Overview
SSEN Transmission Stannergate 132kV Substation and Network Rail Feeder Station Planning Application
Following the pre-application consultation feedback event that we hosted in August of last year at the Apex Hotel in Dundee please be advised we have now submitted our planning application to Dundee City Council for the proposed Stannergate 132kV substation and Network Rail feeder station project.
The primary drivers for the new 132kV substation in the Stannergate area are SSEN Transmission’s obligation for asset upgrades and reinforcements and a new 132kV connection request from Network Rail.
Now approaching 60 years of service, many of the Transmission assets in Dundee have either exceeded or are nearing the end of their economic and operational capability. We are therefore proposing to build a new 132kV substation in the Stannergate area (near Dundee Harbour). This site will provide a location to replace the existing Dudhope substation, which helps provide power to Dundee. In addition, our proposals for this project include a new 132kV feeder station to support Network Rail’s ambitions to electrify the rail network within Scotland’s Central Belt.
Our planning application to construct and operate the Stannergate 132kV substation and Network Rail feeder station located at land bounded by East Dock Street, Market Street and Broughty Ferry Road, Stannergate, Dundee, has been made to Dundee City Council under reference 25/00359/FULN. To view our application in full and submit formal comment to the council, please visit the Dundee City Council planning portal, using the above reference. A copy of the voluntary Environmental Assessment is also available to be viewed and downloaded via the documents section of this webpage where you will find all the associated documents for this project.
We would like to thank those who provided feedback as part of our pre-application consultation events, which have been key in helping us shape our proposals and we now look forward to working with Dundee City Council and other key stakeholders as part of the consenting process.
If you would like to be kept up to date with the development of this project, you can register to receive updates on the button at the top of this page. In addition, if you have any queries please don't hesitate to contact the Community Liaison Manager.
About the Project
SSEN Transmission are developing proposals to replace and upgrade Dundee’s high voltage electricity network.
Now approaching 60 years of service, many of the Transmission assets in Dundee have either exceeded or are nearing the end of their economic and operational capability. We are therefore consulting on proposals to build a new 132kV substation in the Stannergate area (near Dundee Harbor). This site will provide a location to replace the existing Dudhope substation, which helps provides power to Dundee. In addition, our proposals for this project include a new 132kV feeder station to support Network Rail’s ambitions to electrify the rail network within Scotland’s Central Belt.
Community Engagement
Throughout the life of our projects, we aim to work positively with local communities and keep people informed about what we are doing. This is particularly important when we are developing a proposal and we want to understand what local people think about our plans.
We endeavour to take the time to discuss proposals with local community councils, encourage engagement from the wider community and listen to the feedback we receive.
We will do our best to answer any questions and address issues or concerns that are raised with us.
When our project progresses into construction, we will continue working closely with the local community to ensure that our work has as little impact on the lives of those living and working in the area and as many long term positive effects as possible.
How we’re embracing artificial intelligence (AI)
We intend to use AI to assist our experienced teams in the analysis of your feedback, so we can categorise key points raised more quickly. You can learn more about how we’re utilising AI on this dedicated web page.
Project Updates
Featured updates
Featured updates for this project

SSEN Transmission Stannergate 132kV Substation and Network Rail Feeder Station Planning Application
Project updates
Documents
Project Documents
-
August 2024 Pre Application Consultation Feedback Event Booklet
- Type:
- Date:
- 06 August 2024
- Size:
- 4 MB
This document provides information to our stakeholders about the project and was provided during our consultation in August 2024
-
Stannergate 132kV Substation and Network Rail Feeder Station.pdf
- Type:
- Date:
- 07 May 2024
- Size:
- 1.7 MB
This document provides information to our stakeholders about the project and was provided during our consultation in May 2024
Planning Application - Planning Statement
Planning Application - Environmental Appraisal and Appendices
Planning Application - PAC Report and Appendices
FAQs
FAQs
Recite me
To make use of this function please click on the 3 'A's' button at the bottom left of the website.