Beyond 2030: Powering Scotland's Future

Investing in the next generation of transmission infrastructure

The independent National Energy System Operator’s (NESO) ‘Pathway to 2030’ published in 2022 (and then refreshed in 2023) outlined an electricity network design called the Pathway to 2030 Holistic Network Design (HND). The HND outlined the network needed to connect some 23 GW of offshore wind power by 2030.  The HND programme only gets Great Britain so far in its journey towards net zero, including the target outlined in the British Energy Security Strategy of 50 GW of offshore wind by 2030. 

In March 2024, NESO published its 'Beyond 2030' report, responding to the government’s request to build on the HND design to connect more offshore wind. The resulting so-called HND ‘follow-up exercise’ in Beyond 2030 includes additional network upgrades and new capacity to connect a further 21 GW of offshore wind.
 

For the north of Scotland, Beyond 2030 included the next phase of ScotWind and confirmed the need for several new, replacement and upgraded transmission projects to be delivered by 2035, representing a potential investment of over £5 billion.

These projects are essential to:
 

- Enable additional ScotWind connections. 
- Support the deployment of homegrown, low-carbon electricity. 
- Strengthen the UK’s energy security and progress toward net zero. 

New Deer

We’re extending the New Deer substation to increase capacity and enable more renewable power to enter the network.

This project will deliver:

  • an extension of the substation at New Deer
  • approx 3km of new 400kV underground cable between New Deer and Greens

Expected completion date: 2030

There are 2 parts to this project:

 

substation arial

Peterhead, Persley to Kintore

We’re strengthening the grid in Scotland's Northeast and around Aberdeen by increasing capacity of existing transmission linesfrom 275kV to 400kV. This upgrade will help ensure security of supply of power to Aberdeen grid and helps support delivery of renewable energy generated by windfarms.

This project will deliver:

  • upgrading existing 51km of the overhead line between Peterhead to Kintore to allow for operation at 400kV
  • a new substation in the South Formartine area
  • upgrading 12km of the existing overhead line between Persley Tee Point and Persley
  • Installing a new SuperGrid Transformer building at our substation in Peterhead, Boddam to allow Peterhead to Kintore overhead line operate at 400kV 
  • Upgrade works at our existing 400kV substation at Kintore to allow the overheadline between Peterhead and Kintore to operate at 400kV
  • upgrading our Kintore substation so the overhead line to Peterhead can operate at a higher voltage

Expected completion date: 2029 - 2033

There are 2 parts to this project:

Peterhead, Persley and Kintore upgrade


South Formartine substation

substation

Shetland HVDC Link 2

The Shetland HVDC Link 2 is needed to provide a secure, long-term connection between Shetland and the GB electricity network. It will enable new renewable generation, such as onshore and offshore wind farms, to connect to the grid, and support demand projects such as green hydrogen production. By reinforcing the existing Shetland HVDC Link 1, it also provides resilience for the islands’ electricity supply.

This project will deliver:

  • In Northern Shetland, an HVDC converter station, 220kV AC substation and a 400kV AC substation (Northern Hub)  
  • In West Aberdeenshire, an HVDC converter station and a 400kV AC substation (Strathbogie Hub) 
  • In Shetland, up to 40km of underground cable and on Mainland Scotland, up to 30km of underground cable 
  • Over 300km of subsea cable, between landfalls in Shetland and Mainland Scotland.  


Expected completion date: 2035

 

Netherton Hub to Peterhead Upgrade

We’re increasing the capacity on the existing 400kV transmission line between the proposed 400kV AC substation at Netherton Hub and the existing Peterhead 400kV substation, maximising the transfer capability between Netherton Hub and the wider transmission network and increasing network security.

This project will deliver:

  • approx 5-6km of new build 400kV overhead line
  • Decommissioning of redundant spans of overhead line

Expected completion date: 2032

map showing the proposed project between Netherton and Peterhead

Dounreay to Spittal

We’re building a new 400kV line between Dounreay and Spittal to connect renewable energy generated from off shorefarm.

This project will deliver:

  • a new 400kV substation near Dounreay
  • approx 21km of 400kV overhead line 

Expected completion date: 2034

Project page coming soon

400KV LINE

Blackhillock, Cairnford to Kintore

We’re upgrading the line from 275kV to 400kV to allow more power to flow and relieve a bottleneck toward Kintore.

This project will deliver:

  • a substation extension at Blackhillock
  • a substation extension at Kintore
  • a new substation near Cairnford
  • approx 51km of new 400kV overhead line between Blackhillock and Kintore
  • Partial removal of the existing 275kV overhead line between Blackhillock, Cairnford and Kintore

Expected completion date: 2034

Project page coming soon

substation overhead

Frequently Asked Questions

Here are some of the most common questions we get about our future projects