Overview
Coire Mashie Substation and underground cable connection: update on ground investigation and forestry works
We would like to provide an update on upcoming ground investigation (GI) and forestry enabling works associated with the proposed Coire Mashie Substation and underground cable connection.
These surveys and enabling activities are an important part of the development process and will help inform the detailed design of the proposed project.
Welfare compounds and mobilisation
As part of the mobilisation process, two temporary welfare compound areas will be established to support the works. Welfare cabins are scheduled to be delivered to the FLS quarry area on 13 and 14 August 2026. A map showing the locations of the welfare compounds has been shared with local stakeholders.
Ground investigation works
Ground investigation works will be undertaken by BAM Nuttall.
Mobilisation is scheduled to begin on 17 August 2026 and will continue for three days. Borehole and trial pit investigations will then commence on 20 August 2026, starting in the Loch Earba area before progressing north-east across the site.
The programme is expected to run for approximately 10 weeks, with demobilisation anticipated on 21 October 2026.
Scope of works
The investigations will include:
- 78 trial pits
- 29 boreholes
- Up to 15 BAM Nuttall personnel on site at any one time
The information gathered will help improve understanding of ground conditions across the proposed development area and support ongoing project design work.
Working hours
Ground investigation works will be carried out on an 11-day fortnight working pattern, operating from Monday through to the following Thursday, between:
07:30 and 17:00
Planned weekend working
To help maintain progress, weekend working is currently planned every second weekend on the following dates:
- Saturday 22 August and Sunday 23 August 2026
- Saturday 5 September and Sunday 6 September 2026
- Saturday 19 September and Sunday 20 September 2026
- Saturday 3 October and Sunday 4 October 2026
- Saturday 17 October and Sunday 18 October 2026
Where weekend working is required, activities will be undertaken away from nearby properties wherever possible to minimise disturbance to residents.
Forestry enabling works
In parallel with the ground investigation programme, RTS Forestry will undertake forestry enabling works to facilitate access to investigation locations within forestry areas.
Mobilisation is scheduled for 17 August 2026, with works commencing on 18 August 2026 and continuing for approximately six weeks, concluding around 21 September 2026.
Scope of works
The forestry works will involve:
- Tree felling within pre-agreed areas
- Mulching of vegetation
- Stump removal
- Creation of temporary access corridors to trial pit and borehole locations
Up to six RTS Forestry personnel are expected to be on site at any one time.
Working hours
Forestry works will take place:
Monday to Friday, 07:00 to 19:00
Access arrangements
Access for both the ground investigation and forestry works will be taken from the A86 via the existing route serving Feagour and Loch Earba.
Properties most directly affected by these activities have been contacted separately with additional information regarding the planned works.
Looking ahead
As the project design has developed, alternative access options for the potential construction phase have also been explored.
Subject to the project receiving planning consent, the current preferred approach for construction of the proposed substation and underground cable connection would utilise an alternative access route. This approach could significantly reduce the amount of construction traffic using sections of the existing access route that will be used during the ground investigation and forestry works.
These proposals remain subject to planning consent and further design development. However, they represent a significant change from earlier concepts, and we are committed to keeping communities informed as project planning progresses.
Ongoing engagement
Maintaining open communication with local communities remains a key priority throughout the works programme.
Development Project Managers Darrell and Emma, who attended previous consultation events, will be undertaking regular site visits throughout the programme, typically on a fortnightly basis.
Should any concerns arise during the works, we will be happy to arrange discussions with the Community Council, local residents or other affected stakeholders where appropriate.
Contact us
If you have any questions about the upcoming works or would like further information about the proposed Coire Mashie Substation and underground cable connection project, please do not hesitate to get in touch with the project team. We will continue to provide updates as the works progress.
3D Visualisations Portal
To help provide a better indication of the site options for the proposed Coire Mashie substation within the local setting, we've created a 3D visualisation portal. The portal can be accessed via the link below, where you can view various viewpoints from across the proposed development.
It should be noted that the substation shown in the photospheres is indicative and subject to change following development and refinement of the substation design. There is no screening shown in the photospheres; however, this will be considered as the design develops.
About the Project
New Coire Mashie 400kV Substation
The new 400kV substation required near Ardverikie Estate and Kinloch Laggan in the Highlands of Scotland to allow the connection of Earba Pumped Storage HydroScheme to the National Grid.
The new substation would also be:
- Required to connect into the existing Beauly-Denny overhead line.
- Sited relatively close to the existing Beauly-Denny overhead line to limit the additional infrastructure required.
New Earba 400kV Underground Cable
The Earba Pumped Storage Hydro Scheme requires connection to the National Grid. To facilitate this, a new400 kV underground cable is proposed.
The new underground cable would be:
- Connected from Earba Pumped Storage Hydro Schemes on-site powerhouse located by the Southeast shore of Loch Earba to the new proposed Coire Mashie Substation.
- Approximately 15km in length depending on the route option that is chosen following consultation. We will be able to provide more information regarding the underground cable route once the location for the new 400kV substation has been determined following consultation with local community members and statutory stakeholders.
Why is the Project Required?
SSEN Transmission is required to connect to the proposed Earba Pumped Storage Hydro (PSH) Scheme with an installed capacity of up to 1,800MW.
Under our Network Operators Licence we are required to deliver the connection in a technically efficient, co-ordinated and economic manner, whilst having the least practicable impact on people and the environment
The Proposed Development is located on Ardverikie Estate and Kinloch Laggan, approximately midway between Newtonmore and Spean Bridge, and would operate by transferring water between a lower reservoir, Lochan na h-Earba and an upper reservoir, Loch a' Bhealaich Leamhain.
Further information can be found on Gilkes Energy Ltd website earbastorage.co.uk
Planning was submitted for the Earba PSH in March 2024 - Section 36 planning application can be viewed on the Energy Consents website energyconsents.scot/ApplicationDetails.aspx?cr=ECU00005062
The project is expected to start in mid 2028 and be completed in Late 2032.
Community Engagement
Throughout the life of our projects, we aim to work positively with local communities and keep people informed about what we are doing. This is particularly important when we are developing a proposal and we want to understand what local people think about our plans.
We endeavour to take the time to discuss proposals with local community councils, encourage engagement from the wider community and listen to the feedback we receive.
We will do our best to answer any questions and address issues or concerns that are raised with us.
When our project progresses into construction, we will continue working closely with the local community to ensure that our work has as little impact on the lives of those living and working in the area and as many long term positive effects as possible.

How we’re embracing artificial intelligence (AI)
We intend to use AI to assist our experienced teams in the analysis of your feedback, so we can categorise key points raised more quickly. You can learn more about how we’re utilising AI on this dedicated web page.
Project Updates
Featured updates
Featured updates for this project
Coire Mashie Substation and underground cable connection: update on ground investigation and forestry works
Project updates
Documents
Project Documents
Report on Consultation and Additional Site Options
Site Selection Public Consultation Documents - May 2025
FAQs
FAQs
Recite me
To make use of this function please click on the 3 'A's' button at the bottom left of the website.