Lochay 132/11kV Transformer Replacement
- Type:
- Transmission reinforcement
- Location:
- Stirling
- Rating:
- 132kV
Upgrading Lochay power station by replacing old transformers, powering the future and supporting the transmission network.
Overview
Status: Construction Phase
Stage 4 of 5
-
Stage 1: Project Assessment: (Completed)
During the Project Assessment stage, we’re committed to evaluating potential project strategies. At this stage, we provide information about the proposed project plans on our website for stakeholders to review and provide feedback on, as well as holding in-person events within the local community demonstrating our collaborative approach to the project's development.
-
Stage 2: Early Development: (Completed)
During Early Development, we concentrate on refining the project details, based on our initial assessment of key environmental, technical, and economic factors to identify the best performing approach. We would like to gain further input from communities through accessible in-person and in some cases online consultations, which are crucial in refining our plans and strategies before advancing to the application stage.
-
Stage 3: Project Refinement: (Completed)
The Project Refinement stage is where we finalise project plans and submit the required planning applications to the relevant planning authorities. Communities and other key stakeholders can provide feedback directly to the appropriate body such as their local council and constituent representatives.
-
Stage 4: Construction Phase: (In progress)
Within the construction phase we mobilise our workforce, contractors, and necessary equipment to begin construction. We maintain open channels of communication, allowing communities and stakeholders to submit feedback on the construction activities to our dedicated Community Liaison Managers, ensuring ongoing engagement to any thoughts or concerns while we carry out work in the area.
-
Stage 5: Operational Phase:
At this final stage, the project successfully moves into the operational phase, with the surrounding environment restored to its original state or better. Our Community Liaison Mangers continue to be available to address any questions or concerns, ensuring a lasting positive impact and strong community relations even after the construction activities conclude.
About the Project
The two 25MVA 132/11kV grid transformers at Lochay Power Station were manufactured in 1958 and form an important part of our transmission network. The power station is supplied from the Killin 132/33kV Grid Substation through the 132kV single overhead line.
These transformers have reached their intended operational capabilities, and recent condition assessments indicate the need to replace both transformer units.

Why is the Project Required?
We have a licence obligation to invest in our existing assets to maintain network health and condition. We also have a statutory duty under the Electricity Safety Quality and Continuity Regulations 2002 to ensure that the electricity transmission network is fit for purpose.
The decision making process for asset replacement takes into account both the criticality and condition of existing assets. Criticality is a representation of the risk to stakeholders with respect to safety, environment and reliability. The decision making process has been agreed with the regulatory stakeholders and has been taken into account in prioritising the Lochay transformers for further assessment and asset replacement.

Community Engagement
Throughout the life of our projects, we aim to work positively with local communities and keep people informed about what we are doing. This is particularly important when we are developing a proposal and we want to understand what local people think about our plans.
We endeavour to take the time to discuss proposals with local community councils, encourage engagement from the wider community and listen to the feedback we receive.
We will do our best to answer any questions and address issues or concerns that are raised with us.
When our project progresses into construction, we will continue working closely with the local community to ensure that our work has as little impact on the lives of those living and working in the area and as many long term positive effects as possible.

How we’re embracing artificial intelligence (AI)
We intend to use AI to assist our experienced teams in the analysis of your feedback, so we can categorise key points raised more quickly. You can learn more about how we’re utilising AI on this dedicated web page.
Project Updates
Featured updates
Featured updates for this project
Upcoming Works
Project updates
-
SSEN Transmission publishes new economic analysis highlighting transformative growth potential of £29bn grid investment programme
We have today published a new economic report setting out the significant economic benefits associated with our planned £29bn investment in new and upgraded electricity transmission infrastructure across the north of Scotland.
The report, titled ‘Re‑energising the North: Transforming Scotland’, provides an update on our previously outlined economic analysis on plans to invest billions in mission-critical grid infrastructure, providing further insight into the scale of economic opportunity associated with the investment programme.
The report reaffirms our programme as one of the largest private infrastructure investments in Scotland’s history, with around £29bn of planned investment across the north of Scotland in the next five years, and it details the extent of the economic opportunity across the region.Using advanced economic modelling to analyse the impact of clean power infrastructure investment, the report’s findings conclude that our investment:
- Will support up to 10,000 jobs in the north of Scotland, and 24,000 across Scotland;
- When added to investment by other transmission operators and investment in generation will add around £60bn to UK economic output - with the Scottish economy up to 3% larger over the long term;
- Will deliver long-term improvements in productivity, wages and economic resilience, with employees moving into higher-value roles and key sectors expanding permanently; and
- Will create unique opportunities for Scottish suppliers, businesses and communities across multiple sectors, including forestry, peatland restoration, aggregates and concrete too.
The findings highlight the importance of ensuring that the benefits of investment are felt locally, with thousands of skilled jobs, increased supply chain activity, and investment flowing into communities across the north of Scotland.
Read the full News and Views article to find out more.Upcoming Works
Following the successful delivery of the new transformers earlier this month, we will be carrying out planned works at the substation between Wednesday 17 June and Thursday 18 June 2026.
What’s happening
The work involves filling the transformers with insulation oil, which is an important step before the equipment can be safely brought into operation.
What to expect
- These works are short-term and taking place on a single day.
- There may be some low-level noise and vibration during the activity. the transformers are required to be filled under vacuum therefore there is the possibility this will be running overnight.
- Lighting will be limited, with any temporary lighting directed downwards and within the site for safety.
- Overall, activity on site will remain minimal.
Why this matters
Transformers play a key role in transferring electricity efficiently across the network, helping to deliver a reliable supply of power to homes and businesses locally and across Scotland.
Keeping you informed
We are committed to keeping our neighbours updated and minimising disruption wherever possible. If you have any questions, please get in touch with our Community Liaison Manager.
-
Successful Delivery of Transformers
Our two new electricity transformers have been successfully delivered to the Lochay 132/11kV Transformer Replacement Project site, marking a key milestone in the ongoing upgrade of the local transmission network.
To watch a short video capturing the transformers passing over the Dochart Bridge and travelling through the glen up to the substaion please click on the adjacent image.
Transformer Deliveries
Our upcoming transformer deliveries are scheduled on Tuesday 12 and Wednesday 13 May 2026.
The transformers will travel through Killin, passing through the village and crossing Dochart Bridge, before turning off the A827 and travelling up the glen to reach the substation.
All movements will be carried out under an agreed traffic management plan, with support where required, to help minimise disruption and keep people safe.
Key timings to be aware of
• Crossing Dochart Bridge: Approximately 12.30pm
• Turning off the A827 to travel up the glen: Approximately 12.35-12.40pm
• Arrival at Lochay substation site: Approximately 12.50-1pm
We will manage vehicle movements carefully and, where possible, allow traffic to pass once it is safe to do so. Temporary traffic controls may be in place for short periods while the transformers pass through constrained sections of the route. -
Project Update
We have published the minutes from our 9th Community Liaison Group meeting, held on site in September 2025. These are now available to view within the ‘Documents’ section of this webpage and capture the discussions, questions raised, and the progress shared at the meeting.
We have also published our April 2026 community newsletter. This provides an overview of works completed since December, along with a look ahead at planned activities for the next quarter.
In addition, we want to share the next upcoming milestone for the project which will be delivery of the new transformers which are currently scheduled for delivery in May. We are continuing to finalise the wider programme delivery timeline to ensure plans are robust.
Once timings are confirmed, we will issue a targeted update directly to local residents with clear information on what to expect and when. We remain committed to keeping you informed and working together as the project progresses. -
2025 Festive Period
As our teams start to prepare the site for closing over the festive period, we wanted to confirm that works will pause on site from Friday 19 December 2025 to Monday 5 January 2026.
Although the site will be closed for all construction workers during this period, security will remain in place 7 days a week and 24 hours per day.
We have also published the final project newsletter of the year giving you an insight into what works and activities have been undertaken on site in the last quarter as well as those that are coming up in the first part of 2025. -
8th CLG Meeting Minutes
As our work continues to progress on the Lochay 132/11kV transformer replacement project we were pleased to host the projects 9th Community Liaison Group (CLG) on site on Thursday 25 September 2025.
You can find all minutes from CLG meetings held since the groups conception in 2022 including our 8th meeting that was held in June in the project documentation section of this website.
If you have issues, concerns or comments you would like discussed at a CLG, please contact any of the Lochay or SSEN Transmission representatives.
If you wish to attend a CLG in person, you are required to declare an agenda item in advance to Community Liaison Manager, Louise Anderson. We anticipate the next CLG meeting to take place in December 2025 ahead of the site closing for the festive period. -
7th CLG Meeting
We hosted our eighth CLG meeting on site last week on Tuesday 17 June. Minutes from the seventh meeting that was held in March can be downloaded from the project documentation section of this website.
If you have issues, concerns or comments you would like discussed at a CLG, please contact any of the Lochay or SSEN Transmission representatives.
If you wish to attend a CLG in person, you are required to declare an agenda item in advance to Community Liaison Manager, Louise Anderson. We anticipate the next CLG meeting to take place in September 2025. -
Spring clean for primary school thanks to Lochay substation transformer project
Our Principal Contractors Balfour Beatty and Global Infrastructure site teams took part in a volunteering day at Killin Primary School carrying our various activities that included but not limited to painting fences and railings.
To find out more click here. -
CLG Minutes
We hosted the first of 2025’s CLG meetings on site on Tuesday 18 March.
The Minutes from the 6th Community Liaison Group (CLG) meeting that was held in November 2024 can be downloaded from the project documentation section of this website.
If you have issues, concerns or comments you would like discussed at a CLG, please contact any of the Lochay or SSEN Transmission representatives.
If you wish to attend a CLG in person, you are required to declare an agenda item in advance to Community Liaison Manager, Louise Anderson. We anticipate the next CLG meeting to take place in June 2025. -
2024 Festive Period
As our teams start to prepare the site for closing over the festive period, we wanted to confirm that works will pause on site from 20 December 2024 to 6 January 2025.
Although the site will be closed for all construction workers during this period, security will remain in place 7 days a week and 24 hours per day.
We have also published the final project newsletter of the year giving you an insight into what works and activities have been undertaken on site in the last quarter as well as those that are coming up in the first part of 2025.
The newsletter can be downloaded from the documents section of this webpage.
6th Community Liaison Group Meeting
Ahead of the Lochay 132/11kV Transformer Replacement site closing for the Christmas and New Year break we were delighted to host our final Community Liaison Group (CLG) meeting of 2024 on site on 19 November.
The Minutes from the 5th Community Liaison Group (CLG) meeting that was held in July can be downloaded from the project documentation section of this website.
If you have issues, concerns or comments you would like discussed at a CLG, please contact any of the Lochay or SSEN Transmission representatives.
If you wish to attend a CLG in person, you are required to declare an agenda item in advance to Community Liaison Manager, Louise Anderson. We anticipate the next CLG meeting to take place in March 2025. -
CLG Minutes
We recently hosted the 5th Lochay 132/11kV Transformer Replacement Community Liaison Group (CLG) meeting on site on 23 July. Minutes from the 4th meeting that was held in April can be downloaded from the project documentation section of this website.
If you have issues, concerns or comments you would like discussed at a CLG, please contact any of the Lochay or SSEN Transmission representatives.
If you wish to attend a CLG in person, you are required to declare an agenda item in advance to Community Liaison Manager, Louise Anderson. We anticipate the next CLG meeting to take place in October 2024. -
4th CLG Meeting
The fourth CLG meeting for our Lochay 132/11kV transformer replacement project was hosted on site on 23 April. Minutes from the third meeting that was held in November can be downloaded from the project documentation section of this website.
If you have issues, concerns or comments you would like discussed at a CLG, please contact any of the Lochay or SSEN Transmission representatives.
If you wish to attend a CLG in person, you are required to declare an agenda item in advance to Community Liaison Manager, Louise Anderson. We anticipate the next CLG meeting to take place in July 2024. -
December 2023 Project Update
To give you an insight into what works and activities have been undertaken since construction commenced as well of those that are coming up on site, the Lochay transformer replacement project team have created and published the first quarterly project newsletter.
The newsletter will share an overview of the works underway and keep you updated with the projects progress during construction.The newsletter can be downloaded from the project documentation section of this website.
Works on site will pause for the festive period with the site closing from 22 December 2023 until 5 January 2024.
Although the site will be closed for all construction workers during this period, security will remain in place. -
3rd CLG Meeting
We held the third Lochay transformer replacement CLG meeting on 9 November at McLaren Hall in Killin. Minutes from the second meeting that was held in July can be downloaded from the project documentation section of this website.
If you have issues, concerns or comments you would like discussed at a CLG, please contact any of the Lochay or SSEN Transmission representatives. If you wish to attend a CLG in person, you are required to declare an agenda item in advance to Community Liaison Manager, Louise Anderson. We anticipate the next CLG meeting to take place in February/March 2024. -
CLG Minutes
We held the second Lochay transformer replacement CLG meeting on 11 July at McLaren Hall, Killin. Minutes from the inaugural meeting that was held in November 2022 along with the Terms of Reference can be downloaded from the project documentation section of this website.
If you have issues, concerns or comments you would like discussed at a CLG, please contact any of the Lochay or SSEN Transmission representatives. If you wish to attend a CLG in person, you are required to declare an agenda item in advance to Community Liaison Manager, Louise Anderson. We anticipate the next CLG meeting to take place in October 2023. -
Community liaison group
We held our first Community Liaison Group (CLG) meeting on 29 November 2022. The CLG is made up of representatives from the local community as well as Killin Community Council, Councillors from Trossachs and Teith Ward and project representatives from SSEN Transmission.
Meetings will take place at regular intervals to discuss any matters relating to the Lochay 132/11kV transformer replacement project in the lead up to and during the construction period. Minutes will be made publicly available via this website and through local channels such as Killin Community Council. We anticipate the next CLG to be held in February 2023. If you have any queries relating to this project please contact Louise Anderson, Lead Community Liaison Manager.
Meet the buyer event
We will shortly be beginning construction works on replacing the existing 132/11kV transformers currently situated at Lochay power station. As part of this project, we are welcoming local businesses to attend an informal meeting at McLaren Hall in Killin on Wednesday 7 December between 4-7pm, to engage with our Principal Contractors to exchange details to further discuss out with this introduction the possible business opportunities for the local supply chain that may be available.
This project has the potential to create local business opportunities in the following fields; accommodation, security, catering, cleaningservices, aggregate services, local labour services, road gritting, building and wholesaler merchants and others.
We would encourage any local businesses to attend the session and discuss what possible business opportunities there are with our Principal Contractors. -
Planning Consent
SSEN Transmission welcomes the decision made by Stirling Council on 24 March to grant permission to replace the 132/33kV transformers and erect a new electricity substation on land adjacent to Lochay hydro station. Throughout the life of our projects, we aim to work positively with local communities and keep people informed about what we are doing. We will continue to engage with the local community of Killin before, during and after construction. -
Planning Application Update
Following our planning application submission on 23 June 2021 to Stirling Council, the application has now been validated and is available for comments to be made. This can be done via the Stirling Council planning portal using reference number 21/00570/FUL. -
Planning Application Submission
We are delighted to confirm we have now submitted our final planning application to Stirling Council regarding our proposal to erect an electricity substation adjacent to the existing Lochay hydro station. We will provide a further update once the application has been validated by Stirling Council and a reference number has been applied to the application to allow for comments to be made. -
2020 FAQs
Following the feedback and comments received from the virtual consultation the Lochay 132/11kV transformer replacement project team held on 17 September, the online webinar that was held on 29 September and on-site meetings we have had, the project team have created a new FAQ document, covering the various questions raised by members of the public and other interested parties. This document is available to download from the project documentation section of this website. -
September 2020 Feedback Period Closed
The feedback period for providing comments following our virtual consultation that we held on the 17th of September has now closed. The project team would like to extend thanks to all members of the public who took the time to provide feedback on our updated design proposals. All responses received will now be reviewed. -
September Consultation Feedback
We have extended the feedback period for the September consultation to Friday 30th October 2020. -
Online Webinar
Following the online virtual consultation event SSEN Transmission held on 17th September 2020 for the Lochay 132/11kV transformer replacement project and ahead of submitting a planning application to Stirling Council, we are pleased to be hosting an online information webinar to allow for further discussions to be held with the project team.This webinar is free to join, and we would be delighted to hear from all interested parties and stakeholders on the day.We hope that by joining this session, we will be able to provide greater insight into the requirements for these works at our chosen site.To register for the webinar and the opportunity to submit any questions you wish to ask the team ahead of the session please click on the link that can be found on the main project overview page. There will also be the ability to ask questions direct to the team during the session. -
Virtual Consultation
SSEN Transmission are pleased to be holding a virtual consultation exhibition to provide an update on our proposed designs to the local community and interested parties following the events held in May and December 2019 on the Lochay 132/11kV transformer replacement project ahead of submitting a planning application to Stirling Council.The virtual consultation exhibition has been designed to be fully interactive, allowing for presentation of key project information and plans, as well as providing an opportunity to ask questions aboutthe project.Visitors will be able to engage directly with the project team, via a live text chat function, where they can ask any questions they might have about the project and share their feedback on the current proposals. The virtual online consultation will be held on Thursday 17 September 2020 between 4-7pm.
Proposal of Application Notice
A 3rd Proposal of Application Notice (PAN) has been submitted to Stirling Council under the terms of the Town and Country Planning (Development Management Procedure)(Scotland) Regulations 2013. This notice states our intent to submit a planning application to erect an electricity substation adjacent to the existing Lochay hydrostation.The notice can be viewed on the Stirling Council website under reference : PAN-2020-010. -
Project Update - July 2020
Following the second public consultation that was held in McLaren Hall, Killin in December 2019 the Lochay Transformer Replacement project team have been holding discussions with SSE Renewables (SSER) who are the licenced operator of Lochay Power Station to gain their feedback on our updated design options and project proposals that we presented at the December consultation. SSER have provided feedback that our proposal to extend the site to the west of the power station, including the construction of the substation compound to the west would impact their operations including access to the fish pass, which is essential for safe operation of the Lochay power station, it would also require a longer power station outage than any other location that we considered.Review of the design options and project proposals is still ongoing, taking into consideration all comments that we have received since the initial public consultation in May 2019, from stakeholders including, the local community, statutory consultees and SSER. The project team are working on a new draft design that we hope will be agreeable to all the comments and feedback we’ve received to date. We hope to present the new draft design at a virtual online public consultation in September, of which further details will be issued in due course. -
Second PAN Frequently Asked Questions
Following the second public consultation that the project team held in McLaren Hall on the 10th of December 2019, and the feedback we received from this consultation, in the interest of engaging openly and meaningfully with the local community the FAQ section of this webpage has been updated to include answers to various questions raised by members of the public and other interested parties. The FAQs can also be downloaded as a whole document by going to the project documentation tab.
Feedback Period Closed
The feedback period following our second PAN public consultation that we held at McLaren hall in Killin on the 10th of December is now closed. All responses received will now be reviewed ahead of our planning application submission. -
Consultation Feedback
The project team would like to extend thanks to all members of the public and interested parties who took the time to attend our second public pre-application consultation event at McLaren hall on Tuesday the 10th of December 2019, where we presented our updated design proposals.We would encourage all that attended to provide feedback on the proposals presented. The feedback period is open until Friday the 3rd of January at 4pm. -
Pre-Application Consultation
Following the public exhibition SSEN Transmission held in May and the feedback we have received from the local community regarding our plans to replace the two 25MVA 132/11kV grid transformers at Lochay power station. We are pleased to be hosting a second public exhibition at McLaren Hall in Killin on Tuesday the 10th December 2019 between 2-7pm to provide greater detail about this project and an update on our proposed designs.SSEN Transmission would like to extend an invitation to local members of the community and interested parties to attend the exhibition on the below date to discuss our plans with the project team and to provide feedback on our proposals. -
Frequently Asked Questions
Following the public consultation that the project team held on the 9th May in Mclaren Hall and the feedback we received from this consultation, in the interest of engaging openly and meaningfully with the local community, the FAQ section of this webpage has been updated to include answers to various questions raised by members of the public and other interested parties. The FAQs can also be downloaded as whole document by going to the project documentation tab. -
Lochay Pre-Application Consultation Feedback
The project team would like to extend thanks to all members of the public who took the time to attend our public pre-application consultation event on the 9th May 2019 at McLaren hall in Killin. All responses received are currently being reviewed ahead of submission of a planning application. All materials that were displayed can be downloaded from the Project documentation tab.
Documents
Project Newsletter
-
April 2026 Newsletter
- Type:
- Date:
- 10 March 2026
- Size:
- 327 KB
This newsletter for April 2026 provides project updates, key dates and information on planned activities in the area.
-
December 2025 Newsletter
- Type:
- Date:
- 24 November 2025
- Size:
- 208.8 KB
This newsletter for December 2025 provides project updates, key dates and information on planned activities in the area.
-
October 2025 Newsletter
- Type:
- Date:
- 29 September 2025
- Size:
- 1.5 MB
This project newsletter for October 2025 provides project updates, key dates and information on planned activities in the area and on site.
-
June 2025 Newsletter
- Type:
- Date:
- 06 June 2025
- Size:
- 1.3 MB
This project newsletter for June 2025 provides project updates, key dates and information on planned activities in the area and on site.
-
April 2025 Newsletter
- Type:
- Date:
- 26 March 2025
- Size:
- 2.1 MB
This newsletter for April 2025 provides project updates, key dates and information on planned activities in the area.
-
December 2024 Newsletter
- Type:
- Date:
- 29 November 2024
- Size:
- 1.5 MB
This project newsletter for December 2024 provides project updates, key dates and information on planned activities in the area and on site.
-
August 2024 Newsletter
- Type:
- Date:
- 01 August 2024
- Size:
- 1.8 MB
This project newsletter for August 2024 provides project updates, key dates and information on planned activities in the area and on site.
-
April 2024 Newsletter
- Type:
- Date:
- 01 April 2024
- Size:
- 960 KB
This project newsletter for April 2024 provides project updates, key dates and information on planned activities in the area and on site.
-
December 2023 Newsletter
- Type:
- Date:
- 12 December 2023
- Size:
- 579.2 KB
This project newsletter for December 2023 provides project updates, key dates and information on planned activities in the area and on site.
Community Liaison Group Meeting Minutes
-
Community Liaison Group Meeting Minutes 9 - September 2026
- Type:
- Date:
- 10 March 2026
- Size:
- 179.7 KB
Minutes of the 9th Lochay transformer replacement Community Liaison Group Meeting
-
Community Liaison Group Meeting Minutes 8 - June 2025
- Type:
- Date:
- 29 September 2025
- Size:
- 174 KB
Minutes of the 8th Lochay transformer replacement Community Liaison Group Meeting
-
Community Liaison Group Meeting Minutes 7 - March 2025
- Type:
- Date:
- 23 June 2025
- Size:
- 186.9 KB
Minutes of the 7th Lochay transformer replacement Community Liaison Group Meeting
-
Community Liaison Group Meeting Minutes 6 - November 2024
- Type:
- Date:
- 26 March 2025
- Size:
- 184.7 KB
Minutes of the 6th Lochay transformer replacement Community Liaison Group Meeting
-
Community Liaison Group Meeting Minutes 5 - July 2024
- Type:
- Date:
- 20 November 2024
- Size:
- 179.8 KB
Minutes of the 5th Lochay transformer replacement Community Liaison Group Meeting
-
Community Liaison Group Meeting Minutes 4 - April 2024
- Type:
- Date:
- 26 July 2024
- Size:
- 188.6 KB
Minutes of the 4th Lochay transformer replacement Community Liaison Group Meeting
-
Community Liaison Group Meeting Minutes 3 - November 2023
- Type:
- Date:
- 17 May 2024
- Size:
- 194.5 KB
Minutes of the 3rd Lochay transformer replacement Community Liaison Group Meeting
-
Community Liaison Group Meeting Minutes 2 - July 2023
- Type:
- Date:
- 17 November 2023
- Size:
- 195.7 KB
Minutes of the 2nd Lochay transformer replacement Community Liaison Group Meeting
-
Community Liaison Group Meeting Minutes 1 - November 2022
- Type:
- Date:
- 12 July 2023
- Size:
- 199.5 KB
Minutes of the inaugural Lochay transformer replacement Community Liaison Group Meeting
-
Lochay Transformer Replacement CLG Terms of Reference
- Type:
- Date:
- 05 December 2022
- Size:
- 291.6 KB
This document provides the Terms of Reference for the Lochay transformer replacement Community Liaison Group.
Project Documents
-
Meet the Buyer Information Poster
- Type:
- Date:
- 05 December 2022
- Size:
- 486.1 KB
Poster detailing plans to host a Meet the Buyer event to introduce local supply chain to our Principal Contractors
-
September 2020 FAQs
- Type:
- Date:
- 16 December 2020
- Size:
- 2.4 MB
Frequently Asked Questions following the public consultation held in September 2020.
-
September 2020 webinar presentation
- Type:
- Date:
- 29 September 2020
- Size:
- 1 MB
Presentation slides from webinar hosted in September 2020.
-
View point 01 AIS -Meall Clachach track
- Type:
- Date:
- 16 September 2020
- Size:
- 303 KB
Visualisation from Meall Clachach track
-
View point 01 Meall Clachach summit
- Type:
- Date:
- 16 September 2020
- Size:
- 5.9 MB
Visualisation from Meall Clachach summit
-
View point 02 AIS road south
- Type:
- Date:
- 16 September 2020
- Size:
- 294.4 KB
Visualisation from south road
-
View point 02 minor road near power station north
- Type:
- Date:
- 16 September 2020
- Size:
- 5.9 MB
Visualisation from minor road near power station north
-
View point 03 AIS road north
- Type:
- Date:
- 16 September 2020
- Size:
- 333.8 KB
Visualisation from north road
-
View point 03 minor road near power station south
- Type:
- Date:
- 16 September 2020
- Size:
- 7.4 MB
Visualisation from minor road near power station south
-
View point 04 minor road near power station south-a
- Type:
- Date:
- 16 September 2020
- Size:
- 454.3 KB
Visualisation from minor road near power station south
-
View point 05 Meall Clachach track
- Type:
- Date:
- 16 September 2020
- Size:
- 9.1 MB
Visualisation from Meall Clachach track
-
View point 06 Murlaganmore
- Type:
- Date:
- 16 September 2020
- Size:
- 10.2 MB
Visualisation from Murlaganmore
-
View point 07 road north of substation
- Type:
- Date:
- 16 September 2020
- Size:
- 10.4 MB
Visualisation from road north of substation
-
September 2020 public consultation booklet
- Type:
- Date:
- 15 September 2020
- Size:
- 591.9 KB
Information booklet that supported our information event held in September 2020. Containing project details ahead of submitting our planning application.
-
Virtual consultation times
- Type:
- Date:
- 25 August 2020
- Size:
- 111.1 KB
Poster detailing the time and date of the September 2020 public online consultation.
-
December 2019 FAQs
- Type:
- Date:
- 27 January 2020
- Size:
- 8.3 MB
Frequently Asked Questions following the public consultation held in December 2019.
-
December 2019 public consultation booklet
- Type:
- Date:
- 09 December 2019
- Size:
- 10.2 MB
Information booklet that supported our information event held in December 2019. Containing project details.
-
Revised red line boundary
- Type:
- Date:
- 29 November 2019
- Size:
- 4 MB
Drawing showing the revised proposal of application notice red line boundary included as part of the projects planning application.
-
May 2019 FAQs
- Type:
- Date:
- 23 June 2019
- Size:
- 5.9 MB
Frequently Asked Questions following the public consultation held in May 2019.
-
Environmental and heritage constraints map
- Type:
- Date:
- 29 May 2019
- Size:
- 3 MB
Map that shows environmental and heritage constraints around Lochay substation
-
Phase 1 habitat survey map
- Type:
- Date:
- 29 May 2019
- Size:
- 335 KB
Map that shows the Phase 1 habitat survey undertaken around Lochay substation
-
Visualisations
- Type:
- Date:
- 26 May 2019
- Size:
- 1.9 MB
Photosphere visualisations from various locations in proximity of the proposed development site to show what the project will look like.
-
May 2019 public consultation booklet
- Type:
- Date:
- 07 May 2019
- Size:
- 1.1 MB
Information booklet that supported our information event held in May 2019. Containing project details.
-
Proposed site layout
- Type:
- Date:
- 08 April 2019
- Size:
- 3.4 MB
Map including the proposed site layout as part of the projects Proposal of Application Notice (PAN) submission to Stirling Council
-
Red line boundary
- Type:
- Date:
- 07 April 2019
- Size:
- 4.2 MB
Drawing showing the proposal of application notice red line boundary included as part of the projects planning application.
-
Site location
- Type:
- Date:
- 07 April 2019
- Size:
- 3.3 MB
Map detailing the Lochay 132/11kV substation site location
FAQs
FAQs
-
The existing substation was constructed in 1958 when the hydro station was commissioned. Since 1958, electricity regulations and specifications have changed significantly which impact the way in which electricity infrastructure is designed, constructed and maintained. With the introduction of the Construction (Design and Management) Regulations, the Government has introduced legal requirements to ensure that health and safety risks are managed throughout the lifecycle of a project. We must take note of these regulations and ensure that all equipment can be maintained safely. The standard safe method of maintenance in the energy industry is by a mobile work platform (also known as a MEWP) which requires space to manoeuvre around the platform to access the plant at high level for maintenance, whilst allowing for clearance to live electrical equipment. The existing substation did not cater for these maintenance requirements. The transformers themselves are larger in overall footprint as they are designed to allow for noise enclosures to be fitted around the transformer tank if noise mitigation is deemed a requirement in future. This is now common design practice.
-
There are two main constraints in this area which have prevented the substation being positioned any closer to the existing site:
1) The underground penstock piipeline which feeds Lochay Power Station
2) The 33kV overhead line SHE Transmission need to maintain a safe distance from this Penstock to ensure that it’s protected.
In addition it is no longer good practice to locate oil filled transformers so close to a watercourse. Usually, the Scottish Environment Protection Agency’s (SEPA) good practice guidance requires that works should not commence within 10m of a watercourse; however, it is likely that this distance will increase due to the sensitivities of the watercourse Special Area of Conservation (SAC). The River Lochay, which is near the existing Lochay substation, forms part of the Loch Tay SAC. "The River Tay SAC is designated as a Natura 2000 site for Atlantic salmon, sea lamprey, river lamprey, brook lamprey, clear water-lochs and otters. It is also important for freshwater pearl mussel which is a protected species. The proposed location is 100m north of the River Lochay and further away than other options which is advantageous.
-
The main power station building has been designed and finished to sympathetically respond to this attractive landscape setting. It was a well-established objective of the then North of Scotland Hydro Electricity Board to ensure hydro power buildings and infrastructure harmonised with their Highland surroundings. The new development of SHE Transmission intends to follow the same principle by screen planting and additional tree planting sympathetic to that already established on site. Additional design improvements will be encouraged during the detailed phase to allow maximum possible distance from the public road to accommodate additional screening.
-
SHE Transmission undertook a detailed site selection assessment for any new or upgrade to existing electrical assets. The site selection process has identified a site which SHE Transmission consider at this stage, to be the best solution based on technical, environmental, safety and economic parameters. These designs were presented at the consultation event and will undergo further detailed review following the feedback from the event.
There are several constraints which are considered in this assessment which are factors in why the existing substation site cannot be used; oversailing conductors, proximity to live equipment, 3rd party equipment, underground services including the power station penstock pipeline. In addition to this, with the introduction of the Construction (Design and Management) Regulations, the Government has introduced legal requirements to ensure that health and safety risks are managed throughout the lifecycle of a project. We must take note of these regulations and ensure that all equipment can be maintained safely throughout the lifetime of the plant.
-
The access road to the power station has been assessed and it does not require any modifications or widening to enable the safe delivery of the transformers. In relation to the volume of traffic we are currently assessing traffic figures as a result of the earthworks strategy/design and look to keep movements as low as possible.
-
By the nature of electrical equipment, there are restrictions to where the equipment must be located and connected to ensure the substation operates correctly. SHE Transmission have undertook design studies to provide what we feel as the most efficient solution at this stage of the consultation. We aim to minimise the footprint of the substation as much as possible.
-
SHE Transmission undertake a detailed site selection assessment which is tailored for that specific site. The site selection assessment is based on key technical, environmental, safety and economic parameters and is used to identify the preferred layout for the substation. The design presented is tailor made for the site.
-
The control building must be within the substation fence line.
-
The transmission pylon has to be positioned in a location which allows for the connection into the substation. This does not have to be within the substation fence line, however SHE Transmission must ensure that there are no safety clearance infringements with the proposal.
-
There is no technical reason why the transformers have to be side by side, however consideration on the delivery, offloading, removal, and fire damage protection of the transformers has led to SHE Transmission positioning the transformers in this way.
-
There are several constraints why the existing substation site cannot be used; oversailing conductors, proximity to live equipment, 3rd party equipment, underground services including the power station penstock pipeline. In addition to this, with the introduction of the Construction (Design and Management) Regulations, the Government has introduced legal requirements to ensure that health and safety risks are managed throughout the lifecycle of a project. We must take note of these regulations and ensure that all equipment can be maintained safely throughout the lifetime of the plant.
-
Any overhead line modifications will comply with legislations and statutory clearance requirements.
-
SHE Transmission has undertaken ground investigation and appointed specialist civil engineers to prepare drainage strategy and design drainage plans to prevent flooding due to the current landscape and the proposed development. The importance of the River Lochay which is a part of the wider River Tay Special Area of Conservation and its proximity to the newly proposed substation is a key consideration of drainage strategy.
The site lies within the Tay Local Flood Management Plan catchment area. The management plan does not identify the project site as being within a ‘potentially vulnerable area’ for flooding. The Scottish Environment Protection Agency (SEPA) National Flood Risk Assessment Flood Map, does not identify the project site as being within an area likely to experience river or surface water flooding. Relevant sections of the SSEN General Environmental Management Plans (GEMPs) will be built in to a Contractor Environmental Management Plans (CEMP) to be implemented by the project’s selected contractor. This will mitigate the potential for impact to waterbodies during construction.
-
The noise output from the transformers often varies depending on the level of generation export. SHE Transmission expect that the noise levels from the transformers will be within the statutory noise requirements. The transformers themselves are designed to allow for noise enclosures to be fitted around the transformer tank if noise mitigation is deemed a requirement in future.
-
The new substation is a like for like replacement of the existing substation with modern equivalent equipment. No additional water is expected to be extracted for electricity generation as a result of this development. A permanent drinking water supply will be installed but the new substation will be normally unmanned.
-
There is potential for travel disruption during construction, when we take delivery of key plant items or because of increased volumes of traffic on the local road network. Disruption will be minimised and typically controlled through an agreed Traffic Management Plan with Stirling Council as part of any consent conditions. SHE Transmission aims to ensure that construction traffic uses the roads safely and that any inconvenience to the public is kept to a minimum whilst maintaining a safe environment for the workforce and other road users.
As part of the Environmental Assessments, potential impact from construction noise will be evaluated and mitigation measures instigated where necessary. These are controlled through Consented conditions.
-
SHE Transmission expect to submit their application for planning consent under the Electricity Act to Stirling Council in quarter 2 of 2020. The application will be advertised and opportunities for submission of representations will be available at that time. SHE Transmission will continue consulting with the Scottish Government Local Energy and Consents Unit, Stirling Council and other key statutory bodies as well as the local community prior to submitting a formal application.
-
SHE Transmission is undertaking an Environmental Appraisal with input from specialist consultants covering topics such as ecology, hydrology and landscape and visual (not limited to), to ensure minimal impact as a result of the development. Working hours will be agreed with the local authority as part of the planning permission, in addition to a traffic management plan.
-
Yes, SHE Transmission will assess the condition of the road before the commencement of works and after completion. Reinstatement will be carried out to repair any damage caused due to SHE Transmission.
-
The power supply to Murlaganmore Cottage does not originate from the power station. The cable route starts at a pole-mount transformer further uphill from the proposed works and takes a route further west of the planned site extension. Hence it is not anticipated that the construction work will affect the power supply.
-
No, changes to the walkway and salmon lift / fish pass and it’s access are not part of this project.
-
Minimal tree removal is anticipated but can’t be confirmed until detail design stage which will be later in 2020.
-
A landscaping plan will be put in place as per agreement with Stirling Council once we have a final layout and liaised further with the statutory authorities.
-
Yes access will be maintained along the Glen Lochay Road South throughout the duration of the works. A Traffic Management Plan will be developed with Stirling Council to manage traffic volume, peak activity times and vehicle type along this road.
-
SSEN Transmission is responsible for maintaining and investing in the electricity transmission network in the north of Scotland and our network extends over a quarter of the UK’s land mass, crossing some of its most challenging terrain.
Our operating area is home to vast renewable energy resources, and this is being harnessed by wind, hydro and marine generation. Working closely with National Grid Electricity System Operator (the 'ESO'), we enable electricity generators to connect to the transmission system, allowing the electricity generated by them to be transported to areas of demand across the country. -
Following a minority stake sale which completed in November 2022, SSEN Transmission is now owned 75% by SSE plc and 25% by Ontario Teachers’ Pension Plan Board.
SSE plc sold its UK domestic electricity and gas retail business, along with domestic energy services to OVO Energy in January 2020 and no longer manages these customer accounts.
-
It’s the highest voltage electricity network in the UK – the ‘motorway network’ of the energy world. It transmits large quantities of electricity over long distances via wires carried on a system of mainly metal towers (pylons) and large substations. Transmission voltages in Scotland are 132kV, 275kV and 400kV. Larger generation schemes usually connect to the Transmission system.
The lower voltage parts of the system are called distribution networks. In Scotland, these local networks operate below 132kV whereas in England the distribution network includes 132kV.
-
As a stakeholder-led business, throughout the life of our projects, we aim to work positively with local communities and keep people informed about what we are doing. This is particularly important when we are developing new projects, we want to understand what local people think about our plans.
We always endeavour to take the time to discuss our proposals with local community councils and the wider affected community and to carry out engagement throughout each of the development stages, listening to feedback before finalising project plans. The feedback we receive is vital to help us develop proposals that reflect the views of a variety of stakeholder.
-
To find out more about a project, visit our project web pages which can be searched by location or area. Each project has a dedicated Community Liaison Manager that you can contact. You can find their contact details in the individual project pages, where you can also sign up to project updates.
Project Contacts
Louise Anderson | Lead Community Liaison Manager
Telephone: 07384 454233
Address: Grampian House, 200 Dunkeld Road, Perth, PH1 3GH
Lynn Dandie | Senior Land Manager
Recite me
To make use of this function please click on the 3 'A's' button at the bottom left of the website.