

The two 25MVA 132/11kV grid transformers at Lochay power station were manufactured in 1958 and form an important part of the SHE Transmission system. The power station is supplied from the Killin 132/33kV grid substation through the 132kV single overhead line.
These transformers have reached their intended operational capabilities, and recent condition assessments also indicate that there is a need to replace both transformer units.
SHE Transmission Plc has a licence obligation to invest in its existing assets to maintain network health and condition. SHE Transmission Plc also has a statutory duty under the Electricity Safety Quality and Continuity Regulations 2002 to ensure that the electricity transmission network is fit for purpose.
The decision making process for asset replacement takes into account both the criticality and condition of existing assets. Criticality is a representation of the risk to stakeholders with respect to safety, environment and reliability. The decision making process has been agreed with the regulatory stakeholders and has been taken into account in prioritising the Lochay transformers for further assessment and asset replacement.
Throughout the life of our projects, we aim to work positively with local communities and keep people informed about what we are doing. This is particularly important when we are developing a proposal and we want to understand what local people think about our plans.
We endeavour to take the time to discuss proposals with local community councils, encourage engagement from the wider community and listen to the feedback we receive.
We will do our best to answer any questions and address issues or concerns that are raised with us.
When our project progresses into construction, we will continue working closely with the local community to ensure that our work has as little impact on the lives of those living and working in the area and as many long term positive effects as possible.
To support everyone online, we provide accessibility and language options on our website through ‘Recite Me’. The accessibility and language support options provided by ‘Recite Me’ include text-to-speech functionality, fully customisable styling features, reading aids, and a translation tool with over 100 languages, including 35 text-to-speech. Please select “Accessibility” on our website to try out our inclusive toolbar.
To make use of this function please click on the 'accessibility' button at the top right of the website.
The data in this map is provided for indicative purposes only and may be subject to change. Scottish Hydro Electric Transmission plc do not accept responsibility for its accuracy, completeness or validity. The data should not be copied, reproduced or utilised externally without permission.
Scottish and Southern Electricity Networks is the trading name of Scottish and Southern Energy Power Distribution Limited, Scottish Hydro Electric Transmission plc, Scottish Hydro Electric Power Distribution plc and Southern Electric Power Distribution plc.
It’s the highest voltage electricity network in the UK – the ‘motorway network’ of the energy world. It transmits large quantities of electricity over long distances via wires carried on a system of mainly metal towers (pylons) and large substations. Transmission voltages in Scotland are 132kV, 275kV and 400kV. Larger generation schemes usually connect to the Transmission system.
The lower voltage parts of the system are called distribution networks. In Scotland, these local networks operate below 132kV whereas in England the distribution network includes 132kV.
Investments in projects are made by SHE Transmission plc. Electricity transmission companies are authorised to recover the costs of such investments through 'use of system' charges which are levied by National Grid Electricity Transmission plc on generators and suppliers of electricity. Suppliers recover their costs from all electricity customers. In order to protect the interests of customers, the transmission companies have to demonstrate to the energy regulator, Ofgem (Office for Gas and Electricity Markets) that proposed investments are necessary, are efficient and are economical so that the charges which are ultimately levied on all electricity customers are justified.
This means SHE Transmission is subject to a funding mechanism established by Parliament and regulated by Ofgem. Cross subsidies between different businesses in the SSE group is not permitted.
SHE Transmission are regulated by the Office for Gas and Electricity Markets (Ofgem), the regulator responsible for representing consumers' interests. Electricity consumer interests are therefore one of our key drivers and this is enshrined in our statutory duties under the Electricity Act.
In particular we have a statutory duty to develop, maintain and operate an efficient, economic and co-ordinated transmission system. Since the costs of these projects will ultimately be paid for by electricity consumers, we have a responsibility to take cost into account with due weighting in a comparison against other important factors.
The existing substation was constructed in 1958 when the hydro station was commissioned. Since 1958, electricity regulations and specifications have changed significantly which impact the way in which electricity infrastructure is designed, constructed and maintained. With the introduction of the Construction (Design and Management) Regulations, the Government has introduced legal requirements to ensure that health and safety risks are managed throughout the lifecycle of a project. We must take note of these regulations and ensure that all equipment can be maintained safely. The standard safe method of maintenance in the energy industry is by a mobile work platform (also known as a MEWP) which requires space to manoeuvre around the platform to access the plant at high level for maintenance, whilst allowing for clearance to live electrical equipment. The existing substation did not cater for these maintenance requirements. The transformers themselves are larger in overall footprint as they are designed to allow for noise enclosures to be fitted around the transformer tank if noise mitigation is deemed a requirement in future. This is now common design practice.
There are two main constraints in this area which have prevented the substation being positioned any closer to the existing site:
1) The underground penstock piipeline which feeds Lochay Power Station
2) The 33kV overhead line SHE Transmission need to maintain a safe distance from this Penstock to ensure that it’s protected.
In addition it is no longer good practice to locate oil filled transformers so close to a watercourse. Usually, the Scottish Environment Protection Agency’s (SEPA) good practice guidance requires that works should not commence within 10m of a watercourse; however, it is likely that this distance will increase due to the sensitivities of the watercourse Special Area of Conservation (SAC). The River Lochay, which is near the existing Lochay substation, forms part of the Loch Tay SAC. "The River Tay SAC is designated as a Natura 2000 site for Atlantic salmon, sea lamprey, river lamprey, brook lamprey, clear water-lochs and otters. It is also important for freshwater pearl mussel which is a protected species. The proposed location is 100m north of the River Lochay and further away than other options which is advantageous.
The main power station building has been designed and finished to sympathetically respond to this attractive landscape setting. It was a well-established objective of the then North of Scotland Hydro Electricity Board to ensure hydro power buildings and infrastructure harmonised with their Highland surroundings. The new development of SHE Transmission intends to follow the same principle by screen planting and additional tree planting sympathetic to that already established on site. Additional design improvements will be encouraged during the detailed phase to allow maximum possible distance from the public road to accommodate additional screening.
SHE Transmission undertook a detailed site selection assessment for any new or upgrade to existing electrical assets. The site selection process has identified a site which SHE Transmission consider at this stage, to be the best solution based on technical, environmental, safety and economic parameters. These designs were presented at the consultation event and will undergo further detailed review following the feedback from the event.
There are several constraints which are considered in this assessment which are factors in why the existing substation site cannot be used; oversailing conductors, proximity to live equipment, 3rd party equipment, underground services including the power station penstock pipeline. In addition to this, with the introduction of the Construction (Design and Management) Regulations, the Government has introduced legal requirements to ensure that health and safety risks are managed throughout the lifecycle of a project. We must take note of these regulations and ensure that all equipment can be maintained safely throughout the lifetime of the plant.
The access road to the power station has been assessed and it does not require any modifications or widening to enable the safe delivery of the transformers. In relation to the volume of traffic we are currently assessing traffic figures as a result of the earthworks strategy/design and look to keep movements as low as possible.
By the nature of electrical equipment, there are restrictions to where the equipment must be located and connected to ensure the substation operates correctly. SHE Transmission have undertook design studies to provide what we feel as the most efficient solution at this stage of the consultation. We aim to minimise the footprint of the substation as much as possible.
SHE Transmission undertake a detailed site selection assessment which is tailored for that specific site. The site selection assessment is based on key technical, environmental, safety and economic parameters and is used to identify the preferred layout for the substation. The design presented is tailor made for the site.
The control building must be within the substation fence line.
The transmission pylon has to be positioned in a location which allows for the connection into the substation. This does not have to be within the substation fence line, however SHE Transmission must ensure that there are no safety clearance infringements with the proposal.
There is no technical reason why the transformers have to be side by side, however consideration on the delivery, offloading, removal, and fire damage protection of the transformers has led to SHE Transmission positioning the transformers in this way.
There are several constraints why the existing substation site cannot be used; oversailing conductors, proximity to live equipment, 3rd party equipment, underground services including the power station penstock pipeline. In addition to this, with the introduction of the Construction (Design and Management) Regulations, the Government has introduced legal requirements to ensure that health and safety risks are managed throughout the lifecycle of a project. We must take note of these regulations and ensure that all equipment can be maintained safely throughout the lifetime of the plant.
Any overhead line modifications will comply with legislations and statutory clearance requirements.
SHE Transmission has undertaken ground investigation and appointed specialist civil engineers to prepare drainage strategy and design drainage plans to prevent flooding due to the current landscape and the proposed development. The importance of the River Lochay which is a part of the wider River Tay Special Area of Conservation and its proximity to the newly proposed substation is a key consideration of drainage strategy.
The site lies within the Tay Local Flood Management Plan catchment area. The management plan does not identify the project site as being within a ‘potentially vulnerable area’ for flooding. The Scottish Environment Protection Agency (SEPA) National Flood Risk Assessment Flood Map, does not identify the project site as being within an area likely to experience river or surface water flooding. Relevant sections of the SSEN General Environmental Management Plans (GEMPs) will be built in to a Contractor Environmental Management Plans (CEMP) to be implemented by the project’s selected contractor. This will mitigate the potential for impact to waterbodies during construction.
The noise output from the transformers often varies depending on the level of generation export. SHE Transmission expect that the noise levels from the transformers will be within the statutory noise requirements. The transformers themselves are designed to allow for noise enclosures to be fitted around the transformer tank if noise mitigation is deemed a requirement in future.
The new substation is a like for like replacement of the existing substation with modern equivalent equipment. No additional water is expected to be extracted for electricity generation as a result of this development. A permanent drinking water supply will be installed but the new substation will be normally unmanned.
There is potential for travel disruption during construction, when we take delivery of key plant items or because of increased volumes of traffic on the local road network. Disruption will be minimised and typically controlled through an agreed Traffic Management Plan with Stirling Council as part of any consent conditions. SHE Transmission aims to ensure that construction traffic uses the roads safely and that any inconvenience to the public is kept to a minimum whilst maintaining a safe environment for the workforce and other road users.
As part of the Environmental Assessments, potential impact from construction noise will be evaluated and mitigation measures instigated where necessary. These are controlled through Consented conditions.
SHE Transmission expect to submit their application for planning consent under the Electricity Act to Stirling Council in quarter 2 of 2020. The application will be advertised and opportunities for submission of representations will be available at that time. SHE Transmission will continue consulting with the Scottish Government Local Energy and Consents Unit, Stirling Council and other key statutory bodies as well as the local community prior to submitting a formal application.
SHE Transmission is undertaking an Environmental Appraisal with input from specialist consultants covering topics such as ecology, hydrology and landscape and visual (not limited to), to ensure minimal impact as a result of the development. Working hours will be agreed with the local authority as part of the planning permission, in addition to a traffic management plan.
Yes, SHE Transmission will assess the condition of the road before the commencement of works and after completion. Reinstatement will be carried out to repair any damage caused due to SHE Transmission.
The power supply to Murlaganmore Cottage does not originate from the power station. The cable route starts at a pole-mount transformer further uphill from the proposed works and takes a route further west of the planned site extension. Hence it is not anticipated that the construction work will affect the power supply.
No, changes to the walkway and salmon lift / fish pass and it’s access are not part of this project.
Minimal tree removal is anticipated but can’t be confirmed until detail design stage which will be later in 2020.
There have been no specific beaver surveys carried out to date, however preconstruction surveys will be carried out and specialist beaver surveys will be undertaken if a potential impact is highlighted.
A landscaping plan will be put in place as per agreement with Stirling Council once we have a final layout and liaised further with the statutory authorities.
Yes access will be maintained along the Glen Lochay Road South throughout the duration of the works. A Traffic Management Plan will be developed with Stirling Council to manage traffic volume, peak activity times and vehicle type along this road.
Related Projects: Lochay 132/11kV Transformer Replacement
Related Projects: Lochay 132/11kV Transformer Replacement
Related Projects: Lochay 132/11kV Transformer Replacement
Related Projects: Lochay 132/11kV Transformer Replacement
Related Projects: Lochay 132/11kV Transformer Replacement
Related Projects: Lochay 132/11kV Transformer Replacement
Related Projects: Lochay 132/11kV Transformer Replacement
Related Projects: Lochay 132/11kV Transformer Replacement
Related Projects: Lochay 132/11kV Transformer Replacement
Related Projects: Lochay 132/11kV Transformer Replacement
Related Projects: Lochay 132/11kV Transformer Replacement
Related Projects: Lochay 132/11kV Transformer Replacement
Related Projects: Lochay 132/11kV Transformer Replacement
Related Projects: Lochay 132/11kV Transformer Replacement
Related Projects: Lochay 132/11kV Transformer Replacement
Related Projects: Lochay 132/11kV Transformer Replacement
Related Projects: Lochay 132/11kV Transformer Replacement
Related Projects: Lochay 132/11kV Transformer Replacement
Related Projects: Lochay 132/11kV Transformer Replacement
Related Projects: Lochay 132/11kV Transformer Replacement
Related Projects: Lochay 132/11kV Transformer Replacement
Related Projects: Lochay 132/11kV Transformer Replacement
Related Projects: Lochay 132/11kV Transformer Replacement
Related Projects: Lochay 132/11kV Transformer Replacement
Related Projects: Lochay 132/11kV Transformer Replacement
Related Projects: Lochay 132/11kV Transformer Replacement
Related Projects: Lochay 132/11kV Transformer Replacement
Related Projects: Lochay 132/11kV Transformer Replacement
To keep informed of all that is happening on this project, please complete your details below and provide consent to enable us to send you updates via email
For information on how we collect and process your data, please see our privacy notice at www.ssen.co.uk/PrivacyNotice/. If you do not have access to our website, or would like to receive a hard copy, please contact us.