Beyond 2030: Powering Scotland's Future
Investing in the next generation of transmission infrastructure
The independent National Energy System Operator’s (NESO) ‘Pathway to 2030’ published in 2022 (and then refreshed in 2023) outlined an electricity network design called the Pathway to 2030 Holistic Network Design (HND). The HND outlined the network needed to connect some 23 GW of offshore wind power by 2030. The HND programme only gets Great Britain so far in its journey towards net zero, including the target outlined in the British Energy Security Strategy of 50 GW of offshore wind by 2030.
In March 2024, NESO published its 'Beyond 2030' report, responding to the government’s request to build on the HND design to connect more offshore wind. The resulting so-called HND ‘follow-up exercise’ in Beyond 2030 includes additional network upgrades and new capacity to connect a further 21 GW of offshore wind.
In June of 2026, NESO updated their Beyond 2030 report which sets out a series of additional new and upgraded electricity transmission network reinforcements across Great Britain that are required to deliver UK and Scottish energy targets.
For the north of Scotland, Beyond 2030 included the next phase of ScotWind and confirmed the need for several new, replacement and upgraded transmission projects to be delivered by 2035, representing a potential investment of over £5 billion.
These projects are essential to:
- Enable additional ScotWind connections.
- Support the deployment of homegrown, low-carbon electricity.
- Strengthen the UK’s energy security and progress toward net zero.
Pathway to 2030 and beyond
New Deer
We’re extending the New Deer substation to increase capacity and enable more renewable power to enter the network.
This project will deliver:
- An extension of the substation at New Deer
- Approx 3km of new 400kV underground cable between New Deer and Greens
Expected completion date: 2030
There are two parts to this project:
New Deer Substation Extension
Peterhead, South Formartine to Kintore
We’re strengthening the grid in Scotland's Northeast and around Aberdeen by increasing capacity of existing transmission linesfrom 275kV to 400kV. This upgrade will help ensure security of supply of power to Aberdeen grid and helps support delivery of renewable energy generated by windfarms.
We’re strengthening the grid in Scotland's north-east and around Aberdeen by increasing capacity of existing transmission lines from 275kV to 400kV. This upgrade will help ensure security of supply of power to the Aberdeen grid and helps support delivery of renewable energy generated by windfarms.
This project will deliver:
- Upgrading 51km of the existing overhead line between Peterhead to Kintore to allow for operation at 400kV
- A new 400/132kV substation in the South Formartine area
- Upgrading 12km of the existing overhead line between Persley Tee Point and Persley. The line will continue to operate at 275kV until substation works are complete, after which it will operate at 132kV.
- Installation of a new transformer building at our substation in Peterhead (Boddam) and upgrading our existing Kintore substation to allow the Peterhead to Kintore overhead line to operate at 400kV
Expected completion date: 2029 - 2033
There are three parts to this project:
Peterhead, Persley and Kintore upgrade
South Formartine substation
Peterhead Substation upgrade
Shetland HVDC Link 2
The Shetland HVDC Link 2 is needed to provide a secure, long-term connection between Shetland and the GB electricity network. It will enable new renewable generation, such as onshore and offshore wind farms, to connect to the grid, and support demand projects such as green hydrogen production. By reinforcing the existing Shetland HVDC Link 1, it also provides resilience for the islands’ electricity supply.
This project will deliver:
- In Northern Shetland, an HVDC converter station, 220kV AC substation and a 400kV AC substation (Northern Hub)
- In West Aberdeenshire, an HVDC converter station and a 400kV AC substation (Strathbogie Hub)
- In Shetland, up to 40km of underground cable and on Mainland Scotland, up to 30km of underground cable
- Over 300km of subsea cable, between landfalls in Shetland and Mainland Scotland.
Expected completion date: 2035
Netherton Hub to Peterhead Upgrade
We’re increasing the capacity on the existing 400kV transmission line between the proposed 400kV AC substation at Netherton Hub and the existing Peterhead 400kV substation, maximising the transfer capability between Netherton Hub and the wider transmission network and increasing network security.
This project will deliver:
- Approx 5-6km of new build 400kV overhead line
- Decommissioning of redundant spans of overhead line
Expected completion date: 2032
Dounreay to Spittal
We’re building a new 400kV line between Dounreay and Spittal to connect renewable energy generated from off shorefarm.
This project will deliver:
- A new 400kV substation near Dounreay
- Approx 21km of 400kV overhead line
Expected completion date: 2034
Project page coming soon
Blackhillock, Cairnford to Kintore
We’re upgrading the line from 275kV to 400kV to allow more power to flow and relieve a bottleneck toward Kintore.
We’re upgrading the line from 275kV to 400kV to allow more power to flow and relieve a bottleneck toward Kintore.
This project will deliver:
- A substation extension at Blackhillock
- A substation upgrade at Kintore
- A new substation near Cairnford
- Approx 51km of new 400kV overhead line between Blackhillock and Kintore
- Partial removal of the existing 275kV overhead line between Blackhillock, Cairnford and Kintore
Expected completion date: 2034
Project page coming soon
