Overview
Extension Energisation
After almost 24 months of hard work, we are celebrating the energisation of the new extension to Abernethy substation which will facilitate the connection of up to 50 megawatts (MW) of renewable energy to the local electricity distribution network – enough to power around 60,000 homes each year.
Follow this link to find out more.
About the Project
Transmission connection offers were accepted by our sister company, Scottish Hydro Electric Power Distribution Plc (SHEPD) across 4 schemes to the local 33kV network supplied from Abernethy Grid Supply Point (GSP) 132/33kV substation.
The addition of these four schemes will mean the total connected and contracted generation at Abernethy GSP will exceed the existing 60MVA firm capacity, therefore we are proposing to upgrade the Abernethy GSP.
It is proposed to replace the existing 2 x 60MVA 132/33kV grid transformers with 2 x 120MVA 132/33kV transformer units within the Abernethy GSP substation. The works will include the following:
At Abernethy GSP substation, install two new 132/33kV 120MVA grid transformer units. Undertake upgrades to the existing transformer plinths and foundations to accommodate the larger transformers. Connect new transformers to the existing 33kV circuit breakers.
Why is the Project Required?
As part of our statutory and Transmission Licence obligations, we have a number of duties including:
- the development and maintenance of an efficient, coordinated and economical system of electricity transmission
- to facilitate competition in the supply and generation of electricity
- to ensure that the security of the network is maintained as the demand and/or generation connections change over time
Community Engagement
Throughout the life of our projects, we aim to work positively with local communities and keep people informed about what we are doing. This is particularly important when we are developing a proposal and we want to understand what local people think about our plans.
We endeavour to take the time to discuss proposals with local community councils, encourage engagement from the wider community and listen to the feedback we receive.
We will do our best to answer any questions and address issues or concerns that are raised with us.
When our project progresses into construction, we will continue working closely with the local community to ensure that our work has as little impact on the lives of those living and working in the area and as many long term positive effects as possible.
How we’re embracing artificial intelligence (AI)
We intend to use AI to assist our experienced teams in the analysis of your feedback, so we can categorise key points raised more quickly. You can learn more about how we’re utilising AI on this dedicated web page.
Project Updates
Featured updates
Featured updates for this project

Extension Energisation
Project updates
Project Documents
Project Documents
-
Public consultation booklet
- Type:
- Date:
- 06 July 2020
- Size:
- 18 MB
This document is the information booklet that accompanied the virtual consultation held on 7 July 2020.
-
Location plan with environmental constraints
- Type:
- Date:
- 06 July 2020
- Size:
- 1.6 MB
This document provides the location of the Abernethy substation and highlights environmental constraints.
-
Proposal of application notice red line boundary layout
- Type:
- Date:
- 06 July 2020
- Size:
- 6.8 MB
This document provides the red line boundary layout included in our Proposal of Application Notice (PAN) to Perth and Kinross Council.
-
View point 7 at year 15
- Type:
- Date:
- 06 July 2020
- Size:
- 4.3 MB
This document provides a viewpoint visualisation at viewpoint 7 of the landscape mitigation at year 15 of screening following the planting that is proposed.
-
View point 7 at year 0
- Type:
- Date:
- 06 July 2020
- Size:
- 4.3 MB
This document provides a viewpoint visualisation at viewpoint 7 of the landscape mitigation at year 0 of screening following the planting that is proposed.
-
View point 4 at year 15
- Type:
- Date:
- 06 July 2020
- Size:
- 4.9 MB
This document provides a viewpoint visualisation at viewpoint 4 of the landscape mitigation at year 15 of screening following the planting that is proposed.
-
View point 4 at year 0
- Type:
- Date:
- 06 July 2020
- Size:
- 4.5 MB
This document provides a viewpoint visualisation at viewpoint 4 of the landscape mitigation at year 0 of screening following the planting that is proposed.
-
View point 3 at year 15
- Type:
- Date:
- 06 July 2020
- Size:
- 5.5 MB
This document provides a viewpoint visualisation at viewpoint 3 of the landscape mitigation at year 15 of screening following the planting that is proposed.
-
View point 3 at year-0
- Type:
- Date:
- 06 July 2020
- Size:
- 5.5 MB
This document provides a viewpoint visualisation at viewpoint 3 of the landscape mitigation at year 0 of screening following the planting that is proposed.
-
Indicative landscape environmental mitigation plan
- Type:
- Date:
- 06 July 2020
- Size:
- 1.6 MB
This document details our indicative landscape and environmental mitigation plan for the substation.
-
Proposed layout
- Type:
- Date:
- 06 July 2020
- Size:
- 1.2 MB
This document provides the proposed electrical layout drawing for the extension to Abernethy substation.
-
Consultation times
- Type:
- Date:
- 17 June 2020
- Size:
- 1.1 MB
This document provides the timings of the virtual consultation held 7 July 2020.
Gallery
Progress Gallery
FAQs
FAQs
Latest Links
-
New substation extension energised at Abernethy
Recite me
To make use of this function please click on the 3 'A's' button at the bottom left of the website.
