinforcement Strategy LOTI Final Needs Case 2023
- Type:
- Date:
- 13 June 2023
- Size:
- 3.4 MB
This is an initial or final needs case submitted to Ofgem, seeking support and approval for the recommended reinforement strategy. Submitted 10 May 2023.
-
Pre_Application Consultation Report
- Type:
- Date:
- 26 January 2023
- Size:
- 6.5 MB
This material provides information to our stakeholders about the project.
-
Planning Statement
- Type:
- Date:
- 26 January 2023
- Size:
- 775.3 KB
This document provides the Planning Statement for the Proposed Development at Crarae Substation produced in November 2022.
-
Earraghail Report on Consultation - Route selection.pdf
- Type:
- Date:
- 20 January 2023
- Size:
- 8.3 MB
-
Appendix-1-figures 1-2
- Type:
- Date:
- 18 September 2022
- Size:
- 7.7 MB
These maps provide information to our stakeholders about the study area and natural heritage present within the project, produced 07 June 2021.
-
Appendix 1- figures-3-4
- Type:
- Date:
- 18 September 2022
- Size:
- 7.4 MB
These maps provide information to our stakeholders about the surface water features and peatland classifications present within the project, produced 07 June 2021.
-
Appendix 1 - figures 5-7
- Type:
- Date:
- 18 September 2022
- Size:
- 6.9 MB
This map provides information to our stakeholders about the Topography and preferred site locations present within the project, produced 07 June 2021.
-
Argyll and Kintyre 275kv Strategy Consultation Brochure 2021
- Type:
- Date:
- 18 September 2022
- Size:
- 10.2 MB
This document provides information to our stakeholders about the project and was provided during our consultation in July 2021.
-
Argyll and Kintyre 275kv Strategy Consultation Poster 2021
- Type:
- Date:
- 18 September 2022
- Size:
- 100.7 KB
This document provides information to our stakeholders about our consultation events in July 2021.
-
Argyll and Kintyre 275kv Substations Pre-application Consultation Booklet
- Type:
- Date:
- 18 September 2022
- Size:
- 23.3 MB
This material provides information to our stakeholders about the project.
-
Report on Consultation Argyll Substations
- Type:
- Date:
- 18 September 2022
- Size:
- 9.4 MB
This Report on Consultation (and associated appendices/maps) documents the consultation process which has been undertaken for the project at substation site selection stage. It describes the key responses received and provides detail on the actions proposed in response to the issues raised.
-
Substation Site Selection Consultation Document
- Type:
- Date:
- 18 September 2022
- Size:
- 6.4 MB
This material provides information to our stakeholders about the project or consultation events in July 2021.
Crarae Substation Town and Country planning application
-
Environmental Appraisal Annex A - General Environmental Management Plans.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 4.3 MB
-
Environmental Appraisal Annex B - EIA Screening Opinion.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 322 KB
-
Environmental Appraisal Annex C - LVA Methodology.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 280.5 KB
-
Environmental Appraisal Annex D - Landscape Character Sensitivity.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 288.8 KB
-
Environmental Appraisal Annex E - Part 1 Landscape Figures.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 4.2 MB
-
Environmental Appraisal Annex E - Part 2 Photomontages.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 1.4 MB
-
Environmental Appraisal Annex F - Ornithology Consultation.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 896.1 KB
-
Environmental Appraisal Annex G - Extended Phase 1 Survey Report.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 2.3 MB
-
Environmental Appraisal Annex H - Species Protection Plans.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 3.6 MB
-
Environmental Appraisal Annex I - Habitat Regulations Appraisal.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 679.5 KB
-
Environmental Appraisal Annex J - Forestry.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 3.6 MB
-
Environmental Appraisal Annex K - Drainage Strategy and Drainage Plans.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 1.5 MB
-
Environmental Appraisal Annex L - Hydrology Methodology.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 369.5 KB
-
Environmental Appraisal Annex M - Private Water Supply Risk Assessment.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 990.7 KB
-
Environmental Appraisal Annex N - Water Construction Management Plan.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 1.4 MB
-
Environmental Appraisal Annex O - Peat Management Plan.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 4.6 MB
-
Environmental Appraisal Annex P - Peat Slide Risk Assessment.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 3.1 MB
-
Environmental Appraisal Annex Q - Routing Report.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 4 MB
-
Environmental Appraisal Annex R - Cultural Heritage Site Gazetteer and Walkover Survey Report.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 2.5 MB
-
Environmental Appraisal Annex S - Noise and Vibration.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 1.3 MB
-
Environmental Appraisal Chapter 1 - Contents Introduction and Scope.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 1.3 MB
-
Environmental Appraisal Chapter 10 - Mitigation Summary.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 292.1 KB
-
Environmental Appraisal Chapter 3 - LVIA.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 366.7 KB
-
Environmental Appraisal Chapter 4 - Ecology.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 4 MB
-
Environmental Appraisal Chapter 5 - Forestry.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 603.1 KB
-
Environmental Appraisal Chapter 6 - Hydrology.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 1.8 MB
-
Environmental Appraisal Chapter 7 - Archaeology.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 1.4 MB
-
Environmental Appraisal Chapter 8 - Noise.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 306 KB
-
Environmental Appraisal Chapter 9 - Traffic.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 343.8 KB
-
Figure 10 - Proposed Site Profiles.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 2.5 MB
-
Figure 11 - Proposed Site Access Profiles.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 1.1 MB
-
Figure 4b - Substation Building Elevations.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 339.6 KB
-
Figure 4d - Transformer Building Elevations.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 341.1 KB
-
Figure 5 - Generator Building Elevations.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 256 KB
-
Figure 6 - Electrical Layout Elevations.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 651.5 KB
-
Figure 7 - Typical Deer Fence and Gate.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 287.3 KB
-
Figure 8a - Typical Access Track Sections Sheet 1.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 259 KB
-
Figure 8b - Typical Access Track Sections Sheet 2.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 266.7 KB
-
Figure 9 - Site Access Details.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 283.7 KB
-
Pre Application Consultation Report.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 6.5 MB
-
Red Line Boundary Plan.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 1.9 MB
-
Septic Tank and Private Water Supply Location Plan.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 2.6 MB
-
Site Location Plan.pdf
- Type:
- Date:
- 12 October 2023
- Size:
- 3.7 MB
FAQs
FAQs
-
SSEN Transmission is responsible for maintaining and investing in the electricity transmission network in the north of Scotland and our network extends over a quarter of the UK’s land mass, crossing some of its most challenging terrain.
Our operating area is home to vast renewable energy resources, and this is being harnessed by wind, hydro and marine generation. Working closely with National Grid Electricity System Operator (the 'ESO'), we enable electricity generators to connect to the transmission system, allowing the electricity generated by them to be transported to areas of demand across the country. -
Following a minority stake sale which completed in November 2022, SSEN Transmission is now owned 75% by SSE plc and 25% by Ontario Teachers’ Pension Plan Board.
SSE plc sold its UK domestic electricity and gas retail business, along with domestic energy services to OVO Energy in January 2020 and no longer manages these customer accounts.
-
It’s the highest voltage electricity network in the UK – the ‘motorway network’ of the energy world. It transmits large quantities of electricity over long distances via wires carried on a system of mainly metal towers (pylons) and large substations. Transmission voltages in Scotland are 132kV, 275kV and 400kV. Larger generation schemes usually connect to the Transmission system.
The lower voltage parts of the system are called distribution networks. In Scotland, these local networks operate below 132kV whereas in England the distribution network includes 132kV.
-
As a stakeholder-led business, throughout the life of our projects, we aim to work positively with local communities and keep people informed about what we are doing. This is particularly important when we are developing new projects, we want to understand what local people think about our plans.
We always endeavour to take the time to discuss our proposals with local community councils and the wider affected community and to carry out engagement throughout each of the development stages, listening to feedback before finalising project plans. The feedback we receive is vital to help us develop proposals that reflect the views of a variety of stakeholder.
-
To find out more about a project, visit our project web pages which can be searched by location or area. Each project has a dedicated Community Liaison Manager that you can contact. You can find their contact details in the individual project pages, where you can also sign up to project updates.
Project Contacts
Amanda McClintock | Community Liaison Manager
Lynn Dandie | Senior Land Manager
Latest Links
-
SSEN Transmission Launches £3m Argyll Community Benefit Fund
Recite me
To make use of this function please click on the 3 'A's' button at the bottom left of the website.