Skye Reinforcement
- Type:
- Transmission reinforcement
- Location:
- Highland
- Rating:
- 132kV
We are reinforcing the high voltage electricity network from Ardmore on the Isle of Skye to Fort Augustus.
Overview
Status: Construction Phase
Stage 4 of 5
-
Stage 1: Project Assessment: (Completed)
During the Project Assessment stage, we’re committed to evaluating potential project strategies. At this stage, we provide information about the proposed project plans on our website for stakeholders to review and provide feedback on, as well as holding in-person events within the local community demonstrating our collaborative approach to the project's development.
-
Stage 2: Early Development: (Completed)
During Early Development, we concentrate on refining the project details, based on our initial assessment of key environmental, technical, and economic factors to identify the best performing approach. We would like to gain further input from communities through accessible in-person and in some cases online consultations, which are crucial in refining our plans and strategies before advancing to the application stage.
-
Stage 3: Project Refinement: (Completed)
The Project Refinement stage is where we finalise project plans and submit the required planning applications to the relevant planning authorities. Communities and other key stakeholders can provide feedback directly to the appropriate body such as their local council and constituent representatives.
-
Stage 4: Construction Phase: (In progress)
Within the construction phase we mobilise our workforce, contractors, and necessary equipment to begin construction. We maintain open channels of communication, allowing communities and stakeholders to submit feedback on the construction activities to our dedicated Community Liaison Managers, ensuring ongoing engagement to any thoughts or concerns while we carry out work in the area.
-
Stage 5: Operational Phase:
At this final stage, the project successfully moves into the operational phase, with the surrounding environment restored to its original state or better. Our Community Liaison Mangers continue to be available to address any questions or concerns, ensuring a lasting positive impact and strong community relations even after the construction activities conclude.
About the project
Find out more about the project by exploring this section.
What are we doing?
- Extend the substations at Broadford and Edinbane to accommodate the new infrastructure
- Install 15km of underground cable near the Cuillin Hills on Skye
- Install 9km of underground cable on the approach to Fort Augustus Substation.
Why is this project needed?
The need to upgrade the grid has been assessed by the National Energy System Operator (NESO), approved by Ofgem and endorsed by the UK Government through its Clean Power 2030 Action Plan. As the owner of the transmission network in the north of Scotland, SSEN Transmission is required under its licence obligations to develop and deliver this work.
What happens next?
- Ground investigations and surveys across the project area, including vegetation management
- Public road improvements
- Site mobilisation
- Additional ancillary planning applications from our contractors, including for borrow pits and access tracks
- Developing and sharing traffic management plans
- Progressing detailed designs and delivery models/methods
How will this construction affect me?
As work on the Skye Reinforcement Project progresses, you may notice construction activity in your local area. This could include construction vehicles, temporary traffic management and activity at access points or along the new overhead power line route.
The level of activity will vary depending on where you live and what work is taking place nearby. We understand that construction can affect day-to-day life, and we will work closely with our local communities and contractors to help minimise disruption wherever possible.
We will keep communities informed about upcoming works and provide updates to help residents, businesses and road users know what to expect.
To keep up to date with construction activity near you, please register for project updates for your local area. We’ll use these updates to share information about upcoming works and anything you may need to be aware of. These are also available in the Project Updates section on this page.
If you have any questions about the project or construction activity in your area, please contact us at skye.reinforcement@sse.com.
What else is happening nearby?
Our individual projects form part of a wider energy grid that transmits electricity across the north of Scotland and beyond.
This includes overhead lines, substations and subsea links which are part of a major upgrade of the electricity transmission network across Great Britain.
There are a number of related projects in this area. If you are intererested in learning more about these projects please visit their dedicated pages using the following links:
Fort Augustus Substation 400kV upgrade
Loch Fearna PSH Connection
Coire Glas Connection and Loch Lundie Substation
Quoich Power Station to Switching Station OHL Replacement
You can also visit our project map to find projects in your area.
SSEN Distribution, the company responsible for carrying electricity into homes and businesses, is also working in the area. If you need to get in touch, you can contact them via the SSEN Distribution website.
Contact us
Maren Ebeling
Community Liaison Manager
- Address: 10 Henderson Road, Inverness, IV1 1SN
WATCH: Over the hills again...learn about the project from our team
Project updates
Featured updates
Featured updates for this project
SSEN Transmission working to explore new temporary workforce accommodation location in Portree
Skye Reinforcement Local Fund opens November 2026
Planned Drone Surveys – September/October 2026
SSEN Transmission begins recruitment for community benefit fund decision-making forum in West and Mid Highland
Project updates
-
SSEN Transmission working to explore new temporary workforce accommodation location in Portree
SSEN Transmission is working with Lochalsh & Skye Housing Association (LSHA) to explore Kiltaraglen, near Portree, as a potential location for temporary workforce accommodation for the Skye Reinforcement Project.
The site is already identified for future housing. The proposals could see SSEN Transmission deliver infrastructure such as access roads, drainage and utility access, which could remain after the temporary accommodation is removed and help LSHA bring forward permanent homes.
Public consultations will be held in the coming months, giving the community an opportunity to view the proposals and provide feedback ahead of any planning application.
The plans follow the withdrawal of the previous Broadford accommodation proposal and build on SSEN Transmission and LSHA’s recent partnership to bring five flats in Portree back into use.
Please click here to read the full press release and find out more.
-
Skye Reinforcement Local Fund opens November 2026
We’re pleased to confirm that the Skye Reinforcement Local Fund will open for applications on 4 November 2026, with applications accepted until 10 February 2027.
The fund guidance, including information to help community groups and organisations prepare their applications, is now available on the Skye Reinforcement Local Fund webpage.
Once the fund has opened, we will hold two online information sessions. These will give community groups and organisations considering applying the opportunity to find out more about the fund before submitting an application.
Online information sessions:
- Wednesday 11 November, 2pm to 3pm: Register here
- Wednesday 2 December, 7pm to 8pm: Register here
We would encourage local groups and organisations interested in applying to take a look at the guidance in advance and join one of the information sessions if they would like to learn more.
Planned Drone Surveys – September/October 2026
As part of the Skye Reinforcement Project, the planned drone surveys are scheduled to continue through September and October 2026 at locations across the project area.
The Drone Surveys are undertaken by Balfour Beatty. All flights are being logged with the appropriate aviation authorities and details of timing and location are available to view on TheDroneMap portal.
These surveys will capture aerial imagery and support project planning and design activities.
We thank local communities for their patience where survey activities are undertaken.
Please do not hesitate to get in touch on skye.reinforcement@sse.com if you have any questions.If you would like to contact Balfour Beatty directly, please contact skyecommunications@balfourbeatty.com.
SSEN Transmission begins recruitment for community benefit fund decision-making forum in West and Mid Highland
SSEN Transmission begins recruitment for community benefit fund decision-making forum in West and Mid Highland
We are inviting people from across West and Mid Highland to apply to join a new decision-making forum that will help direct millions of pounds of investment into local communities.
We have launched recruitment for members of our new West and Mid Highland Local Investment Forum, which will be responsible for assessing and deciding on applications to our community benefit funds across the region.
The forum's initial focus will be the Skye Reinforcement Local Fund, which is expected to launch in autumn 2026 and will invest £5.46 million into local communities over a minimum three-year period.
Read the full article here
Welfare Cabin deliveries to Edinbane Substation (Balmeanach, Struan)
As part of preparations for the next phase of construction at Edinbane Substation, 44 welfare cabins will be delivered to site during the week commencing 14 September 2026.
Residents may notice an increase in large vehicle movements across Skye while the cabins are transported to site. Deliveries will begin on Monday 14 September, with the main programme of cabin deliveries taking place throughout the week. Around five to seven deliveries are expected each day, and all cabins are expected to be in place by the end of the week.
The cabins will form a temporary welfare compound at the substation, providing office accommodation, meeting rooms, drying facilities and staff welfare areas.
We appreciate that these deliveries may cause some inconvenience along the delivery route and would like to thank all road users for their patience and understanding as this work is carried out.
Keeping you informed
We will continue to provide updates as the works progress. For the latest project information and to sign up for email updates, visit the Skye Reinforcement Project webpage.
For any questions, please contact skye.reinforcement@sse.com.
-
Road improvement works to begin at Broadford Substation / A87
We would like to inform that road improvement works associated with the Broadford Substation development are due to begin on 1 September 2026 at the A87/Old Corry Road junction in Broadford.
Key information
- Start date: 1 September 2026
- Location: A87/Old Corry Road junction, Broadford
- Activity: Junction access (bellmouth) upgrade
- Duration: Approximately 5-6 weeks
- Traffic management: Northbound lane closure on the A87 with three-way traffic lights operating 24/7
The works are required to provide safe access for construction traffic serving the Broadford Substation site.
Materials for the junction works will be sourced from Sconser Quarry, with around three to four aggregate deliveries per day expected during this phase.
Old Corry Road upgrade works
Following completion of the junction improvements, upgrade works will begin on Old Corry Road. These works are expected to last around 11-12 weeks and will be carried out using the new diversion road, ensuring access remains open at all times.
The Old Corry Road works will not affect traffic on the A87. Material deliveries from Sconser Quarry are expected to increase to approximately 10-15 loads per day during this phase.
Keeping you informed
We appreciate the patience and understanding of residents, businesses and road users while these essential improvements are completed and will continue to provide updates as the works progress.
For the latest project information and to sign up for email updates, visit the Skye Reinforcement Project webpage.
For any questions, please contact skye.reinforcement@sse.com.
Kinloch Hourn C1144/U1207 road works update
We are pleased to confirm that all road closures associated with SSEN Transmission's works on the C1144 and U1207 to Kinloch Hourn have now been lifted, and the road is now fully open to traffic.
A small number of minor snagging works are still to be completed. These will not require any further road closures, but stop/go traffic management may be in place at certain times/locations to allow these final activities to be carried out safely. Works on the Quoich Bridge also remain outstanding but again, these works will be undertaken with stop/go traffic management in place.
We would like to thank residents, businesses and road users for their patience and cooperation throughout the works. We appreciate the support shown by local communities while this programme of improvements was completed.
Please don’t hesitate to get in touch if you have any questions regarding the Skye Reinforcement Project by contacting skye.reinforcement@sse.com
Kinloch Hourn Road works update 18 August 2026
We are pleased to confirm that the road leading to Kinloch Hourn (C1144 & U1207) is currently fully open.
The white lining works originally scheduled for the week commencing 17 August have been postponed due to weather conditions.
These works on the U1207, west of Quoich Bridge, are now planned for the coming week and will require a short road closure. Details of the planned closure are provided below.
Please note that the white lining works remain weather dependent. While the current forecast is favourable, the programme may be subject to change.
Expected Road Closure Details
Location: U1207 west of Quoich Bridge – click here for a map.
Start Date: Monday 24 August 2026
End Date: Wednesday 26 August 2026
Closure times: 8:30am – 5:30pmOther localise stop/go traffic management might remain in place at certain locations while contractors continue to complete remaining activities.
We recognise the impact these road closures have on the community and all road users, and we sincerely apologise for any inconvenience caused.
Please get in touch on skye.reinforcement@sse.com if you have any questions, concerns or feedback.
Planned Drone Surveys – August 2026
As part of the Skye Reinforcement Project, photogrammetry drone surveys are scheduled to take place between 11 and 19 August 2026 at a number of locations along sections of the B885, A863, A87 (between Glen Varragil & Sconser) and Kinlochhourn Road.
These surveys will be carried out using drones to capture aerial imagery and support project planning and design activities.
Please note that all drone operations are weather dependent and cannot be undertaken during high winds or moderate to heavy rain. Any weather-related delays may result in survey dates being pushed back.
The Drone Surveys are undertaken by Balfour Beatty. All flights have been logged with the appropriate aviation authorities and details are available to view on TheDroneMap portal.
We thank local communities for their patience while these short-duration survey activities are completed.
If you would like to contact Balfour Beatty directly, please contact skyecommunications@balfourbeatty.com.
Please do not hesitate to get in touch on skye.reinforcement@sse.com if you have any questions.
Kinloch Hourn Road works update
We are pleased to confirm that the road leading to Kinloch Hourn (C1144 & U1207) is currently fully open.
A further short road closure will be required to allow for whitelining on the U1207 west of Quoich Bridge. These works are highly weather dependant with the expected schedule outlined below.
Expected Road Closure Details
Location: west of Quoich Bridge - click here for a mapStart Date: Monday 17 August 2026
End Date: Wednesday 19 August 2026
Closure times: 8:30am – 5:30pmOther localise stop/go traffic management might remain in place at certain locations while contractors continue to complete remaining activities.
We recognise the impact these road closures have on the community and all road users, and we sincerely apologise for any inconvenience caused.
Please get in touch on skye.reinforcement@sse.com if you have any questions, concerns or feedback.
-
Kinloch Hourn Road (U1207/C1144) currently open
We are pleased to confirm that the road to Kinloch Hourn is currently fully open with stop/go traffic management in place at some locations.
Due to circumstances outside our control, some surfacing works remain outstanding. We will communicate in advance as to when these works will be undertaken as these will required short road closures.
We would like to thank the community for its continued patience and understanding. We recognise that these works have caused disruption to journeys and apologise for any inconvenience experienced. SSEN Transmission and its contractors remain committed to keeping future disruption to a minimum wherever possible.
If you have any questions please contact skye.reinforcement@sse.com
-
C1144/U1207 Road Closure Update
We are pleased to share a further update on the current road closures timelines for the Kinloch Hourn Road (C114 & U1207).
Unfortunately works were set back by a day due to heavy rain end of last week and whilst our contractors have done their best to catch up, this has impacted the programme. Please find the updated timings below – where timings/circumstances have changed from previous communication these have been underlined in the below
From 02 July 2026 onwards full access is expected to be re-established all the way to Kinloch Hourn.
C1144 (Road from A87 Junction to Quoich Bridge):
- The C1144 closure has been lifted as of midday today (Wed 24 June);
- stop go operations might remain in place in certain locations whilst final works are completed
U1207 (Road from Quoich Bridge to Kinloch Hourn):
- weekday closure Mon-Fri 08:30-17:30 (applies all this week, including on 25/26 June)
- 29 June – 01 July 2026 – road closure remains in place 08:30-17:30
- Road reopens on 02 July
- Stop/go operations will remain in place at certain locations and specifically at the Quoich Bridge
We thank all road users for their patience while we are nearing completion of these road works. Please don’t hesitate to get in touch on skye.reinforcement@sse.com if you have any questions, concerns or feedback.
SSEN Transmission publishes new economic analysis highlighting transformative growth potential of £29bn grid investment programme
We have today published a new economic report setting out the significant economic benefits associated with our planned £29bn investment in new and upgraded electricity transmission infrastructure across the north of Scotland.
The report, titled ‘Re‑energising the North: Transforming Scotland’, provides an update on our previously outlined economic analysis on plans to invest billions in mission-critical grid infrastructure, providing further insight into the scale of economic opportunity associated with the investment programme.
The report reaffirms our programme as one of the largest private infrastructure investments in Scotland’s history, with around £29bn of planned investment across the north of Scotland in the next five years, and it details the extent of the economic opportunity across the region.Using advanced economic modelling to analyse the impact of clean power infrastructure investment, the report’s findings conclude that our investment:
- Will support up to 10,000 jobs in the north of Scotland, and 24,000 across Scotland;
- When added to investment by other transmission operators and investment in generation will add around £60bn to UK economic output - with the Scottish economy up to 3% larger over the long term;
- Will deliver long-term improvements in productivity, wages and economic resilience, with employees moving into higher-value roles and key sectors expanding permanently; and
- Will create unique opportunities for Scottish suppliers, businesses and communities across multiple sectors, including forestry, peatland restoration, aggregates and concrete too.
The findings highlight the importance of ensuring that the benefits of investment are felt locally, with thousands of skilled jobs, increased supply chain activity, and investment flowing into communities across the north of Scotland.
Read the full News and Views article to find out more.
Proposed Ashaig Workers Village – Update on Planning Application
We would like to inform you that our contractor Balfour Beatty has submitted an updated layout for the proposed Ashaig workers’ village to the Highland Council.
This update was made following feedback from the Highland Council and consultees. The overall footprint of the site has been reduced, with a focus on utilising existing brownfield land and minimising use of greenfield land. While the layout remains broadly similar to the previous design, the storage facilities have been moved off site and the accommodation blocks are now proposed as double storey rather than single storey, allowing for a more compact arrangement.
The updated layout is now available to view on the Highland Council planning portal with reference 25/02051/FUL; the application remains open for public comment until 29 June 2026.
We would encourage anyone with an interest to review the information and share any feedback through the planning portal comment system. Please visit www.streets-uk.com/balfour/ where you find further details on the proposed workers' village and other ancillary planning applications Balfour Beatty have proposed, such as borrow pits.
If you have any questions regarding Balfour Beatty’s planning applications, please don’t hesitate to reach out to skyecommunications@balfourbeatty.com.
C1144/U1207 Road Closure Update
We are pleased to share an update on current road closures timelines:
C1144 (Road from A87 Junction to Quoich Bridge):
- weekday closure until 26 June 2025, Mon-Thu 08:30-16:00 & Fri 08:30-13:00
U1207 (Road from Quoich Bridge to Kinloch Hourn):
- until and including 24 June 2026 – weekday closure Mon-Fri 08:30-17:30
- 25/26 June 2026 – road open, stop/go traffic management
- 29/30 June 2026 – road closure 08:30-17:30
- 01 July – completion of closures, road re-opens
Full access all the way to Kinloch Hourn expected from 01 July 2026 onwards.
Please find below some further background information:
A short delay has affected the reopening of the C1144 due to recent adverse weather conditions, which prevented surfacing works from being completed during periods of significant rainfall. The road was originally scheduled to reopen on 19 June 2026. This has now been revised to 26 June 2026, with works ongoing to bring this forward to 23 June, if conditions allow.
On the U1207, the current closure will remain in place up to and including 24 June 2026. Temporary traffic management using stop and go will be in operation on 25 and 26 June. A further full closure is required on 29 and 30 June to complete final surfacing works. The road is expected to be fully reopened following completion of these works.
We will continue to provide updates as further information becomes available. If you have any questions, concerns or feedback please contact skye.reinforcement@sse.com
-
U1207/C1144 road works update
We are continuing work on the C1144 and U1207 Kinloch Hourn Road. Traffic management, including stop and go measures and daytime road closures, will remain in place while these works are completed.
- Kinloch Hourn to Quoich Bridge: ongoing daytime weekday closures, Monday to Friday, 8.30am to 5.30pm.
- Quoich Bridge to Kingie: daytime weekday closures from 11 May 2026 to 01 June 2026: Monday to Friday, 8.30am to 5.30pm
- Kingie to A87: Shorter daytime closures at work locations from the week commencing 01 June 2026 as follows:
Section
Closure Dates
Closure Times
Approx. distance
Kingie to Tomdoun (A-B)
01/06/26 to 05/06/26
08:30am – 4pm
Approx. 4 miles
Tomdoun to Tornacarry Entrance (B-C)
08/06/26 to 12/06/26
08:30am – 4pm
Approx. 2.5 miles
Tornacarry Entrance to A87 junction (C-G)
15/06/26 to 19/06/26
08:30am – 4pm
Approx. 3 miles
The above information is also available on this map
Parking and Access
We recognise this is a popular area for hill walking and apologise for any inconvenience caused by the works, which have resulted in reduced parking availability.
We kindly ask all visitors to:
- Park responsibly
- Keep Passing Places, the road itself, and farm tracks clear at all times to ensure safe vehicle movement and maintain essential access for residents, emergency services, and road work teams.
We appreciate your understanding and cooperation as we carry out these works. Please accept our apologise for the inconvenience caused.
For enquiries, please contact:
skye.reinforcement@sse.com
Balfour Beatty - Borrow Pit Consultations
Borrow pit consultation underway
Consultation is now under way on proposals for two borrow pit sites near Skeabost and Glenelg, which would support construction of local sections of the Skye Reinforcement Project .
Borrow pits are temporary excavations used to source materials locally. This helps reduce heavy vehicle movements and overall impact on local roads and the environment.
What happens next
Balfour Beatty recently held drop‑in events for local communities and the consultation remains open. The initial feedback period closes 27 May 2026, with further in-person events planned in June 2026
Have your say
You can view the proposals and share feedback online:
If you would prefer a printed copy of the information, or have any questions, you can contact the project team via:
- Freephone: 0800 987 5990
Broadford Substation - Old Corry Road improvement works
As part of the Broadford Substation Extension project, we will be carrying out improvement works on a short section of Old Corry Road. This includes around 300 metres between the A87 junction and the substation entrance. Dates are indicative and may change as the programme is confirmed.
The works will help keep the road safe during construction and will leave a better‑quality road once the project is complete. The works will include rebuilding and widening the road, widening of the A87 junction and repairs to potholes along the full length of Old Corry Road.
Access for residents, local businesses and emergency services will be maintained at all times, and traffic will continue to move with management measures in place if required.
The road works are expected to take around five months in total. Subject to approvals, works are currently planned as follows:
- May 2026: site set‑up
- June 2026: temporary diversion road
- July and August 2026: road reconstruction
- September 2026: A87 junction improvements
Upcoming deliveries
Temporary welfare facilities for construction staff will be installed near the substation to support the works. We have been advised that deliveries will take place from Wednesday 13 May to Friday 15 May 2026. Over this period, approximately 20 heavy goods vehicles will travel to the site.
There may be short delays as vehicles turn from the A87 into Old Corry Road. We apologise for any inconvenience and thank you for your patience and understanding.
If you have any questions, please get in touch on skye.reinforcement@sse.com.
U1207/C1144 road works update
We are continuing work on the C1144 and U1207 Kinloch Hourn Road. Traffic management, including stop and go measures and daytime road closures, will remain in place while these works are completed.
- Kinloch Hourn to Quoich Bridge: ongoing daytime weekday closures, Monday to Friday, 8.30am to 5.30pm.
- Quoich Bridge to Kingie: daytime weekday closures from 11 May 2026 to 01 June 2026: Monday to Friday, 8.30am to 5.30pm
- Kingie to A87: Shorter daytime closures at work locations from the week commencing 01 June 2026. Timings will be confirmed closer to the start of works.
- Please click here for a map of the locations mentioned above.
Please be aware that a culvert at Inshlaggan will be replaced on Monday, 11 May and Tuesday, 12 May 2026, using stop/go traffic management. Apologies for slightly longer delays while the road is required to be made safe for passing vehicles.
This set of overall road works are due to be completed during the week commencing 22 June 2026.
Parking and Access
We recognise this is a popular area for hill walking and apologise for any inconvenience caused by the works, which have resulted in reduced parking availability.
We kindly ask all visitors to:
- Park responsibly
- Keep Passing Places, the road itself, and farm tracks clear at all times to ensure safe vehicle movement and maintain essential access for residents, emergency services, and road work teams.
We appreciate your understanding and cooperation as we carry out these works. Please accept our apologise for the inconvenience caused.
For enquiries, please contact:
skye.reinforcement@sse.com
Edinbane substation update
Works at Edinbane Substation are expected to restart in the coming weeks, with plans still being finalised. Early activity is likely to include setting up the site compound and welfare facilities, and potential works linked to the borrow pit, subject to planning consent.
As contractors return to site, there will be an increase in traffic from workforce movements and deliveries. One specific activity to note is the delivery of around 44 site cabins to form the new compound. These will be delivered over a short period, with advance notice provided. While the borrow pit at Edinbane Substation is awaiting planning determination, aggregate may need to be brought in by road. Further information on traffic numbers will be shared in due course.
If you have any concerns around access or traffic, or local events we should be aware of, please get in touch. We will continue to share updates as plans are confirmed.
STEM engagement
We recently held a STEM session with pupils from Edinbane and Macdiarmid Primary Schools, giving them hands‑on activities to learn how electricity works and why it matters. The session encouraged teamwork, problem‑solving, and awareness of safety and the environment.
Road works update - U1207 & C1144 Kinloch Hourn Road
We are continuing work on the C1144 and U1207 Kinloch Hourn Road. Traffic management, including stop and go measures and daytime road closures, will remain in place while these works are completed.
- Kinloch Hourn to Quoich Bridge: ongoing daytime weekday closures, Monday to Friday, 8.30am to 5.30pm.
- Quoich Bridge to Kingie: daytime weekday closures from the week commencing 11 May 2026, for up to three weeks (Monday to Friday, 8.30am to 5.30pm).
- Kingie to A87: Short daytime closures at work locations from the week commencing 25 May 2026. Timings will be confirmed closer to the start of works.
Please click here for a map of the locations mentioned above.
This set of overall road works are due to be completed during the week commencing 22 June 2026.
Parking and Access
We recognise this is a popular area for hill walking and apologise for any inconvenience caused by the works, which have resulted in reduced parking availability.
We kindly ask all visitors to:
- Park responsibly
- Keep Passing Places, the road itself, and farm tracks clear at all times to ensure safe vehicle movement and maintain essential access for residents, emergency services, and road work teams.
We appreciate your understanding and cooperation as we carry out these works. Please accept our apologise for the inconvenience caused.
For enquiries, please contact:
skye.reinforcement@sse.com -
Cable Drum Deliveries to Fort Augustus Substation
We wanted to let you know about upcoming cable drum deliveries to a laydown area south of Fort Augustus Substation by Auchterawe as part of the Skye Reinforcement Project.
When and where
- Deliveries are scheduled to take place from Monday to Wednesday next week (13th – 16th April), with six deliveries each day, totalling eighteen over the three-day period.
- They will travel via lorry along the A82 from Inverness, turning toward Auchterawe, to a laydown area adjacent to the site, turning off before the substation. This will be the same route as previous cable drum deliveries carried out earlier this year.
- They are expected to take place during the morning across the 3 days.
The team are coordinating to ensure all logistics run smoothly, including escorts to minimise disruption, however if you have any questions or concerns regarding these deliveries, please do not hesitate to get in touch.
We’d also like to apologise for the limited notice regarding these deliveries and for any inconvenience they may cause as we work to support the progress of the project.
U1207 Closure and C1144 Works
As part of ongoing works in the area, please be advised of the following traffic management arrangements on the C1144 and U1297:
U1207 Road Closure
- Location: U1207 Kinloch Hourn Road West of Quoich Bridge
- Duration: ongoing and until further notice
- Closure Times: Monday to Friday, 08:30–17:30
C1144 works
- Location: C1144 from A87 junction to Quoich Bridge
- Duration: ongoing and until further notice
- Traffic Management: stop/go operations in place in selected locations
- Upcoming periodic and localised closure which may be starting during week commencing 20 April 2026 to allow for surfacing - updates will be made available on this website.
We are aiming to have all roadworks completed by end of May 2026.
Parking and Access
We recognise this is a popular area for hill walking and apologise for any inconvenience caused by the works, which have resulted in reduced parking availability.
We kindly ask all visitors to:
- Park responsibly
- Keep Passing Places, the road itself, and farm tracks clear at all times to ensure safe vehicle movement and maintain essential access for residents, emergency services, and road work teams.
We appreciate your understanding and cooperation as we carry out these works.
For enquiries, please contact:
skye.reinforcement@sse.com -
C1144 Road Works Update - w/c 02 March 2026
Road Works Update – East of Quoich Bridge / KingieTo complete surfacing works, a couple of short road closures will be required East of Quoich Bridge to allow tarring to take place.
Confirmed closure:
- Starting Wednesday 04 March 2026 – just west of Kingie/nr Kingie Lodge
- 4-5 days of full weekday closures, no daytime amnesties, open overnight
Advance notice – end of March 2026:A further 5-day closure will be required at Kingie to complete tarring works.- 5 days of full weekday closure, no daytime amnesties, open overnight
- The school bus will be accommodated.
All road closures run from 08:30 to17:30 on week days. The road closure West of Quoich Bridge also remains in place until further notice. The tarring works will result in additional traffic on the C1144.Stephen Moore, RJ McLeod, can be contacted on 07909 232 507 to discuss urgent residential/business access requirements in advance.
Further details will be shared in advance as dates are confirmed and/or in case of any unforeseen changes to the above. We appreciate the road users' continued patience while we work as quickly as possible to complete all outstanding works.
Please don't hesitate to get in touch on skye.reinforcement@sse.com if you have questions, feedback or concerns. -
WEEKEND CLOSURE 17/18 January 2026- U1207 Kinloch Hourn Road
Please be informed that there will be an emergency weekend closure on the U1207 (just west of Quoich Bridge) on:
Saturday 17 January & Sunday 18 January 2026
09am - 5pm
The weekday closure also remains in place.
Please accept our apologies for the short notice of this weekend closure.
If you have any questions or concerns, please contact skye.reinforcement@sse.com
U1207 West of Quoich Bridge - Road Closure and Access
U1207 West of Quoich Bridge – Road Closure and Access Information
As part of ongoing works in the area, please be advised tha the following road closure remains in place:
Road Closure
Location: U1207 Kinloch Hourn Road West of Quoich Bridge
Duration: From Monday 7 July 2025 until early 2026
Closure Times: Monday to Friday, 08:30–17:30
Parking and Access
We recognise this is a popular area for hill walking and apologise for any inconvenience caused by the works, which have resulted in reduced parking availability.
We kindly ask all visitors to:
Park responsibly
Keep Passing Places, the road itself, and farm tracks clear at all times to ensure safe vehicle movement and maintain essential access for residents, emergency services, and road work teams.
We appreciate your understanding and cooperation as we carry out these works.
For enquiries, please contact:
skye.reinforcement@sse.com -
SSEN Transmission withdraws Broadford planning application for temporary accommodation following community feedback
SSEN Transmission has advised its contractor to withdraw a planning application for a proposed temporary accommodation village near Broadford in Skye to support the workforce involved in building its Skye Reinforcement Project.
You can view the full press release here
SSEN Transmission welcomes tenfold increase in community benefit funding generated by Skye Reinforcement project
SSEN Transmission has today (Tuesday) announced that more than £10m of community benefit funding will be generated by the business’s Skye Reinforcement project, which will replace the existing overhead line between Fort Augustus and Skye.
You can view the full press release here. -
WEATHER DELAY (east of Quoich Bridge)
Due to the recent yellow weather warnings, we’ve had to adjust our plans for the works east of Quioch Bridge.
New Road Closure Dates (applies to east of Quoich Bridge only!):
- Monday 6th, Tuesday 7th & Wednesday 8th October
- 08:30-17:30
Road Open (applies to east of Quoich Bridge only!):- Wednesday 1st, Thursday 2nd & Friday 3rd October
Please note:
🚧 The closure west of Quoich Bridge remains in place throughout, as before.
Many thanks for your understanding as we respond to changing weather condidtions.
Please get in touch via skye-reinforcement@sse.com if you have any questions.
Road Closure Extended to East of Quoich Bridge – One Week Only (29 Sep-03 Oct 2025)
As part of ongoing road works, please note that the current road closure will be extended to begin 1.8 miles east of Quoich Bridge for one week only, from 29 September to 03 October 2025.
Road Closure
Location: U1207/C1144 Kinloch Hourn Road East of Quoich Bridge
Duration: From Monday 29 Sep until 03 Oct 2025
Closure Times: Monday to Friday, 08:00–17:30
From 06 October 2025, the road closure will revert to its original location west of Quoich Bridge (ongoing until Feb 2026).Parking and Access
We recognise this is a popular area for hill walking and apologise for any inconvenience caused by the works, which have resulted in reduced parking availability.
We kindly ask all visitors to:
Park responsibly
Keep Passing Places, the road itself, and farm tracks clear at all times to ensure safe vehicle movement and maintain essential access for residents, emergency services, and road work teams.
We appreciate your understanding and cooperation as we carry out these works.
For enquiries, please contact:
skye.reinforcement@sse.com -
U1207 West of Quoich Bridge – Road Closure Change to Access Times
Since Monday 07 July, a road closure has been in place, located on the U1207 Kinloch Hourn Road West of Quoich Bridge, anticipated to continue until early 2026.
The initial closure times implemented were as follows: Monday to Friday, 08:00–17:30
However, following review from our contractors, as of Monday 28 July, the closure has been pushed back by 30 minutes in the morning to increase the availability of public access.
The updated closure times (as of 28 July) are as follows:
- Monday to Friday, 08:30–17:30
We apologise for any inconvenience caused by these works and hope that the adjusted closure time proves beneficial to road users.
We kindly remind all visitors to please:
- Park responsibly
- Keep Passing Places, the road itself, and farm tracks clear at all times to ensure safe vehicle movement and maintain essential access for residents, emergency services, and road work teams.
We appreciate your understanding and cooperation as we carry out these works.
For enquiries, please contact:
skye.reinforcement@sse.com
Welfare Cabin Delivery to Edinbane- W/C 14 July
Delivery of Welfare Cabins to Edinbane Substation
As part of our ongoing Skye Reinforcement project, this week will see the commencement of a delivery of Welfare Cabins to the Edinbane Substation Site.
The delivery operation for the Welfare setup will begin on Wednesday 16 July and there will be intermittent large delivery traffic for 2-3 weeks following this which may cause some disruption to regular traffic, particularly on Balmeanach Road.
We would be happy to liaise further to address specific concerns and should you require any additional information please get in touch with us at skye.reinforcement@sse.com
C1144/U1207 - Kinloch Hourn Road - works update from 07 July 2026 onwards
U1207 West of Quoich Bridge – Road Closure and Access Information
As part of ongoing works in the area, please be advised of the following:
Road Closure
Location: U1207 Kinloch Hourn Road West of Quoich Bridge
Duration: From Monday 7 July 2025 until early 2026
Closure Times: Monday to Friday, 08:00–17:30
Parking and AccessWe recognise this is a popular area for hill walking and apologise for any inconvenience caused by the works, which have resulted in reduced parking availability.
We kindly ask all visitors to:
Park responsibly
Keep Passing Places, the road itself, and farm tracks clear at all times to ensure safe vehicle movement and maintain essential access for residents, emergency services, and road work teams.
We appreciate your understanding and cooperation as we carry out these works.
For enquiries, please contact:
skye.reinforcement@sse.com -
C1144/U1207 - Kinloch Hourn Road - Road works update - Monday 23 June to Friday 04 July 2025
We would like to inform you that the U1207 Kinloch Hourn Road road will be closed west of Quoich Bridge during the period Monday 23 June and Friday 04 July 2025:
The road is open during the night, Friday afternoon and on Saturday/Sunday. Please find the exact closure times below.
Road Closed (Mon-Thu)
Road Open (Mon-Thu)
08:30 – 12:30
12:30 – 13:30
13:30 – 17:30
17:30 – 08:30
Road Closed (Fri)
Road Open (Fri, Sat, Sun)
08:30 – 12:30
From 12:30 on Friday and all day Sat/Sun
Advance Notice: From 07th July the closure times at the same location will change to full weekday day-time closures (08:00-17:30) without midday amnesties. The road will remain open during the evenings/nights and on weekends.
We thank all road users for passing the road works with care and at the appropriate speed which helps keeping all road users and the workforce safe. Many thanks.Please accept our apologies for the inconvenience these closures may cause and please do not hesitate to get in touch if you have any questions, concerns or feedback.
Maren Ebeling, Community Liaison Manager
Email: skye.reinforcement@sse.com
C1144/U1207 - Kinloch Hourn Road - Road works update - week commencing 16 June 2025
The U1207 Kinloch Hourn Road road will be closed west of Quoich Bridge Monday 16 June – Thursday 19 June 2025 all day with midday amnesty (12:30-13:30) and on Friday 20 June 2025 in the morning only (until 12:30). The road is open during the night, Friday afternoon and on Saturday/Sunday.
We thank all road users for passing the road works with care and at the appropriate speed which helps keeping all road users and the workforce safe. Many thanks.
Please accept our apologies for the inconvenience these closures may cause and please do not hesitate to get in touch if you have any questions, concerns or feedback.
Full Road Closure details :Road Closed (Mon-Thu)
Road Open (Mon-Thu)
08:30 – 12:30
12:30 – 13:30
13:30 – 17:30
17:30 – 08:30
Road Closed (Fri)
Road Open (Fri)
08:30 – 12:30
From 12:30 onwards
Maren Ebeling, Community Liaison ManagerEmail: skye.reinforcement@sse.com
Mobile: 07721 462 330
Planning consent granted for the Skye Reinforcement project
Planning consent granted for the Skye Reinforcement project
SSEN Transmission has welcomed the decision by the Scottish Government to approve its Section 37 consent application for the replacement of the existing overhead line between Fort Augustus and Ardmore on Skye, the ‘Skye Reinforcement’, which will boost energy security and renewable connection to the grid.
The existing, single circuit overhead line is fast reaching the end of its operational life, with its replacement critical to maintaining network reliability and security of supply for homes and businesses along its route and in the Western Isles.
The existing overhead line is operating at its capacity limit, preventing the connection of new renewable electricity in the area. Its replacement will have a greater capacity, enabling the connection of new renewable electricity generation - and will also further strengthen network reliability and security of supply.
The replacement of the overhead line will also require the extension of Broadford and Edinbane Substations.
The full Press Release is available to read here.
C1144/U1207 - Kinloch Hourn Road - Road works update - week commencing 09 June 2025
The roads authority are continuing to undertake essential surfacing works from Loch Coire Schubh in a westerly direction for a length of approximately 1km. These works were programmed for 5 days from but experienced a delayed start due to unforeseen circumstances. The works will now be finishing on Monday 09 June with the tempory closure remaining in place for Monday 09 June.
SSEN Transmission road works will also continue for the remainder of the week. These will be undertaken under day-time closure with midday amnesties.
All road closures are in force to protect the workforce and the public.
Please find below the details of closure
Monday 09 June 2025:
Kinloch Hourn Brae
Day time closure 09:00-17:00, no amnesties
Tuesday 10 June - Friday 13 June 2025:
West of Quoich Bridge
Day time road closure with midday amnesty
Tue-Thur closure: 08:30-12:30 and 13:13-17:30
Fri closure: 08:30-12:30
Please accept our apologies for the inconvenience these works may cause and please do not hesitate to contact us with any quesitons or concerns.
Maren Ebeling,
Community Liaison Manager -
C1144/U1207 - Kinloch Hourn Road - Road works update - week commencing 26 May 2025
Please note that the U1207 road will be closed west of Quoich Bridge on Monday 26 - Thursday 29 May 2025, midday amnesties apply.
We thank all road users for passing the road works with care and at the appropriate speed which helps keeping all road users and the workforce safe. Many thanks.
Please get in touch if you have any questions, concerns or feedback.
Maren Ebeling, Community Liaison Manager
Email: skye.reinforcement@sse.com
Mobile: +44 (0)7721 462 330
Road closure order details for information (enforced locally Monday 26 May 2025 – Thursday 29 May 2025)
Road Closed (Mon-Thu)
Road Open (Mon-Thu)
08:30 – 12:30
12:30 – 13:30
13:30 – 17:30
17:30 – 08:30
Road Closed (Fri)
Road Open (Fri)
08:30 – 12:30
From 12:30 onwards
Road remains open all day Saturday and Sunday.
C1144/U1207 - Kinloch Hourn Road - Road works update - week commencing 02 June 2025
The roads authority are planning to undertake surfacing works from Loch Coire Schubh in a westerly direction for a length of approximately 1km. These works are programmed for 5 days from Monday 02 June to Friday 06 June. The road will be temporarily closed for these essential operational resurfacing works.
Due to the restricted road widths no passing places on the Kinloch Hourn brae these works require a temporary road closure between 0900hrs until 1700hrs with no amnesty opening times. The road closure will be in force to protect the public and the workforce.
Please get in touch if you have any questions.Maren Ebeling, Community Liaison Manager
Email: skye.reinforcement@sse.com
Mobile: +44 (0)7721 462 330
C1144/U1207 - Kinloch Hourn Road - Road works update - week commencing 19 May 2025
There will be no planned closures on the C1144/U1207 during the week commencing 19 May 2025.
Surfacing works west of the Quoich Bridge will be undertaken under Stop/Go traffic management - please accept our apologies for any delays.
We thank all road users for passing the road works with care and at the appropriate speed which helps keeping all road users and the workforce safe. Many thanks.
Please get in touch if you have any questions, concerns or feedback.
Maren Ebeling, Community Liaison Manager
Email: skye.reinforcement@sse.com
Mobile: +44 (0)7721 462 330
C1144/U1207 - Kinloch Hourn Road - Road works update - week commencing 12 May 2025
Please note that the Kinloch Hourn (U1207) road will be closed west of Quoich Bridge on
- Thursday 15 May 2025 08:30-12:30 and 13:30-17:30 and on
- Friday 16 May 2025 08:30-12:30The C1144/U1207 remains open otherwise with all other works undertaken under Stop/Go traffic management. Please expect delays of up to 30mins Monday-Wednesday west of Quoich Bridge
Two machinery deliveries on low loaders are planned for Monday and Tuesday (one each day) - this will cause delays between the A87 and Quoich Bridge.
We thank all road users for passing the road works with care and at the appropriate speed which helps keeping all road users and the workforce safe. Many thanks.Please get in touch if you have any questions, concerns or feedback.
Maren Ebeling, Community Liaison Manager
Email: skye.reinforcement@sse.com
Mobile: +44 (0)7721 462 330
C1144 - Kinloch Hourn Road - Road works update - week commencing 05 May 2025
Please note that the C1144 Kinlochhourn road will be closed 3 miles west of Quoich Bridge on Tuesday 06 May 2025 in the afternoon for approximately 2 hrs from 13:30 due to rock blasting taking place.
The C1144 remains open otherwise with all other works undertaken under Stop/Go traffic management where required. Short delays my occur.
Please note there’s expected to be a planned short delay of up to 20mins near Quoich Bridge on Wednesday afternoon (07 May) due to off-road blasting.We thank all road users for passing the road works with care and at the appropriate speed which helps keeping all road users and the workforce safe. Many thanks.
Please get in touch if you have any questions, concerns or feedback.
Maren Ebeling, Community Liaison Manager
Email: skye.reinforcement@sse.com
Mobile: +44 (0)7721 462 330
-
UPDATE - C1144 - Kinloch Hourn Road - Road works update - week commencing 28 April 2025
Please note that the C1144 Kinloch Hourn Road will be closed WEST OF QUOICH BRIDGE, on the following dates this week:
Tuesday 29 April 2025 (closed in the afternoon only)
Wednesday 30 April 2025 (closed all day with amnesty)
Thursday 01 May 2025 (closed all day with amnesty)
Friday 02 May 2025 (closed in the morning)
The road closure order details are listed below:Road Closed
Road Open
08:30 – 12:30
12:30 – 13:30
13:30 – 17:30
17:30 – 08:30
Road Closed (Fri)
Road Open (Fri)
08:30 – 12:30
From 12:30 onwards
Maren Ebeling
Please accept our apologies for any inconvenience these closures may cause and please get in touch if you have any feedback or concerns regarding these closures.
Community Liaison Manager, skye.reinforcement@sse.com
C1144 - Kinloch Hourn Road - Road works update - week commencing 28 April 2025
Please note that the C1144 will be closed at 2.5 miles west of Quoich Bridge in the afternoon of Tuesday 29 April (12:30-17:30).
The C1144 remains open otherwise with all other works undertaken under Stop/Go traffic management. Short delays my occur.We thank all road users for passing the road works with care and at the appropriate speed which helps keeping all road users and the workforce safe. Many thanks.
Please get in touch if you have any questions, concerns or feedback.
Maren Ebeling, Community Liaison Manager
Email: skye.reinforcement@sse.com
Mobile: +44 (0)7721 462 330
C1144 - Kinloch Hourn Road - Road works update - week commencing 21 April 2025
It is expected that all works on the C1144 will be undertaken under Stop/Go operations during the week commencing 21 April 2025. Please expect short delays, particularly west of Kingie.
We thank all road users for passing the road works with care and at the appropriate speed which helps keeping all road users and the workforce safe. Many thanks.
Please get in touch if you have any questions, concerns or feedback.
Maren Ebeling, Community Liaison Manager
Email: skye.reinforcement@sse.com
Mobile: +44 (0)7721 462 330
C1144 - Kinloch Hourn Road - Road works update - week commencing 14 April 2025
It is expected that all works on the C1144 will be undertaken under Stop/Go operations during the week commencing 14 April 2025. Please expect short delays.
We thank all road users for passing the road works with care and at the appropriate speed which helps keeping all road users and the workforce safe. Many thanks.
Please get in touch if you have any questions, concerns or feedback.
Maren Ebeling, Community Liaison Manager
Email: skye.reinforcement@sse.com
Mobile: +44 (0)7721 462 330
C1144 - Kinloch Hourn Road - Road works update - week commencing 07 April 2025
It is expected that all works on the C1144 will be undertaken under Stop/Go operations during the week commencing 07 April 2025. Please expect short delays.
We thank all road users for passing the road works with care and at the appropriate speed which helps keeping all road users and the workforce safe. Many thanks.
Please get in touch if you have any questions, concerns or feedback.
Maren Ebeling, Community Liaison Manager
Email: skye.reinforcement@sse.com
Mobile: +44 (0)7721 462 330
-
C1144 - Kinloch Hourn Road - Road works update - week commencing 31 March 2025
It is expected that all works on the C1144 will be undertaken under Stop/Go operations during the week commencing 31 March 2025. Please expect short delays, particularly west of Kingie.
We thank all road users for passing the road works with care and at the appropriate speed which helps keeping all road users and the workforce safe. Many thanks.
Please get in touch if you have any questions, concerns or feedback.
Maren Ebeling, Community Liaison Manager
Email: skye.reinforcement@sse.com
Mobile: +44 (0)7721 462 330
C1144 - Kinloch Hourn Road - Road works update - week commencing 24 March 2025
It is expected that all works on the C1144 will be undertaken under Stop/Go operations during the week commencing 24 March 2025. Please expect short delays, particularly west of Kingie.
We thank all road users for passing the road works with care and at the appropriate speed which helps keeping all road users and the workforce safe. Many thanks.
Please get in touch if you have any questions, concerns or feedback.
Maren Ebeling, Community Liaison Manager
Email: skye.reinforcement@sse.com
Mobile: +44 (0)7721 462 330
C1144 - Kinloch Hourn Road - Road works update - week commencing 17 March 2025
We would like to inform the public that the C1144 will be closed west of Quoich Bridge for one hour between 2pm and 4pm on Monday 17th March 2025.
The road remains open at all other times.
We thank all road users for passing the road works with care and at the appropriate speed which helps keeping all road users and the workforce safe. Many thanks.
Please get in touch if you have any questions, concerns or feedback.
Maren Ebeling, Community Liaison Manager
Email: skye.reinforcement@sse.com
Mobile: +44 (0)7721 462 330
C1144 - Kinloch Hourn Road - Road works update - week commencing 10 March 2025
The C1144 will be closed west of Quoich Bridge for one hour between 2pm and 4pm on Wednesday 12th March.The road remains open at all other times.
We thank all road users for passing the road works with care and at the appropriate speed which helps keeping all road users and the workforce safe. Many thanks.
Please get in touch if you have any questions, concerns or feedback.
Maren Ebeling, Community Liaison Manager
Email: skye.reinforcement@sse.com
Mobile: +44 (0)7721 462 330
-
C1144 - Kinloch Hourn Road - Road works update - week commencing 03 March 2025
Road closure information for week commencing 03 March 2025:
- West of Quoich Bridge up to Loch Doire Duibh: The road closure (with amnesties) will be enforced on Monday only (amnesties apply).
- Road failure at Loch Doire Duibh: full road closure all week Mon-Fri 08:30am – 5:30pm, no midday or Friday afternoon amnesties. Road open during the evening/night. Emergency access for blue light vehicles at all times.
We thank all road users for passing the road works with care and at the appropriate speed which helps keeping the workforce safe.
Road Closure Order details:
Road Closed (Mon-Thu)
Road Open (Mon-Thu)
08:30 – 12:30
12:30 – 13:30 *
13:30 – 17:30
17:30 – 08:30
Road Closed (Fri)
Road Open (Fri)
08:30 – 12:30
From 12:30 onwards *
* no midday/early Friday amnesties at Loch Doire Duibhe
Road remains open all day Saturday and Sunday.
“Access will be maintained throughout the closures for: Emergency Services, Postal Services, Waste Collection and School Transport. Other deliveries outside the opening times will be accommodated where possible to do so.“ (The Highland Council, 20 Aug 2024).
Please get in touch if you have any questions, concerns or feedback.
Maren Ebeling, Community Liaison Manager
Email: skye.reinforcement@sse.com
Mobile: +44 (0)7721 462 330
C1144 - Kinloch Hourn Road - Road works update - week commencing 24 February 2025
Due to surfacing works the road will be closed all week (w/c 24 February 2025) between Kingie and Quoich Bridge (amnesties as per the table below).
We thank all road users for passing the road works with care and at the appropriate speed which helps keeping the workforce safe.
Road Closure Order details:
Road Closed (Mon-Thu)
Road Open (Mon-Thu)
08:30 – 12:30
12:30 – 13:30
13:30 – 17:30
17:30 – 08:30
Road Closed (Fri)
Road Open (Fri)
08:30 – 12:30
From 12:30 onwards
Road remains open all day Saturday and Sunday.
“Access will be maintained throughout the closures for: Emergency Services, Postal Services, Waste Collection and School Transport. Other deliveries outside the opening times will be accommodated where possible to do so.“ (The Highland Council, 20 Aug 2024).
Please get in touch if you have any questions, concerns or feedback.
Maren Ebeling, Community Liaison Manager
Email: skye.reinforcement@sse.com
Mobile: +44 (0)7721 462 330
We're here to lend a helping hand
We are committed to supporting the communities in the north of Scotland where we operate, both now and in the future. As part of our ongoing efforts to make a difference and have a positive impact on local communities, we are proud to offer volunteering days to local groups and charities, particularly in the areas that host our electricity infrastructure or where our proposed projects are located.
This month, we’re excited to announce the launch of our new Volunteering Webpage, designed to make it easier for local communities to request volunteering support from us. To request our help, simply complete the ‘Volunteering Nomination Form’ linked at the bottom of our new webpage. Please note, as our team works on a voluntary basis, it may take us some time to coordinate our people and match them with opportunities. We kindly ask for your patience as we work to keep up with volunteering demand.
Thank you for considering SSEN Transmission as a partner in your community efforts. Together, we can leave a positive, lasting legacy and help transform communities across the north of Scotland.
C1144 - Kinloch Hourn Road - Road works update - week commencing 17 February 2025
Due to surfacing works the road will be closed all week (w/c 17 February 2025) between Kingie and Quoich Bridge (amnesties as per the table below)
We thank all road users for passing the road works with care and at the appropriate speed which helps keeping the workforce safe.
Road Closure Order details:
Road Closed (Mon-Thu)
Road Open (Mon-Thu)
08:30 – 12:30
12:30 – 13:30
13:30 – 17:30
17:30 – 08:30
Road Closed (Fri)
Road Open (Fri)
08:30 – 12:30
From 12:30 onwards
Road remains open all day Saturday and Sunday.
“Access will be maintained throughout the closures for: Emergency Services, Postal Services, Waste Collection and School Transport. Other deliveries outside the opening times will be accommodated where possible to do so.“ (The Highland Council, 20 Aug 2024).
Please get in touch if you have any questions, concerns or feedback.
Maren Ebeling, Community Liaison Manager
Email: skye.reinforcement@sse.com
Mobile: +44 (0)7721 462 330
C1144 - Kinloch Hourn Road - Road works update - week commencing 10 February 2025
There are no planned road closures during the week commencing 10 February 2025. All works will be undertaken under stop/go operations where required.
We thank all road users for passing the road works with care and at the appropriate speed which helps keeping the workforce safe.
The road closure order remains in place but will not be enforced w/c 10 February:Road Closed (Mon-Thu)
Road Open (Mon-Thu)
08:30 – 12:30
12:30 – 13:30
13:30 – 17:30
17:30 – 08:30
Road Closed (Fri)
Road Open (Fri)
08:30 – 12:30
From 12:30 onwards
Road remains open all day Saturday and Sunday.
“Access will be maintained throughout the closures for: Emergency Services, Postal Services, Waste Collection and School Transport. Other deliveries outside the opening times will be accommodated where possible to do so.“ (The Highland Council, 20 Aug 2024).
Please get in touch if you have any questions, concerns or feedback.
Maren Ebeling, Community Liaison Manager
Email: skye.reinforcement@sse.com
Mobile: +44 (0)7721 462 330
-
C1144 - Kinloch Hourn Road - Road works update - week commencing 03 February 2025
There are no planned road closures during the week commencing 03 February 2025. All works will be undertaken under stop/go operations where required.
We thank all road users for passing the road works with care and at the appropriate speed which helps keeping the workforce safe.
The road closure order remains in place but will not be enforced w/c 03 February:Road Closed (Mon-Thu)
Road Open (Mon-Thu)
08:30 – 12:30
12:30 – 13:30
13:30 – 17:30
17:30 – 08:30
Road Closed (Fri)
Road Open (Fri)
08:30 – 12:30
From 12:30 onwards
Road remains open all day Saturday and Sunday.
“Access will be maintained throughout the closures for: Emergency Services, Postal Services, Waste Collection and School Transport. Other deliveries outside the opening times will be accommodated where possible to do so.“ (The Highland Council, 20 Aug 2024).
Please contact us if you have any questions, concerns or feedback.
Maren Ebeling, Community Liaison Manager
Email: skye.reinforcement@sse.com
Mobile: +44 (0)7721 462 330
C1144 - Kinloch Hourn Road - Road works update - week commencing 27 January 2025
Please note that this schedule might change at short notice as the team on the road might always face unexpected scenarios. Any significant deviations from the below will be communicated.
Works Update Week Commencing 27 January 2025
C1144 (Kinloch Hourn Road) - timed, localised road closure during the following dates/at the following locations:
Wednesday 29 January - Friday 31 January midday closure between Ardochy Forest Track and Kingie. (Road open during amnesties noted below).
Traffic might also be slightly delayed in other locations due to the road works.
We thank all road users for passing the road works with care and at the appropriate speed which helps keeping the workforce safe.
Works are undertaken under the general Road Closure Order:Road Closed (Mon-Thu)
Road Open (Mon-Thu)
08:30 – 12:30
12:30 – 13:30
13:30 – 17:30
17:30 – 08:30
Road Closed (Fri)
Road Open (Fri)
08:30 – 12:30
From 12:30 onwards
Road remains open all day Saturday and Sunday.
“Access will be maintained throughout the closures for: Emergency Services, Postal Services, Waste Collection and School Transport. Other deliveries outside the opening times will be accommodated where possible to do so.“ (The Highland Council, 20 Aug 2024).
Please direct any access or other enquiries to skye.reinforcement@sse.com -
C1144 Road works - Road Open 20 December - 10 January
There will be no road works during the festive holidays (20 December 2024 - 03 January 2024). The C1144 will be fully accessible during this time.
Works will re-commence week commencing 06th January. There's no planned closure during this week but stop/go operations might be in place in certain locations.
Going forward, any temporary enforcement of the road closure order will be communicated in advance where possible. -
C1144 - CHANGE TO ROAD WORKS SCHEDULE w/c 19 November
Please note: Due to the cold weather access restrictions on the C1144 Kinloch Hourn Road will now run into Thursday 21 November 2024 on bridges Bhiora (10) and Ardochy East (10c19)A map showing the bridge locations can be found here.
Works are undertaken under the general Road Closure Order:
Road Closed (Mon-Thu)
Road Open (Mon-Thu)
08:30 – 12:30
12:30 – 13:30
13:30 – 17:30
17:30 – 08:30
Road Closed (Fri)
Road Open (Fri)
08:30 – 12:30
From 12:30 onwards
C1144 Road Closure- Works update week commencing 18 November 2024
Please find below the the expected/planned work schedule for next week.
Please note that this schedule might change at short notice as the team on the road might always face unexpected scenarios. Any significant deviations from the below will be communicated.
We thank all road users for passing the road works with care and at the appropriate speed which helps keeping the workforce safe.Works Update Week Commencing 18 November 2024
C1144 (Kinloch Hourn Road) - timed, localised road closure during the following dates/at the following locations:
Tuesday 19th November 2024: resurfacing of bridges Chorainn (20), Inchlaggan (30), Tomdoun (40)
Monday 18th November 2024: resurfacing of bridges Aultnaslat (50), ‘Unnamed’ (50c14), Poll-airigh (50c43), Gohbhain (60)
Wednesday 20th November 2024: resurfacing of bridges Bhiora (10), Ardochy East (10c19), Ardochy West (10c60)A map showing the bridge locations can be found here.
Traffic might also be slightly delayed in other locations on the C1144 due to tree cutting works.
Works are undertaken under the general Road Closure Order:Road Closed (Mon-Thu)
Road Open (Mon-Thu)
08:30 – 12:30
12:30 – 13:30
13:30 – 17:30
17:30 – 08:30
Road Closed (Fri)
Road Open (Fri)
08:30 – 12:30
From 12:30 onwards
Road remains open all day Saturday and Sunday.
“Access will be maintained throughout the closures for: Emergency Services, Postal Services, Waste Collection and School Transport. Other deliveries outside the opening times will be accommodated where possible to do so.“ (The Highland Council, 20 Aug 2024).
Please direct any enquiries to skye.reinforcement@sse.com -
C1144 Road Closure- Works update week commencing 04 November 2024
Please find below the expected/planned work schedule for week commencing 04 November 2024.
Please note that this schedule might change at short notice as the team on the road might always face unexpected scenarios. Any significant deviations from the below will be communicated.
We thank all road users for passing the road works with care and at the appropriate speed which helps keeping the workforce safe.Works Update Week Commencing 04 November 2024
C1144 Kinloch Hourn Road:
Tue 05 – Thu 07 November: timed, localised road closure at Poll-arigh bridgeAll other bridge locations are passable with care. A map showing the bridge locations can be found here.
Road Closed (Mon-Thu)
Road Open (Mon-Thu)
08:30 – 12:30
12:30 – 13:30
13:30 – 17:30
17:30 – 08:30
Road Closed (Fri)
Road Open (Fri)
08:30 – 12:30
From 12:30 onwards
Road remains open all day Saturday and Sunday.
“Access will be maintained throughout the closures for: Emergency Services, Postal Services, Waste Collection and School Transport. Other deliveries outside the opening times will be accommodated where possible to do so.“ (The Highland Council, 20 Aug 2024).
Please direct any enquiries to skye.reinforcement@sse.com
C1144 Road Closure- Works update week commencing 28 October 2024
Please find below the the expected/planned work schedule for next week.
Please note that this schedule might change at short notice as the team on the road might always face unexpected scenarios. Any significant deviations from the below will be communicated.
We thank all road users for passing the road works with care and at the appropriate speed which helps keeping the workforce safe.Works Update Week Commencing 28 October 2024
C1144 (Kinloch Hourn Road)
Monday - Wednesday: timed, localised road closure at Gobhain Bridge, with contractors aiming to keep closure to Monday only
Tuesday – Thursday: timed, localised road closure at Alt na H’Eiric Bridge, with contractors aiming to keep closure to Wednesday only
Friday: beam removal works at Poll-airigh Bridge might start, but contractors are expecting road to be kept open on Friday
All other bridge locations are passable with care. A map showing the bridge locations can be found here.
Works are undertaken under the general Road Closure Order:Road Closed (Mon-Thu)
Road Open (Mon-Thu)
08:30 – 12:30
12:30 – 13:30
13:30 – 17:30
17:30 – 08:30
Road Closed (Fri)
Road Open (Fri)
08:30 – 12:30
From 12:30 onwards
Road remains open all day Saturday and Sunday.
“Access will be maintained throughout the closures for: Emergency Services, Postal Services, Waste Collection and School Transport. Other deliveries outside the opening times will be accommodated where possible to do so.“ (The Highland Council, 20 Aug 2024).
Please direct any enquiries to skye.reinforcement@sse.com
C1144 Road Closure- Works update week commencing 21 October 2024
Please find below the expected/planned work schedule for next week and the week after.
Please note that this schedule might change at short notice as the team on the road might always face unexpected scenarios. Any significant deviations from the below will be communicated.
We thank all road users for passing the road works with care and at the appropriate speed which helps keeping the workforce safe.Works Update Week Commencing 21 October 2024
C1144:
Monday/Tuesday/Wednesday: timed, localised road closure at Aultnaslat Bridge
Thursday/Friday: timed, localised road closure at Inshlaggan Bridge
All other bridge locations are passable with care. A map showing the bridge locations can be found here.
Earthworks at Ardochy Access Track will continue on Mon/Tue and might result in increased traffic due to stone deliveries.
Road Closed (Mon-Thu)
Road Open (Mon-Thu)
08:30 – 12:30
12:30 – 13:30
13:30 – 17:30
17:30 – 08:30
Road Closed (Fri)
Road Open (Fri)
08:30 – 12:30
From 12:30 onwards
Road remains open all day Saturday and Sunday.
“Access will be maintained throughout the closures for: Emergency Services, Postal Services, Waste Collection and School Transport. Other deliveries outside the opening times will be accommodated where possible to do so.“ (The Highland Council, 20 Aug 2024).
Please direct any enquiries to skye.reinforcement@sse.com
Glenelg - Upcoming Road Works Notification
This note is to inform about the following upcoming road works in and near the village of Glenelg.
Timing: works are planned to start week commencing 04 November 2024 (for the expected duration of 3 weeks)
Works locations and details:
Road leading from Bernera Bay to the Glenelg Ferry Slipway:- finishing off the road widenings which were started earlier this year
- small section of post and rail fence to secure road edge
C1223 - Road leading to Glenelg:- Extension of one existing layby
Traffic management: All of the above works will be underaken under stop/go operations. Timed, localised road closures might be required for the final laying of tar (any such closures would be communicated in advance).
A small temporary work compound will need to be set up at Bernera Bay, Glengelg, which may result in some additional traffic at the beginning and end of the works.
We thank all road users for their patience and understanding during these works and apologise for any inconvenience these works may cause.
Please direct any enquiries to skye.reinforcement@sse.com
Works update week commencing 14 October 2024 - C1144 Road Closure
Please find below the expected/planned work schedule for next week and the week after.
Please note that this schedule might change at short notice as the team on the road might always face unexpected scenarios. Any significant deviations from the below will be communicated.We thank all road users for passing the road works with care and at the appropriate speed which helps keeping the workforce safe.
Works Update Week Commencing 14 October 2024
C1144:
Monday/Tuesday/Wednesday: timed, localised road closure at Tomdoun Bridge; other bridge locations are passable with care.
Thursday/Friday: timed, localised road closure at Aultnaslat; other bridge locations are passable with care.
A map showing the bridge locations can be found here.
Ardochy Access Track: Earthworks at the access track will result in increased traffic due to stone deliveries.Road Closed (Mon-Thu)
Road Open (Mon-Thu)
08:30 – 12:30
12:30 – 13:30
13:30 – 17:30
17:30 – 08:30
Road Closed (Fri)
Road Open (Fri)
08:30 – 12:30
From 12:30 onwards
Road remains open all day Saturday and Sunday.
“Access will be maintained throughout the closures for: Emergency Services, Postal Services, Waste Collection and School Transport. Other deliveries outside the opening times will be accommodated where possible to do so.“ (The Highland Council, 20 Aug 2024).
Please direct any enquiries to skye.reinforcement@sse.com
Works update week commencing 07 October 2024 - C1144 Road Closure
C1144 KINLOCH HOURN ROAD WORKS
Please find below the expected/planned work schedule for the road works on the C1144 for week commencing 07 October 2024.
Please note that this schedule might change at short notice as the team on the road might always face unexpected scenarios. Any significant deviations from the below will be communicated.We thank all road users for passing the road works with care and at the appropriate speed which helps keeping the workforce safe.
Works Update Week Commencing 07 October 2024
C1144:
Monday/Tuesday: timed, localised road closure at Tomdoun Bridge – other bridge locations are passable with care.
Wednesday/Thursday: timed, localised road closure at Chorainn Bridge – other bridge locations are passable with care.
A map showing the bridge locations can be found here.Ardochy Access Track: Earthworks at the access track will result in increased traffic due to stone deliveries (on average 5 lorries per day Mon-Fri)
Road Closed (Mon-Thu)
Road Open (Mon-Thu)
08:30 – 12:30
12:30 – 13:30
13:30 – 17:30
17:30 – 08:30
Road Closed (Fri)
Road Open (Fri)
08:30 – 12:30
From 12:30 onwards
Road remains open all day Saturday and Sunday.
“Access will be maintained throughout the closures for: Emergency Services, Postal Services, Waste Collection and School Transport. Other deliveries outside the opening times will be accommodated where possible to do so.“ (The Highland Council, 20 Aug 2024).
Please direct any enquiries to skye.reinforcement@sse.com
Glengarry and Glenelg - Ground Investigation Works
Our contractors Balfour Beatty are planning to undertake some Ground Investigation works (GI works) in the Glengarry and Glenelg area. These works are scheduled to start week commencing 7th October 2024 and are expected to run over an eight week period. The programme and a map are available on the respective links.
The works will be undertaken at bridge locations on access tracks. We do not expect these works to have any significant impact on local communities.The works are called ‘Slit Trenching’ - Slit Trenching is the process of creating a narrow trench using an excavator to determine the underlying ground conditions. This information is then used to inform the final design of transmission line and associated access.
Please address any questions to skye.reinforcement@sse.com
-
Works update week commencing 30 September 2024 - C1144 ROAD CLOSURE
C1144 KINLOCH HOURN ROAD WORKS
Please find below the expected/planned work schedule for the road works on the C1144 for week commencing 30 September 2024.
Please note that this schedule might change at short notice as the team on the road might always face unexpected scenarios. Any significant deviations from the below will be communicated.We also thank all road users for passing the road works with care and at the appropriate speed which helps keeping the workforce safe.
Works Update Week Commencing 30 September 2024C1144: timed, localised road closure at Tomdoun Bridge – other bridge locations are passable with care. Timings of closure below, for a map see here.
C1144: Earthworks at Ardochy Access Track will result in increased traffic due to stone deliveries (on average 5 lorries per day Mon-Fri)
Road Closed (Mon-Thu)
Road Open (Mon-Thu)
08:30 – 12:30
12:30 – 13:30
13:30 – 17:30
17:30 – 08:30
Road Closed (Fri)
Road Open (Fri)
08:30 – 12:30
From 12:30 onwards
Road remains open all day Saturday and Sunday.
“Access will be maintained throughout the closures for: Emergency Services, Postal Services, Waste Collection and School Transport. Other deliveries outside the opening times will be accommodated where possible to do so.“ (The Highland Council, 20 Aug 2024).
Please direct any enquiries to skye.reinforcement@sse.com
Works update week commencing 23 September 2024 - C1144 ROAD CLOSURE
C1144 KINLOCH HOURN ROAD WORKS
Please find below the expected/planned work schedule for the road works on the C1144 for the week commencing 23 September 2024.
Please note that this schedule might change at short notice as the team on the road might always face unexpected scenarios. Any significant deviations from the below will be communicated.
Key change to note from previous weeks: With immediate effect the road now remains open for the weekends from FRIDAYS 12:30 (Stop/Go operations might be in place on Friday afternoons).
Week commencing 23 September 2024:C1144 Monday-Thursday: timed, localised road closure between (an including) the bridges Ardochy East and Inchlaggan (map)
C1144 Friday: timed, localised road closure between (an including) the bridges Ardochy East and Tomdoun (map)
Road Closed (Mon-Thu)
Road Open (Mon-Thu)
08:30 – 12:30
12:30 – 13:30
13:30 – 17:30
17:30 – 08:00
Road Closed (Fri)
Road Open (Fri)
08:30 – 12:30
From 12:30 onwards
Road remains open all day Saturday and Sunday.
“Access will be maintained throughout the closures for: Emergency Services, Postal Services, Waste Collection and School Transport. Other deliveries outside the opening times will be accommodated where possible to do so.“ (The Highland Council, 20 Aug 2024).
Please direct any enquiries to skye.reinforcement@sse.com
Works update w/c 16 September 2024 - ROAD CLOSURE
C1144 KINLOCH HOURN ROAD WORKS
Please find below the expected/planned work schedule for the road works on the C1144 for the week commencing 16 September 2024.
Please note that this schedule might change at short notice as the team on the road might always face unexpected scenarios. Any significant deviations from the below will be communicated.The road closures will unfortunately need to be much more strictly enforced from this week onwards as the contractors are moving to the beam removal works which requires them to open up the entire road surface.
Week commencing 16 September 2024:
C1144: timed, localised road closure between (an including) the bridges ‘Ardochy East’ and ‘Aultnaslat’ (for a map see here)Road Closed (Mon-Fri)
Road Open (Mon-Fri)
08:30 – 12:30
12:30 – 13:30
13:30 – 17:30
17:30 – 08:00
Road remains open all day Saturday and Sunday.
“Access will be maintained throughout the closures for: Emergency Services, Postal Services, Waste Collection and School Transport. Other deliveries outside the opening times will be accommodated where possible to do so.“ (The Highland Council, 20 Aug 2024).
Please direct any enquiries to skye.reinforcement@sse.com
Works update for week commencing 09 September 2024 - ROAD CLOSURE
Work Update for week commencing 09 September 2024
C1144: From Tuesday 03 September - bridge strengthening works under temporary localised road closure with timed openings as follows:
Road Closed
Road Open
08:30* – 12:30
12:30 – 13:30
13:30 – 17:30
17:30 – 08:00
*Please note: the morning road closure has been delayed from 8am to 8.30 am to allow for local requirements based on feedback recieved.
“Access will be maintained throughout the closures for: Emergency Services, Postal Services, Waste Collection and School Transport. Other deliveries outside the opening times will be accommodated where possible to do so.“ (The Highland Council, 20 Aug 2024).
RJ MacLeod will minimise actual closure times as much as possible and will do their utmost to remain flexible where possible during closure times. We would be grateful for your assistance and if you could schedule any deliveries and travel accordingly where possible.
During the week commencing 09 September:
- Access will be maintained throughout the for the services mentioned in the Highland Council notice, including emergency services.
- RJ mcleod carrying out scaffolding works on C1144 Road beginning at entrance to C1144 Road A9 Access installing scaffold on bridges
- Loch Ness tree surgeons carrying out devegging works at various locations on C1144 for bridge works
- The road will be open all weekend (14/15 Sep) – Stop/Go operation might be in place during the weekend.
During the week commencing the 09 September works will be carried out in the following areas:
- Bhiora C11440010
- Ardochy East C11440010c19
- Ardochy west Bheithe C11440010c60
- Chorainn C11440020
- Inchlaggan C11440030
- Tomdoun C11440040.
The road will remain open to the East of ‘Bhiora’ bridge and to the West of ‘Ardochy East’ bridge.
For any questions please contact:
skye.reinforcement@sse.com -
Works udpate for week commencing 02 September 2024 - ROAD CLOSURE
Works pdate for week commencing 02 September 2024
C1144: From Tuesday 03 September - bridge strengthening works under temporary localised road closure with timed openings
The Highland Council road closure order reads as follows:
Road Closed
Road Open
08:00 – 12:30
12:30 – 13:30
13:30 – 17:30
17:30 – 08:00
“Access will be maintained throughout the closures for: Emergency Services, Postal Services, Waste Collection and School Transport. Other deliveries outside the opening times will be accommodated where possible to do so.“ (The Highland Council, 20 Aug 2024).
During the week commencing 02 September:
- The first day of closure is Tuesday 03 September 2024 (Road open Monday 02 September but possibly stop/go operations that day)
- The road will be open all weekend (07/08 Sep) – Stop/Go operation might be in place during the weekend.
- Access will be maintained throughout the for the services mentioned in the Highland Council notice, including emergency services.
During the week commencing the 02 September the following bridges will be worked on:
- Bhiora
- Ardochy East
The road will remain open to the East of ‘Bhiora’ bridge and to the West of ‘Ardochy East’ bridge.
For any questions please contact:
skye.reinforcement@sse.com
Works update for week commencing 12 August 2024
Works Update week commencing 12 August 2024
Please note: the planned work schedule below might be subject to change at short notice.
Glengarry (Section 4 & 5)
Faichemard Camping: Access track maintenance works to be finalised, start of start of demobilisation from site.
Kinloch Hourn Road C1144: Localised Road Closure East of Inshlaggan on 15 August, no access between 8am-5pm.
Kinloch Hourn Road C1144: West of Kingie, Trial Pit works under Stop/Go operation at two locations, short delays of up to 15mins max possible.
Glenelg/Arnisdale (Section 4)
Moyle/Ratagan: establishment of small welfare compound, vegetation clearance
For any questions please contact:
skye.reinforcement@sse.com -
Works Update week commencing 29 July 2024
Works Update week commencing 29 July 2024
Please note: the planned work schedule below might be subject to change at short notice.
Glengarry (Section 4 & 5)
Faichemard Camping: Access track maintenance works – works expected to be completed by 09 August 2024
Kinloch Hourn Road C1144: no road works week commencing 29 July 2024
Kingie Site Compound: The Delivery of a water tank on Monday 29 August is expected to be the last sizeable delivery. Further installation work ongoing on site.
*Advance notice* for the Kinloch Hourn Road C1144: Traffic Management in form of localised road closures are expected to come into force from w/c 5 August 2024. Further details will be provided as soon as they have been confirmed.
Edinbane (Section 1)
Substation: Archaeological works ongoing. (Start date 15 July, expected duration 3-4weeks)
For any questions please contact:
skye.reinforcement@sse.com
Works Update week commencing week 22 July 2024 (** last updated Mon 22 Jul)
Works Update week commencing 22 July 2024
Please note: the planned work schedule below might be subject to change at short notice.
Glengarry (Section 4 & 5)
Faichemard Camping: Access track maintenance works – Works on going.
Kinloch Hourn Road C1144: no works this week
Kingie Site Compound: potential set up of site compound (delivery of cabins) - ** now confirmed for Tuesday 23 July , please expect increased traffic and low loaders on the C1144 and approach roads.
Edinbane (Section 1)
Substation: Archaeological works commenced 15/07/24, in the area surrounding Edinbane Substation. Expected to last 3 weeks.
For any questions please contact:
skye.reinforcement@sse.comProject Update w/c 15 July 24
Works Update week commencing 15 July 2024
Please note: the planned work schedule below might be subject to change at short notice.
Glengarry (Section 4 & 5)
Faichemard Camping: Access track maintenance works – Works on going.
A87 Crossing: Access track maintenance works – Work Completed
Kinloch Hourn Road C1144: ground investigations around retaining road infrastructure (walls, gabion baskets); work locations will be under traffic management (stop/go operations); short delays possible west of Kingie. No road closures. Starting 04/07 – Work Ongoing
Glenelg and Arnisdale (Section 4)
Bernera Bay Site Compound: removal of cabins complete; final site clearance ongoing – Site cleared and removed.
Kyleakin (Section 3)
Kyle Farm (off A87): Access track maintenance works complete and site demobilised.
Sconser (Section 2)
Moll Road: Road Works, open for access only. Tarring of road completed, reinstated works ongoing.
For any questions please contact:
skye.reinforcement@sse.com
Works Update W/C 08 July 2024
Please note: the planned work schedule below might be subject to change at short notice.
Glengarry (Section 4 & 5)
Faichemard Camping: Access track maintenance works – Works on going.
Munerigie: Access track maintenance works – Works on going, completed by 12/07.
A87 Crossing: Access track maintenance works – Works on going, completed by 12/07.
Kinloch Hourn Road C1144: ground investigations around retaining road infrastructure (walls, gabion baskets); work locations will be under traffic management (stop/go operations); short delays possible west of Kingie. No road closures. Starting 04/07.
Glenelg and Arnisdale (Section 4)
Bernera Bay Site Compound: removal of cabins complete; final site clearance ongoing – Site cleared and removed
Kyleakin (Section 3)
Kyle Farm (off A87): Access track maintenance works complete. Site to be demobilised. – Site gone.
Sconser (Section 2)
Moll Road: Road Works, open for access only. RJM to commence taring road at Moll, 04/07.
Drone Survey: Possibility of a drone survey taking place (weather dependant)For any questions please contact:
skye.reinforcement@sse.com -
Works Update w/c 01 July 2024
Please note: the planned work schedule below might be subject to change at short notice. Further information on work locations are available in the works document section.
Glengarry (Section 4 & 5)
Faichemard Camping: Access track maintenance works.
Munerigie: Access track maintenance works.
A87 Crossing: Access track maintenance works.
Kinloch Hourn Road C1144: ground investigations around retaining road infrastructure (walls, gabion baskets); work locations will be under traffic management (stop/go operations); short delays possible west of Kingie. No road closures.
Glenelg and Arnisdale (Section 4)
Bernera Bay Site Compound: removal of cabins complete; final site clearance ongoing.
Kyleakin (Section 3)Kyle Farm (off A87): Access track maintenance works complete. Site to be demobilised.
Sconser (Section 2)Moll Road: Road Works, open for access only.
For any questions please contact:
Maren Ebeling, Community Liaison Manager
skye.reinforcement@sse.com
Works Update w/c 24 June 2024
Please note: the planned work schedule below might be subject to change at short notice.
Glengarry (Section 4 & 5)
Faichemard Camping (off A87): Access track maintenance works continue.
Kinloch Hourn Road C1144: Road works delayed. The road will remain open all week (please note this only refers to SSEN Transmission works).
Glenelg and Arnisdale (Section 4)
Bernera Bay Site Compound: Removal of cabins planned for Monday 24 June and Tuesday 25 June.
Kyleakin (Section 3)
Kyle Farm (off A87): Access track maintenance works. To be completed this week.
Sconser (Section 2)
Moll Road: Road Works, open for access only.
For any questions please contact:
Maren Ebeling, Community Liaison Manager
skye.reinforcement@sse.com
Works Update w/c 17 June 2024
Please note that the below is the planned work schedule which might be subject to change at short notice.Glengarry (Section 4 and 5)
Faichemard Camping (off A87): Access track maintenance works continue.
Kinloch Hourn Road C1144: Road works delayed. The road will remain open all week (please note this only refers to SSEN Transmission works).
Glenelg/Arnisdale (Section 4)
Moyle/Ratagan: Clearing of windfall timber to be completed this week.
Kyleakin (Section 3)
Kyle Farm (off A87): Access track maintenance works continue.
Broadford and Strath (Section 2 and 3)
Broadford Substation: Drone Survey work, 18-19 June 2024 (weather dependent).
Sconser (Section 2)
Moll Road: Road Works, open for access only.
Struan (Section 0/1)
Edinbane Substation: Drone Survey work, 17-19 June 2024 (weather dependent).
For any questions please contact:Maren Ebeling, Community Liaison Manager
skye.reinforcement@sse.com
Works Update w/c 10 June 2024
Please note that the below is the planned work schedule which might be subject to change at short notice.
Glengarry (Section 4 and 5)Faichemard Camping (off A87): Access track maintenance works continue. Further information on location here.
A87 (between Glengarry and Glengarry Viewpoint East): Bellmouth surveys; temporary traffic management might be in place to protect workforce. Short delays possible. Further information on locations available here.
Kinloch Hourn Road, C1144: Road works delayed. The road will remain open all week (please note this only refers to SSENT works).
Glenelg/Arnisdale (Section 4)Moyle/Ratagan: Access track maintenance work to start. Further information on location here.
Kyleakin (Section 3)Kyle Farm (off A87): Access track maintenance works continue. Further information on location here.
Sconser (Section 2)Moll Road: Road Works; road open for access only.
Sligachan: Drone survey works.
For any questions please contact:Maren Ebeling, Community Liaison Manager
skye.reinforcement@sse.com -
Works Update w/c 27 May 2024
Please note that the below is the planned work schedule which might be subject to change at short notice.
Invergarry (Section 4 and 5)Kinloch Hourn, Road C1144: Road works delayed. The road will remain open all week (please note this only refers to SSENT works).
Access Track, Faichemard Camping (off A87): Access Track Works taking place during the course of the week.
Quoich Bridge loop track: The plant will be delivered to site during the course of the week.
Glenelg (Section 4)Track at Beolary: Works finished; plant moved to Bernera Bay site compound from where it will be picked up early in the week. Pick up of plant using low loaders (planned Mon/Tue).
Bernera Bay: Welfare units now ready for movement. Pick up dates will be advised as soon as possible.
Broadford (Section 3)Proposed Accommodation Village site: Ground investigation work to inform environmental assessments. One digger on site.
Sligachan (Section 2)A87: Core trialling (continued). Traffic Management by ALBA, please expect short delays.
Sligachan:Drone Survey work (continued).
Look aheadInvergarry/Kinloch Hourn Road (Section 4 and 5): w/c 24 June transport of drilling rig.
For any questions please contact:Maren Ebeling, Community Liaison Manager
skye.reinforcement@sse.com
Works Update for week commencing 20 May 2024
Please note that the below is the planned work schedule which might be subject to change at short notice.
Invergarry (Section 4 and 5)Kinloch Hourn, Road C1144: Road works delayed. The road will remain open all week (please note this only refers to SSENT works).
Access Track, Faichemard Camping (off A87): Survey work taking place during the course of the week.
Glenelg (Section 4)Track at Beolary: Finalising capping works. Expected to be finished by Wed/Thu.
Bernera Bay: Welfare unit movement delayed. No activity this week.
Sligachan (Section 2)
A87: Core trialling (continued). Traffic Management by ALBA, please expect short delays.
Sligachan: Drone Survey work.
For any questions please contact:Maren Ebeling, Community Liaison Manager
skye.reinforcement@sse.com -
Ofgem’s decision to approve the Final Needs Case for the Fort Augustus to Skye Reinforcement Project
Following Ofgem’s decision to approve the Final Needs Case for the Fort Augustus to Skye Reinforcement Project, SSEN Transmission’s Managing Director Rob McDonald said:
“The existing Fort Augustus to Skye overhead line is fast reaching the end of its operational life, as demonstrated by two major faults in recent months which resulted in the temporary loss of power to over 20,000 customers along its route and in the Western Isles, which is supplied by two subsea cables from north Skye.
“Alongside the need to keep the lights on for homes and businesses along its route and in the Western Isles, the replacement line will also increase the capacity of the local electricity transmission network to enable the connection of new renewable electricity generation along its route. The need for this project is therefore beyond doubt and we welcome Ofgem’s final approval of need following its assessment of our robust Final Needs Case.
“We now look forward to the Scottish Government’s determination of our Section 37 planning application and remain committed to work constructively with all stakeholders to ensure the timely delivery of this critical local and national infrastructure, building on our proud heritage of powering the highlands and islands as we continue to deliver a network for net zero emissions and secure future electricity supplies across the north of Scotland.”
View Ofgem's Final Needs Case decision here
Please note that the regulatory Needs Case for the project is very much seperate to the Section 37 planning approval process, which is still under consideration by the Scottish Government's Energy Consents Unit. -
Section 37 Additional Information
Following the Section 37 application for the Skye Reinforcement Project to the Energy Consents Unit (ECU) in October 2022, four pieces of additional information has been submitted to support the application.
These additional pieces include four alternative viewing angles from Kylerhea village and Bealach, a Peat Data Report, corrected figures rectifying some inaccuracies within the forestry chapter of the EIA, and a Derogation Case submitted in relation to Section 3 (Broadford to Kyle Rhea).
The documents can be viewed on the ECU website or via the 'Project Documents' tab on the left hand site of this webpage. -
Section 37 Submission
SSEN Transmission has now applied to the Scottish Ministers for consent under Section 37 of the Electricity Act 1989 to install and keep installed approximately 160km of new overhead line and underground cabling between the existing Ardmore substation located approximately 30km northwest of Portree, to the existing Fort Augustus substation located approximately 2.5km west/southwest of Fort Augustus. This includes 110km of new double circuit 132kV overhead line supported by steel lattice towers between Fort Augustus and Broadford, 27km of new single circuit 132kV overhead line supported by trident wood poles (H poles) between Broadford and Ardmore substation, and approximately 24km of double circuit 132kV underground cable. If you wish to view the Section 37 application that we have submitted, for the overhead line, you can view each of the individual documents which make up this application in our Project Documents tab on the left hand side of this page. This can be viewed via the link below. You can also view the Section 37 application on the Energy Consents Unit’s website https://www.energyconsents.scot/ The application reference is: ECU00003395
Thank you for sharing your views
Thank you for sharing your views with us
We recently launched a pre-application consultation exhibition to gain views and feedback on our proposals for Broadford Substation reinforcement and extension and Edinbane Substation reinforcement and extension.
The proposed substation works are an integral part of the Skye Reinforcement scheme, which will ensure security of supply to homes and businesses and facilitate the connection of renewable energy generation across the region. During our drop-in events held in Skeabost and Broadford on 8th September 2022, attendees were able to view key project information about our substation reinforcement and extension proposals, ask questions to the project team and share feedback ahead of submission of planning applications.
We also hosted an online Virtual Consultation Event on Monday 12th September.
Our feedback period closed on Friday 07th October, and we would like to extend thanks to all those who took the time to attend an event, or provide feedback to the team.
-
Public Consultation Events - Broadford and Edinbane Substations
We are launching a pre-application consultation exhibition to gain views and feedback on our proposals for Broadford and Edinbane Substation reinforcement and extensions. The consultation eventswill be taking place on:Thursday 8th SeptemberSkeabost Memorial Hall,10:00 – 13:00Broadford Village Hall,15:00 – 19:00. We shall also be hosting an online virtual consultation event on Monday 12th September between 5-7pm which can be accessed from the project webpage prior to the event. -
Final Needs Case Submission
SSEN Transmission has submitted to the energy regulator, Ofgem, a Final Needs Case (FNC) for the proposed replacement of the existing Fort Augustus to Skye electricity transmission line, moving towards the final stages of the regulatory funding approvals process for the proposed project. -
Report on Consultation - Alignment Selection Skye Reinforcement Project March 2022
Report on Consultation - Alignment Selection Skye Reinforcement Project March 2022This report has been prepared to provide a summary of the responses received from stakeholders (including statutory and non-statutory consultees, local communities, landowners and individual residents) during consultation between September 2021 and January 2022 in response to the preferred alignment and design solution identified for the proposed Skye Reinforcement Project between Fort Augustus Substation and Ardmore Substation on the Isle of Skye. The report can be viewed under the Project Documentation tab. -
Alignment Public Consultations
Following virtual consultations that we held in June 2020 where we presented our preferred route for the replacement overhead line (OHL) that runs from Fort Augustus to Ardmore in the north of Skye, we are pleased to now be hosting the next round of consultations across dates in September and October where we will present our proposed alignment.To find out where the consultations are taking place and to complete a feedback form on our proposals please visit the project overview page by clicking on the link below. -
Virtual Consultation Events
To continue engagement on the Skye Reinforcement project, SSEN Transmission has developed an online consultation tool, to enable the local community to experience the full exhibition from home on a computer, tablet or mobile device. The online exhibition has been designed to look and feel like a real consultation in a community hall, with exhibition boards, maps, interactive videos and the opportunity to share views on the proposals.Visitors will be able to engage directly with the project team, via a live chat function, where they can ask any questions they might have about the project and share their feedback on the current proposals. The virtual consultation events will be taking place as follows:9 June 2020 14:00 - 16:0010 June 2020 10:00 - 12:0011 June 2020 18:00 - 20:00 -
Public Consultation Events Postponed
In line with Government and medical advice regarding Covid-19, SSEN Transmission has taken the decision to limit external engagement activities. We therefore took the decision to postpone our planned engagement events for the Skye Reinforcement Project. The four events that were scheduled to take place in Skye on 16th to 19th March and those scheduled to take place in the Great Glen 24th -26th March will not go ahead. We would like to apologise for the postponement of our consultation events and will be in touch with information once they have been rearranged.Although we will not be holding the events all the materials from the planned events, presenting our proposals, is available to be downloaded from the project documentation section of this webpage .Consultation is central to the development of our projects, it is an opportunity to share our proposals with the community and hear their views. Without this valuable feedback, we would be unable to progress projects and reach a balanced proposal. We would like to reassure the local community that by postponing our planned events the opportunity to provide their feedback has not been missed. SSEN Transmission takes its responsibilities as a provider of a critical national infrastructure very seriously. The SSE group has taken steps to protect colleagues, key sites and to maintain the effectiveness of teams. We are keeping a watching brief and have a comprehensive structure firmly in place and key personnel meeting daily to reassess the situation. All of the measures we take will be guided by government advice, and our decisions will meet the overriding objective of maintaining our key operations, taking good care of our colleagues, stakeholders and the communities we serve.The consultation events in the following locations have been cancelled:• Dunvegan Hall, Dunvegan: Monday 16 March 2020, 3pm – 7pm• Aros Centre, Portree: Tuesday 17 March 2020, 3pm – 7pm• Broadford Village Hall, Broadford: Wednesday 18 March 2020, 3pm – 7pm• Kyleakin Community Hall, Kyleakin: Thursday 19 March 2020, 3pm – 7pm• Glengarry Community Hall, Glengarry: Tuesday 24 March 2020, 3pm – 7pm• Glenelg Community Hall, Glenelg: Wednesday 25 March 2020, 3pm – 7pm• Fort Augustus Village Hall, Fort Augustus: Thursday 26 March 2020, 3pm – 7pm
Public Consultation Events
SSEN Transmission is holding a series of Public Consultation Events across Skye and the Highlands to gain views and feedback on our proposals to reinforce the high voltage electricity network, from Ardmore on the Isle of Skye, to Fort Augustus. Come meet us on the following dates to hear more about the project and provide feedback: Dunvegan Hall, DunveganMonday 16 March 20203pm – 7pmAros Centre, PortreeTuesday 17 March 20203pm – 7pmBroadford Village Hall, BroadfordWednesday 18 March 20203pm – 7pmKyleakin Community Hall, KyleakinThursday 19 March 20203pm – 7pmGlengarry Community Hall, GlengarryTuesday 24 March 20203pm – 7pmGlenelg Community Hall, GlenelgWednesday 25 March 20203pm – 7pmFort Augustus Village Hall, Fort AugustusThursday 26 March 20203pm – 7pm
Documents
Project route maps
-
Route Map - 1 of 3
- Type:
- Date:
- 09 October 2026
- Size:
- 9.4 MB
The route map for the project, as applied for in our Section 37 Application. Part 1 of 3.
-
Route Map - 2 of 3
- Type:
- Date:
- 09 October 2026
- Size:
- 6.9 MB
The route map for the project, as applied for in our Section 37 Application. Part 2 of 3.
-
Route Map - 3 of 3
- Type:
- Date:
- 09 October 2026
- Size:
- 7.3 MB
The route map for the project, as applied for in our Section 37 Application. Part 3 of 3.
Planning application information
Our projects are subject to planning consents. For this project we have received Section 37 (S37) planning consent to reinforce the overhead power line, and Town and Country (T&C) planning consent for substations. Links to the planning submission and associated documents can be found through the following links to the relevant planning authorities:
Overhead power line - Section 37 planning application
There will be further planning applications required as this project progresses, and we will update this section with relevant planning application information when it becomes available.
Community Liaison Group information
-
Skye North CLG - Meeting 1 - Agenda and Slide Pack - 22 April 2026.pdf
- Type:
- Date:
- 16 September 2026
- Size:
- 901.6 KB
Community Liaison Group Meeting Agenda and Slide Pack March 2026
-
Skye North CLG - Meeting 1 - Minutes - 22 April 2026.pdf
- Type:
- Date:
- 16 September 2026
- Size:
- 140.9 KB
Community Liaison Group Meeting Minutes April 2026
-
Broadford CLG - Meeting 5 - Minutes - 19 March 2026.pdf
- Type:
- Date:
- 16 September 2026
- Size:
- 312.9 KB
Community Liaison Group Meeting Minutes March 2026
-
Volume 3 - Figure V1-1.1 - Overview of Proposed Development.pdf
- Type:
- Date:
- 16 September 2026
- Size:
- 8.1 MB
Local benefits
Local benefits
Community Benefit Funding
Volunteering support
Employment opportunities
Looking after nature
FAQs
Frequently Asked Questions (FAQs)
-
It’s the highest voltage electricity network in the UK – the ‘motorway network’ of the energy world. It transmits large quantities of electricity over long distances via wires carried on a system of mainly metal towers (pylons) and large substations. Transmission voltages in Scotland are 132kV, 275kV and 400kV. Larger generation schemes usually connect to the Transmission system.
The lower voltage parts of the system are called distribution networks. In Scotland, these local networks operate below 132kV whereas in England the distribution network includes 132kV.
-
SSEN Transmission is responsible for maintaining and investing in the electricity transmission network in the north of Scotland and our network extends over a quarter of the UK’s land mass, crossing some of its most challenging terrain.
Our operating area is home to vast renewable energy resources, and this is being harnessed by wind, hydro and marine generation. Working closely with National Grid Electricity System Operator (the 'ESO'), we enable electricity generators to connect to the transmission system, allowing the electricity generated by them to be transported to areas of demand across the country. -
Following a minority stake sale which completed in November 2022, SSEN Transmission is now owned 75% by SSE plc and 25% by Ontario Teachers’ Pension Plan Board.
SSE plc sold its UK domestic electricity and gas retail business, along with domestic energy services to OVO Energy in January 2020 and no longer manages these customer accounts.
-
As a stakeholder-led business, throughout the life of our projects, we aim to work positively with local communities and keep people informed about what we are doing. This is particularly important when we are developing new projects, we want to understand what local people think about our plans.
We always endeavour to take the time to discuss our proposals with local community councils and the wider affected community and to carry out engagement throughout each of the development stages, listening to feedback before finalising project plans. The feedback we receive is vital to help us develop proposals that reflect the views of a variety of stakeholder.
-
To find out more about a project, visit our project web pages which can be searched by location or area. Each project has a dedicated Community Liaison Manager that you can contact. You can find their contact details in the individual project pages, where you can also sign up to project updates.