Crossaig 275kV Substation
- Type:
- Transmission reinforcement
- Location:
- Argyll & Bute
Constructing a new 275kV substation at Crossaig to support renewable energy and upgrade existing infrastructure.
Overview
Status: Construction Phase
Stage 4 of 5
-
Stage 1: Project Assessment: (Completed)
During the Project Assessment stage, we’re committed to evaluating potential project strategies. At this stage, we provide information about the proposed project plans on our website for stakeholders to review and provide feedback on, as well as holding in-person events within the local community demonstrating our collaborative approach to the project's development.
-
Stage 2: Early Development: (Completed)
During Early Development, we concentrate on refining the project details, based on our initial assessment of key environmental, technical, and economic factors to identify the best performing approach. We would like to gain further input from communities through accessible in-person and in some cases online consultations, which are crucial in refining our plans and strategies before advancing to the application stage.
-
Stage 3: Project Refinement: (Completed)
The Project Refinement stage is where we finalise project plans and submit the required planning applications to the relevant planning authorities. Communities and other key stakeholders can provide feedback directly to the appropriate body such as their local council and constituent representatives.
-
Stage 4: Construction Phase: (In progress)
Within the construction phase we mobilise our workforce, contractors, and necessary equipment to begin construction. We maintain open channels of communication, allowing communities and stakeholders to submit feedback on the construction activities to our dedicated Community Liaison Managers, ensuring ongoing engagement to any thoughts or concerns while we carry out work in the area.
-
Stage 5: Operational Phase:
At this final stage, the project successfully moves into the operational phase, with the surrounding environment restored to its original state or better. Our Community Liaison Mangers continue to be available to address any questions or concerns, ensuring a lasting positive impact and strong community relations even after the construction activities conclude.
About the Project
The Crossaig Substation Project comprises the construction of a new 275kV substation and overhead line, which will connect into the recently completed 275kV overhead line between Inveraray and Crossaig. Associated access, drainage, fencing and landscaping are included in the project plans.
The new substation will provide an upgrade to the existing 132kV Crossaig Substation and will support the export of renewable energy from the Argyll area.
Find Out More About Inveraray - Crossaig 275kV Overhead Line
Why is the Project Required?
Due to the projected increase in renewable energy generation in Argyll, a need has been identified for the upgrade and reinforcement of the electricity transmission network on the Argyll peninsula, to ensure security of electricity supply and support the transition to Net Zero.
The replacement Inveraray - Crossaig Overhead Line has been completed at a higher voltage of 275kV. As increased renewable generation requires connection to the electricity network, and the operating voltage is required to increase to 275kV, four 132kV substations along the route need replacing to accommodate this.
Find Out More About Argyll and Kintyre 275kV Substations
Community Engagement
Throughout the life of our projects, we aim to work positively with local communities and keep people informed about what we are doing. This is particularly important when we are developing a proposal and we want to understand what local people think about our plans.
We endeavour to take the time to discuss proposals with local community councils, encourage engagement from the wider community and listen to the feedback we receive.
We will do our best to answer any questions and address issues or concerns that are raised with us.
When our project progresses into construction, we will continue working closely with the local community to ensure that our work has as little impact on the lives of those living and working in the area and as many long term positive effects as possible.
How we’re embracing artificial intelligence (AI)
We intend to use AI to assist our experienced teams in the analysis of your feedback, so we can categorise key points raised more quickly. You can learn more about how we’re utilising AI on this dedicated web page.
Project Updates
Featured updates
Featured updates for this project
Project updates
-
We're here to lend a helping hand
We are committed to supporting the communities in the north of Scotland where we operate, both now and in the future. As part of our ongoing efforts to make a difference and have a positive impact on local communities, we are proud to offer volunteering days to local groups and charities, particularly in the areas that host our electricity infrastructure or where our proposed projects are located.
This month, we’re excited to announce the launch of our new Volunteering Webpage, designed to make it easier for local communities to request volunteering support from us. To request our help, simply complete the ‘Volunteering Nomination Form’ linked at the bottom of our new webpage. Please note, as our team works on a voluntary basis, it may take us some time to coordinate our people and match them with opportunities. We kindly ask for your patience as we work to keep up with volunteering demand.
Thank you for considering SSEN Transmission as a partner in your community efforts. Together, we can leave a positive, lasting legacy and help transform communities across the north of Scotland.
-
Site Closure 2024
Works on site will pause for the 2024 festive period with the site closing from 20 December 2024 until 6 January 2025. Although the site will be closed for all construction workers during this period, security will remain in place. -
Notification of Blasting Works
As part of the associated construction works for the new Crossaig 275kV substation our Principal Contractor Siemens-BAM will be undertaking a programme of rock blasting in the vicinity of the substation site from 24 October for approximately 8 weeks. We anticipate there to be 10 blasts within this period.
Please note these works will not impact the movements of the local community or visitors to the area and while we expect any noise disruption to be minimal, we would like to apologise in advance for any caused due to the works. All works are undertaken in line with industry best practice, however, if you have any concerns on these activities, please do not hesitate to contact your Community Liaison Manager Martha SmartProject update
With forestry works complete, our principal contractor has mobilised to site. Key upcoming works include drainage on the Crossaig North platform with water being diverted to the onsite peat restoration area and the installation of access tracks linking Crossaig South with existing Crossaig North and Overhead Line platform. In addition, access track repairs and maintenance work across the Cross Kintyre Haul Road are ongoing.
The project working hours are as follows;
07.00hrs to 19.00hrs Mon to Friday
07.00hrs to 18.00hrs Saturday
07.00hrs to 17.00hrs Sunday
If you have any questions about this update or the project in general, please contact the Community Liaison Officer;
Martha Elizabeth Smart M: 07880998846
E: Martha.E.Smart@sse.com
-
May CLG Meeting Minutes
May CLG Meeting Minutes
7 May 2024
The 1st combined Crossaig and Craig Murrail substations CLG meeting on 7 May was held via Microsoft Teams. Minutes from the meeting can now be downloaded from the project documentation section of this website. If you have any issues, concerns or comments you would like discussed at a CLG, please contact the Community Liaison Manager, Martha Smart.
Martha.e.smart@sse.comCore Path Disruption
We would like to alert users of a disruption to the core path network as part of the associated works for this project.
The disruption relates specifically to the bridge, shown on the map, just north of Ford at Carradle Water. The works will run from 05/07/24 to 08/07/24 and are intended to secure the bridge for the heavy loads. On Friday 05/07/24 all recreational users will be able to pass the bridge with assistance from contractors. However, there will a period of time on Saturday and Sunday from 10am-1pm where the bridge will not be passable. During this time an alternative walkway will be installed to ensure users are still able to cross safely.
If you have any questions regarding this update please email the Community Liasion Manager.
Martha Smart Martha.E.Smart@sse.com -
June CLG Meeting Minutes
The second combined Crossaig and Craig Murrail substations CLG meeting on 17 June was held via Microsoft Teams. Minutes from the meeting can now be downloaded from the project documentation section of this website. If you have any issues, concerns or comments you would like discussed at a CLG, please contact the Community Liaison Manager, Martha Smart. -
Forestry update
Felling works on this project are due to take place week commencing 29/01/24. These works will consist of the following;
Timber Harvesting.
Mulching.
De-stumping by mulching to ground level of all stumps.
Small-scale motor-manual felling, chipping and timber extraction.
Small-scale arboricultural works.
If you have any questions regarding the above get in touch with the project community Liaison Manager.Meet the Buyer Event
SSEN Transmission will soon begin construction on the Argyll and Kintyre 275kV substations.
As part of these projects and our ongoing commitment to ensure that where possible, opportunities are advertised locally in the first instance, we are welcoming local businesses to attend a informal drop-in meeting to engage with our principal contractor and to exchange details to discuss the possible opportunities for the local supply chain.
These projects have the potential to create local business and employment opportunities in the following fields: Accommodation, fencing, skip hire, catering, cleaning services, plant hire, general operations workers, groundworkers, electricians and more. We would encourage any relevant local businesses to attend these events and discuss what possible business opportunities there are with our principal contractors.
This drop event will be held at the following date and location;
Crossaig North Substation
Thursday 15 February 2024, 2–6pm
Carradale Village Hall, Carradale, PA28 6QG -
Argyll and Kintyre project - Final Needs Case consultation
The GB electricity regulator Ofgem has provisionally approved SSEN Transmission’s proposals to upgrade the electricity transmission network in Argyll and Kintyre.
In its minded-to approve consultation on SSEN Transmission’s Final Needs Case, Ofgem has recognised the clear need for the Argyll and Kintyre Reinforcement Strategy, which will secure future electricity supplies in the area and enable the connection of new renewable electricity generation in the region. It will support the connection of at least 970MW of new renewable electricity generation, enough to power more than 500,000 homes.
As well as supporting the transition to net zero emissions, the investment will also help secure the country’s future energy independence by removing the country’s dependence and price exposure to volatile, global wholesale gas markets, with the deployment of low carbon, affordable, renewable electricity generation.The project will also unlock hundreds of skilled jobs throughout the construction phase and provide a significant economic boost to local and national economies, all while playing a key role in supporting the transition to net zero emissions and helping secure the country’s future energy independence.
Ofgem’s minded-to decision and consultation on the Argyll and Kintyre Final Needs Case can be found here: https://www.ofgem.gov.uk/publications/argyll-and-kintyre-project-final-needs-case-consultation.
As a stakeholder led business SSEN Transmission would like to encourage all interested and relevant stakeholders to contribute to this important consultation before the closing date on 15th of September 2023. -
Argyll and Kintyre 275kV Substation Town and Country planning consent granted
We recently recieved town planning country planning consent for An Suidhe, Crarae, Craig Murrail and Crossaig North substations . We are currently still awaiting decision on our Section 37 applications for these projects from Scottish ministers. Once we receive notification of their outcome we will provide an update to public stakeholders and also publish this information and next steps on our project webpage. -
Crossaig North Town and Country Planning Application submitted
A planning application has been submitted by Scottish Hydro Electric Transmission plc (operating and known as SSEN Transmission) for detailed planning permission under The Town and Country Planning (Scotland) Act 1997 for the Erection of High Voltage Electricity Substation and Formation of Associated Access, Landscaping, Drainage and Means of Enclosure (the Crossaig North Substation) and an Extension to the Platform at the existing Crossaig substation, at land adjacent to the existing Crossaig Substation, approximately 8 km southwest of the village of Claonaig and approximately 6 km north of Grogport, Argyll and Bute.
The Proposed substation forms part of SSEN Transmission’s Argyll and Kintyre Strategy and is required to manage the transportation of renewable energy generation from Argyll to the wider electricity network. The substation would connect into the existing 275 kV Overhead Line (OHL) from Inveraray to Crossaig. An Environmental Appraisal (EA) has been carried out as a non-statutory assessment to allow appropriate environmental management and mitigation measures to be identified.
The relating documents for this application can be found on the project documents section of this webpage.Written comments may be made by e-mail: planning.hq@argyll-bute.gov.uk or Argyll and Bute Council, Development Management, Kilmory Castle, Lochgilphead, Argyll, PA31 8RT.
-
Crossaig North Substation S37 application submitted
SSEN Transmission have submitted their application for consent to the Scottish Ministers for consent under Section 37 of the Electricity Act 1989 1989 to install and keep installed approximately 372m of 275 kV overhead line supported on two new steel towers (one terminal tower and one angle tower) to connect the proposed 275 kV Crossaig North Substation to the existing 275kV Inveraray to Crossaig overhead line. The proposed development is located approximately 8 kilometres (km) southwest of the village of Claonaig and approximately 6 km north of Grogport in the Argyll and Bute local authority area.
Should you wish to view the documents contained within our Section 37 application in full, these are available within the project documents section of this webpage. These can also be viewed on the Scottish Government Energy Consents website at www.energyconsents.scot under application reference ECU00004763.Any representations on the application may be submitted to Scottish Ministers via the Energy Consents Unit website at www.energyconsents.scotAll representations should be made such that they are received by Scottish Ministers not later than 24th April 2023, although Scottish Ministers may consider representations received after this date.As a result of a statutory objection from the relevant planning authority, or where Scottish Ministers decide to exercise their discretion to do so, Scottish Ministers can also cause a Public Inquiry (PI) to be held.
-
Argyll and Bute Information Sharing Webinar 2022
Please click to view our 2022 Argyll and Bute regional webinar where some of the SSEN team have given an overview of ongoing and upcoming projects across the area. -
Submission of our Initial Needs Case for the Argyll and Kintyre 275kV Strategy
We have submitted to the energy regulator, Ofgem, robust proposals to reinforce the Argyll transmission network from 132kV to 275kV operation. At an estimated cost of around £400m, this investment is being taken forward as part of the SSE Group’s Net Zero Acceleration Programme, which will see £12.5bn invested in the five years to 2026, or £7m every day. SSEN Transmission alone expects to invest around £4bn over this period as it delivers a network for net zero emissions. The Argyll 275kV strategy is required to support the connection of several new renewable electricity generation schemes across Argyll and to transport that power to areas of demand across Scotland and beyond. It will support the connection of at least 560MW of new renewable electricity generation, enough to power more than 500,000 homes. -
Pre- Application Consultation Closed
Thank you to those who participated in our Winter 2021 online pre-application consultation and provided feedback on our proposals for the Argyll and Kintyre 275kV Substations project. Our consultation period closed on 10th January and all feedback received will be collated, reviewed and included in the Pre-Application Consultation (PAC) Report which will accompany the Planning Applications submission to Argyll and Bute Council in Spring 2022. As part of our consultation we held a webinar on 14th December 2021, inviting statutory consultees, community council members and local elected members to discuss our proposals ahead of our planning application process. Please see a recording of the webinar adjacent for more information. -
Argyll and Bute Information Sharing Webinar
On Wednesday 17th March 2021, SSEN Transmission hosted an Argyll and Bute Information Sharing Webinar, to provide local stakeholders with an interest in future electricity network plans for Argyll and Bute the chance to join us to hear about our stakeholder-led plans for the future and receive an update on the current construction and operation activities in the region. For those who were unable to attend, we have uploaded a recording of the session which you can view by clicking on the adjacent video.
Documents
-
CLG minutes 12 Nov 24.pdf
- Type:
- Date:
- 24 April 2025
- Size:
- 339 KB
-
CLG mins 03 Sept.pdf
- Type:
- Date:
- 15 January 2025
- Size:
- 1.1 MB
-
CLG mins 17 June.pdf
- Type:
- Date:
- 16 October 2024
- Size:
- 206.7 KB
-
CLG mins 7 May.pdf
- Type:
- Date:
- 16 October 2024
- Size:
- 208.6 KB
-
Argyll-and-Kintyre-A5-Mailer-V4.pdf
- Type:
- Date:
- 27 October 2023
- Size:
- 161.3 KB
-
Argyll and Kintyre Reinforcement Strategy LOTI Final Needs Case 2023.pdf
- Type:
- Date:
- 13 June 2023
- Size:
- 3.4 MB
-
Pre_Application_Consultation_Report[1].pdf
- Type:
- Date:
- 26 January 2023
- Size:
- 6.5 MB
-
Planning_Statement[1].pdf
- Type:
- Date:
- 26 January 2023
- Size:
- 775.3 KB
-
appendix-1-figures-1-2.pdf
- Type:
- Date:
- 18 September 2022
- Size:
- 7.7 MB
-
appendix-1-figures-3-4.pdf
- Type:
- Date:
- 18 September 2022
- Size:
- 7.4 MB
-
appendix-1-figures-5-7.pdf
- Type:
- Date:
- 18 September 2022
- Size:
- 6.9 MB
-
argyll-and-kintyre-275kv-strategy-consultation-brochure-2021.pdf
- Type:
- Date:
- 18 September 2022
- Size:
- 10.2 MB
-
argyll-and-kintyre-275kv-strategy-consultation-poster-2021.pdf
- Type:
- Date:
- 18 September 2022
- Size:
- 100.7 KB
-
argyll-and-kintyre-275kv-substations-pre-application-consultation-final01.pdf
- Type:
- Date:
- 18 September 2022
- Size:
- 23.3 MB
-
r162_11091-002_consultationdoc_final.pdf
- Type:
- Date:
- 18 September 2022
- Size:
- 6.4 MB
-
roc-argyll-substations.pdf
- Type:
- Date:
- 18 September 2022
- Size:
- 9.4 MB
-
ssen_t-argyll-webinar-17march21-final-slides.pdf
- Type:
- Date:
- 18 September 2022
- Size:
- 3.5 MB
-
Cover Letter s.37 Crossaig North.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 184 KB
-
Chapter 1 Contents, Introduction and Scope.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 910.9 KB
-
Chapter 10 Mitigation Summary.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 465.4 KB
-
Chapter 2 Project Description.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 7.7 MB
-
Chapter 3 Landscape and Visual.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 423.9 KB
-
Chapter 4 Ecology and Ornithology.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 4.5 MB
-
Chapter 5 Forestry.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 1.5 MB
-
Chapter 6 Hydrology, Hydrogeology and Geology.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 2.5 MB
-
Chapter 7 Archaeology and Cultural Heritage.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 3.5 MB
-
Chapter 8 Noise.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 307 KB
-
Chapter 9 Traffic and Transport.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 544.2 KB
-
Annex A - General Environmental Management Plans.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 4.3 MB
-
Annex B - EIA Screening.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 384.3 KB
-
Annex C - LVA Methodology.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 474.8 KB
-
Annex D - Landscape Character Sensitivity.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 245.5 KB
-
Annex E Part 1 - Landscape Figures 3.1-3.4 .pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 4.2 MB
-
Annex E Part 2 - Landscape Figure 3.5.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 879.8 KB
-
Annex E Part 3 - Photomontages.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 3.4 MB
-
Annex F - Ornithology Consultation.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 920.7 KB
-
Annex G Part 1 - Extended Phase 1 Survey Report.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 3.5 MB
-
Annex G Part 2 - Extended Phase 1 Survey Report.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 4.4 MB
-
Annex H - Species Protection Plans.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 3.6 MB
-
Annex I - HRA.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 3.6 MB
-
Annex J - Forestry.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 3.9 MB
-
Annex K - Drainage Strategy and Drainage Plans.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 1.7 MB
-
Annex L - Hydrology Methodology.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 320.7 KB
-
Annex M - Private Water Supply Risk Assessment.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 1 MB
-
Annex N - Water Construction Management Plan.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 2.7 MB
-
Annex O - Peat Management Plan (PMP).pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 1.6 MB
-
Annex P - Peat Slide Risk Assessment (PSRA).pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 4 MB
-
Annex Q Part 1 - Routing Report.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 4.1 MB
-
Annex Q Part 2 - Routing Report.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 4.5 MB
-
Annex R Part 1 - Cultural Heritage Appraisal and Site Gazetteer.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 2.4 MB
-
Annex R Part 2 - Cultural Heritage Appraisal and Site Gazetteer.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 3.4 MB
-
Annex S - Noise.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 1.8 MB
-
Figure 1 Site Location and Layout Plan Overview.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 2.5 MB
-
Figure 2 Site Layout Plan.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 1.6 MB
-
Figure 3 OHL Tower Elevations.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 734.2 KB
-
Figure 4 - Site Access Detail.pdf
- Type:
- Date:
- 15 March 2023
- Size:
- 758.7 KB
-
21_01325_PREAPP Crossaig North PAC Report.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 9.8 MB
-
Annex A - General Environmental Management Plans.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 4.3 MB
-
Annex B - EIA Screening.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 384.3 KB
-
Annex C - LVA Methodology.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 474.8 KB
-
Annex D - Landscape Character Sensitivity.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 245.5 KB
-
Annex E Part 1 - Landscape Figures 3.1-3.4 .pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 4.2 MB
-
Annex E Part 2 - Landscape Figure 3.5.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 879.8 KB
-
Annex E Part 3 - Photomontages.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 3.4 MB
-
Annex F - Ornithology Consultation.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 920.7 KB
-
Annex G Part 1 - Extended Phase 1 Survey Report.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 3.5 MB
-
Annex G Part 2 - Extended Phase 1 Survey Report.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 4.4 MB
-
Annex H - Species Protection Plans.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 3.6 MB
-
Annex I - HRA.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 3.6 MB
-
Annex J - Forestry.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 3.9 MB
-
Annex K - Drainage Strategy and Drainage Plans.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 1.7 MB
-
Annex L - Hydrology Methodology.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 320.7 KB
-
Annex M - Private Water Supply Risk Assessment.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 1 MB
-
Annex N - Water Construction Management Plan.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 2.7 MB
-
Annex O - Peat Management Plan (PMP).pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 1.6 MB
-
Annex P - Peat Slide Risk Assessment (PSRA).pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 4 MB
-
Annex Q Part 1 - Routing Report.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 4.1 MB
-
Annex Q Part 2 - Routing Report.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 4.5 MB
-
Annex R Part 1 - Cultural Heritage Appraisal and Site Gazetteer.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 2.4 MB
-
Annex R Part 2 - Cultural Heritage Appraisal and Site Gazetteer.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 3.4 MB
-
Annex S - Noise.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 1.8 MB
-
Chapter 1 Contents, Introduction and Scope.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 910.9 KB
-
Chapter 10 Mitigation Summary.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 465.4 KB
-
Chapter 2 Project Description.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 7.7 MB
-
Chapter 3 Landscape and Visual.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 423.9 KB
-
Chapter 4 Ecology and Ornithology.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 4.5 MB
-
Chapter 5 Forestry.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 1.5 MB
-
Chapter 6 Hydrology, Hydrogeology and Geology.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 2.5 MB
-
Chapter 7 Archaeology and Cultural Heritage.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 3.5 MB
-
Chapter 8 Noise.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 307 KB
-
Chapter 9 Traffic and Transport.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 544.2 KB
-
Crossaig North Planning Statement.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 1.1 MB
-
Figure 10 - Proposed Site Profiles.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 3.2 MB
-
Figure 11 - Proposed Site Access Profiles.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 1.2 MB
-
Figure 13 - Septic Tank and Borehole Plan.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 2.3 MB
-
Figure 4b - 275kV GIS Control Building Elevations.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 555.7 KB
-
Figure 4d- 132kV GIS Control Building Elevations.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 504 KB
-
Figure 4e - Transformer Building Layout.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 567.2 KB
-
Figure 4f - Transformer Building Elevations.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 466.6 KB
-
Figure 5 - Generator Building Elevations.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 426.1 KB
-
Figure 6 - Electrical Layout Elevations.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 568.6 KB
-
Figure 7 - Typical Deer Fence & Gate.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 301.2 KB
-
Figure 9 - Site Access Detail.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 545.7 KB
-
Red Line Boundary - Crossaig North.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 3.1 MB
-
Site Location Plan - Crossaig North.pdf
- Type:
- Date:
- 15 May 2023
- Size:
- 3.3 MB
FAQs
FAQs
-
SSEN Transmission is responsible for maintaining and investing in the electricity transmission network in the north of Scotland and our network extends over a quarter of the UK’s land mass, crossing some of its most challenging terrain.
Our operating area is home to vast renewable energy resources, and this is being harnessed by wind, hydro and marine generation. Working closely with National Grid Electricity System Operator (the 'ESO'), we enable electricity generators to connect to the transmission system, allowing the electricity generated by them to be transported to areas of demand across the country. -
Following a minority stake sale which completed in November 2022, SSEN Transmission is now owned 75% by SSE plc and 25% by Ontario Teachers’ Pension Plan Board.
SSE plc sold its UK domestic electricity and gas retail business, along with domestic energy services to OVO Energy in January 2020 and no longer manages these customer accounts.
-
It’s the highest voltage electricity network in the UK – the ‘motorway network’ of the energy world. It transmits large quantities of electricity over long distances via wires carried on a system of mainly metal towers (pylons) and large substations. Transmission voltages in Scotland are 132kV, 275kV and 400kV. Larger generation schemes usually connect to the Transmission system.
The lower voltage parts of the system are called distribution networks. In Scotland, these local networks operate below 132kV whereas in England the distribution network includes 132kV.
-
As a stakeholder-led business, throughout the life of our projects, we aim to work positively with local communities and keep people informed about what we are doing. This is particularly important when we are developing new projects, we want to understand what local people think about our plans.
We always endeavour to take the time to discuss our proposals with local community councils and the wider affected community and to carry out engagement throughout each of the development stages, listening to feedback before finalising project plans. The feedback we receive is vital to help us develop proposals that reflect the views of a variety of stakeholder.
-
To find out more about a project, visit our project web pages which can be searched by location or area. Each project has a dedicated Community Liaison Manager that you can contact. You can find their contact details in the individual project pages, where you can also sign up to project updates.
Project Contacts
Martha Smart | Community Liaison Manager
Lynn Dandie | Senior Land Manager
Recite me
To make use of this function please click on the 3 'A's' button at the bottom left of the website.
