Overview
About the Project
In order to support the continued growth in onshore and offshore renewables across the north of Scotland, supporting the country's drive towards Net Zero, investment in network infrastructure is needed to connect this renewable power and transport it from source to areas of demand across the country.
Extensive studies have confirmed the need for the Beauly – Denny Second Circuit 400kV Upgrade Project and new 400kV substations at Braco West and Fasnakyle. The project includes the following elements:
- A new 400kV substation at Braco West, known as Cambushinnie
- A new 400kV substation at Fasnakyle (near Beauly), known as Bingally
- Modifications or extensions to other substations along the route, including Fort Augustus, Errochty, Kinardochy and Tummel
- Connections to existing substations will also be required as part of the upgrade
- We do not anticipate any alterations to the existing overhead line in order to upgrade it.
Find out more about the Cambushinnie 400kV substation
Find out more about the Bingally 400kV substation
Find out more about the Fort Augustus substation 400kV Upgrade
Find out more about the Kinardochy – Errochty Underground Cable
The existing Beauly – Denny overhead line is 137 miles long and runs from Beauly, north of Inverness, to Denny near Falkirk. It was the first 400kV overhead line built in our network area and became fully operational in 2015. There are two circuits on the overhead line, one running at 400kV and the other at 275kV. We are now required to upgrade the second circuit to 400kV to help transport large scale renewable generation from the north of Scotland to areas of demand.
Due to the overhead line being constructed for 400kV operation on each of its two circuits, but put into service with one operating at the lower voltage of 275kV, we do not anticipate any alterations to the existing overhead line in order to upgrade it.
New 400kV substations are required at Braco West and Fasnakyle to house more sophisticated switching capability than is present in the existing 275kV substations, which requires significantly more space than either existing substation can currently accommodate.
This video outlines how the project contributes to our role in delivering Net Zero.
Braco West Story Map
Our Environmental Consultants, AECOM, have created a story map for Braco West where you can find out more information on the project.
Please let us know if you require information in an adapted format such as paper copy, large print or braille and we will work with you to accommodate your preferences. We are happy to accommodate all reasonable requests for adapted communications.
Pathway to 2030
The Pathway to 2030, published by National Energy System Operator NESO, the electricity system operator for Great Britain, sets the blueprint for the electricity transmission network infrastructure required to enable the forecasted growth in renewable electricity across Great Britain.
The projects identified within the Pathway to 2030 are critical to delivering the UK and Scottish Government’s offshore wind targets. To deliver these targets, we are investing over £10bn to upgrade the network infrastructure across the north of Scotland as the region plays a leading role in the clean energy transition.
As part of this investment, there is a requirement for the Beauly - Denny 400kV Upgrade Project.
How we’re embracing artificial intelligence (AI)
We intend to use AI to assist our experienced teams in the analysis of your feedback, so we can categorise key points raised more quickly. You can learn more about how we’re utilising AI on this dedicated web page.
Project Updates
Project updates
Documents
Additional Information
Fort Augustus 400kV Substation Consultation Documents
-
Fort Augustus 400kV Substation February 2024 Feedback Event Booklet
- Type:
- Date:
- 19 February 2024
- Size:
- 16.2 MB
This document provides information to our stakeholders about the project and was provided during our feedback event in February 2024.
-
Fort Augustus Feedback Event Poster February 2024
- Type:
- Date:
- 06 February 2024
- Size:
- 475.5 KB
This document provides information to our stakeholders about our feedback events in February 2024.
-
Fort Augustus Consultation Document
- Type:
- Date:
- 20 November 2023
- Size:
- 1.9 MB
This document provides information to our stakeholders about the project and was provided during our consultation in November 2023.
-
Fort Augustus Consultation Event Poster November 2023
- Type:
- Date:
- 16 November 2023
- Size:
- 189.4 KB
This document provides information to our stakeholders about our consultation events in November 2023.
-
Fort Augustus 400kV Substation November 2023 Public Consultation Booklet
- Type:
- Date:
- 16 November 2023
- Size:
- 16.6 MB
This document provides information to our stakeholders about the project and was provided during our consultation in November 2023.
FAQs
Who we are
About the Pathway to 2030 projects
Our approach to routeing and public consultation
Environmental considerations
Community and landowner considerations
Cost and engineering considerations