Eastern Green Link 2
- Type:
- Transmission reinforcement
- Location:
- Aberdeenshire
- Rating:
- Subsea
A new high voltage subsea cable, transporting clean energy from the north of Scotland to England to power around two million homes.
Overview
Status: Construction Phase
Stage 4 of 5
-
Stage 1: Project Assessment: (Completed)
During the Project Assessment stage, we’re committed to evaluating potential project strategies. At this stage, we provide information about the proposed project plans on our website for stakeholders to review and provide feedback on, as well as holding in-person events within the local community demonstrating our collaborative approach to the project's development.
-
Stage 2: Early Development: (Completed)
During Early Development, we concentrate on refining the project details, based on our initial assessment of key environmental, technical, and economic factors to identify the best performing approach. We would like to gain further input from communities through accessible in-person and in some cases online consultations, which are crucial in refining our plans and strategies before advancing to the application stage.
-
Stage 3: Project Refinement: (Completed)
The Project Refinement stage is where we finalise project plans and submit the required planning applications to the relevant planning authorities. Communities and other key stakeholders can provide feedback directly to the appropriate body such as their local council and constituent representatives.
-
Stage 4: Construction Phase: (In progress)
Within the construction phase we mobilise our workforce, contractors, and necessary equipment to begin construction. We maintain open channels of communication, allowing communities and stakeholders to submit feedback on the construction activities to our dedicated Community Liaison Managers, ensuring ongoing engagement to any thoughts or concerns while we carry out work in the area.
-
Stage 5: Operational Phase:
At this final stage, the project successfully moves into the operational phase, with the surrounding environment restored to its original state or better. Our Community Liaison Mangers continue to be available to address any questions or concerns, ensuring a lasting positive impact and strong community relations even after the construction activities conclude.
Project Updates
Featured updates
Featured updates for this project
North Aberdeenshire Local Fund
Planned out of hours working
EGL2 Peterhead works progressing well
Preparations begin at Peterhead landfall site
Project updates
-
North Aberdeenshire Local Fund
We are establishing a new community benefit fund for communities hosting new transmission infrastructure across North Aberdeenshire. The Fund is aimed specifically at communities close to the project infrastructure.
Help design the new fund
We are holding several consultation events to share more information and find out what local communities want the fund to look like.
This is an exciting opportunity to shape key elements of the new fund, including the sorts of projects or activities that will be eligible for funding, how long the fund will run for and the amount of funding available per year.
All community members who live or work in the following areas are warmly invited to attend a local event to learn more about the Fund and share their views on the issues and opportunities that matter most to them:
• Longside and District
• Strathbogie
• Turriff and District
• Huntly
• Mintlaw
• New Deer
• Auchterless, Inverkeithny and Fisherford
• Fyvie, Rothienorman and Monquhitter
• Peterhead
• Boddam
Drop in consultation events
• Baden-Powell Centre, Turriff - Wednesday 28 October
Session 1: 2–4pm, Session 2: 7–9pm
• The Hub, Peterhead - Thursday 29 October, 3.30–7.30pm
• Cuminestown Village Hall - Friday 30 October, 3.30–7.30pm
• Cairnie Memorial Hall - Monday 2 November, 3.30–7.30pm
• Maud Resource Centre - Tuesday 3 November, 10.30am–4pm
• New Deer Public Hall (small hall) - Wednesday 4 November, 3.30–7.30pm
• MACBI, Mintlaw - Thursday 5 November, 10am–4pm
• Buchan Braes Hotel, Boddam - Thursday 19 November, 5.30–8.30pm
• Huntly Farmers Market - Saturday 7 November, 10am–1pm
• Longside Parish Church Hall - Friday 20 November, 3.30–7.30pm
Online event and survey
11 and 16 November, 7–8pm
Register your interest on our website. -
Planned out of hours working
As construction progresses at the Peterhead converter station, periods of 24-hour, seven days a week working are planned to support the next stage of work.
A carefully planned 24-hour operation will allow the team to complete the works in a continuous and coordinated way, avoiding repeated stoppages and reducing the risk of delays.
About the works
The upcoming approved work involves installing a network of ducts inside the converter buildings. These ducts are protective pipes that will provide safe routes for electrical cables through the buildings.
An additional period of extended working hours may be required as the project continues to progress, and further communications will be issued should these arise.
Timing of the works
Aberdeenshire Council has approved 24-hour, seven days a week working during the following period:
05 October to 30 November 2026
There may be periods when weekend work is not necessary. We hope to complete the works in a shorter timeframe, but we have allowed for construction and weather delays.
Managing local impacts
Machinery for activities will include excavators, dumpers, rollers and telehandler. As all work will be contained within the footprint of the fully clad buildings, we don't anticipate any disruption to the surrounding area.
Measures will be used to limit disturbance, including directing lighting away from nearby properties, limiting vehicle reversing and moving excavated material during daytime hours where possible.
Thank you
We will continue to carry out the work with least disruption possible. We apologise for any inconvenience we may cause, and we thank you for your patience as we build this nationally significant energy infrastructure project. -
EGL2 Peterhead works progressing well
Construction on the Eastern Green Link 2 (EGL2) project continues to progress well, with important milestones recently achieved at both the landfall site at Sandford Bay and the converter station near Peterhead.
At Sandford Bay, the first horizontal directional drilling (HDD) pilot hole beneath the beach has been successfully completed, marking a significant step towards the future installation of the subsea cable connection.
At the converter station, the first converter building steel frame has been completed, construction of the AC halls is advancing, and concrete works for both transformer buildings are now finished.
Work will continue over the coming months as construction teams progress building works, complete the second borehole at the landfall site, and prepare for future cable, mechanical and electrical installations.
For further information, please see the project update document.
-
SSEN Transmission publishes new economic analysis highlighting transformative growth potential of £29bn grid investment programme
We have today published a new economic report setting out the significant economic benefits associated with our planned £29bn investment in new and upgraded electricity transmission infrastructure across the north of Scotland.
The report, titled ‘Re‑energising the North: Transforming Scotland’, provides an update on our previously outlined economic analysis on plans to invest billions in mission-critical grid infrastructure, providing further insight into the scale of economic opportunity associated with the investment programme.
The report reaffirms our programme as one of the largest private infrastructure investments in Scotland’s history, with around £29bn of planned investment across the north of Scotland in the next five years, and it details the extent of the economic opportunity across the region.Using advanced economic modelling to analyse the impact of clean power infrastructure investment, the report’s findings conclude that our investment:
- Will support up to 10,000 jobs in the north of Scotland, and 24,000 across Scotland;
- When added to investment by other transmission operators and investment in generation will add around £60bn to UK economic output - with the Scottish economy up to 3% larger over the long term;
- Will deliver long-term improvements in productivity, wages and economic resilience, with employees moving into higher-value roles and key sectors expanding permanently; and
- Will create unique opportunities for Scottish suppliers, businesses and communities across multiple sectors, including forestry, peatland restoration, aggregates and concrete too.
The findings highlight the importance of ensuring that the benefits of investment are felt locally, with thousands of skilled jobs, increased supply chain activity, and investment flowing into communities across the north of Scotland.
Read the full News and Views article to find out more. -
Funding recipient story: Peterhead Sea Cadets Unit
The Peterhead Sea Cadets Unit has received £21,755 from the Eastern Green Link 2 Peterhead Local Fund to replace its 25-year-old rigid inflatable safety boat (RIB) with a new Humber Destroyer 5.8M RIB. This upgrade is essential to maintain safety standards and ensure the continued delivery of high-quality waterborne training for young people.
Investing in safety and skills for the future
From April to September, cadets aged 10–18 take part in activities such as rowing, sailing, paddle sports, and power-boating within Peterhead Marina and Bay. These sessions, led by qualified volunteers, rely on the safety boat for emergency cover and instruction. The new RIB will provide proper seating for all crew members, reducing the risk of injuries during high-speed manoeuvres and meeting modern safety guidelines.
This investment will allow the unit to offer more boating hours, help cadets gain nationally recognised qualifications, and develop skills that can lead to careers in maritime industries. With careful maintenance, the new safety boat will serve the community for the next 25 years, ensuring generations of young people benefit from safe, engaging, and educational experiences on the water.
Marleen Mowatt from Peterhead Sea Cadets, said:
“The funding awarded to Peterhead Sea Cadets from the Eastern Green Link 2 Peterhead Local Fund has enabled the organisation to purchase a new rigid inflatable boat. This replaces our current 25-year-old vessel with an up-to-date model which is fitted with excellent safety and training features.
As well as providing essential quick response safety cover, it will also allow our well qualified instructors to teach navigation, radio and boat handling skills, all of which are transferable to possible future roles in the workplace. Also, because the new boat is larger and has a more powerful engine, cadets can now extend their coastal voyages to gain additional qualifications within the RYA syllabus.
Our adult volunteers are extremely grateful to SSEN Transmission for their support with this project and for investing in our young people.”
Substation cabling works begin
The Eastern Green Link 2 team will begin the first stage of works to prepare for the eventual connection of the new Peterhead converter station to the existing 400kV substation nearby. We are undertaking horizontal directional drilling (HDD) works to prepare for two new high voltage cable circuits that will connect the Eastern Green Link 2 converter station to the existing Peterhead 400kV substation nearby, and thereby to the transmission network.
The upcoming works include horizontal directional drilling and associated civils works required for the 400kV underground cable connection. Both cable corridors will contain three cables (six cables in total), with each route approximately 600 metres in length between the converter station and the Peterhead 400kV substation. Due to the need to cross beneath the U66 road and other utilities infrastructure, a section of the cable route will be installed using HDD technology to avoid disruption to road users and ensure safe installation.
Read the project update for more information.
Eastern Green Link 2 and SSEN Transmission teams support Aberdeenshire community during heavy snow
Eastern Green Link 2’s Peterhead team answered a call for assistance from NHS Grampian earlier this month during the severe winter conditions affecting the region.
Aberdeenshire was hit by some of the harshest winter weather in recent years, with heavy snowfall causing significant disruption across the north-east region. As roads became too treacherous for many commuters, the Eastern Green Link 2 (EGL2) team stepped up to help a healthcare worker reach patients in need and an elderly neighbour who had become snowed in.
In response to a request from NHS Grampian, the team member transported a carer from Maud to Ellon and back using one of the project’s 4WD trucks, ensuring that two vital home appointments could be kept despite the adverse weather.
Beyond healthcare transport, the Peterhead Substation team and Eastern Green Link 2 team worked together during the same period to support an elderly neighbour who had become snowed in and was experiencing internet connectivity issues. After receiving a call from a concerned relative, the project manager from Peterhead Substation alerted the Eastern Green Link 2 team and they worked together on a response. During a home visit to discuss the issue with the resident, two of our EGL2 team members took the initiative to clear snow from around the house, ensuring safe access and peace of mind for her relatives.
The rapid response shown by the teams to those who were most at risk during cold weather reflects their dedication and commitment to making a difference to the communities that SSEN Transmission operates in.
-
Upcoming overnight working in Peterhead
We will carry out concrete pours during January and February at our Peterhead converter station construction site, these will require short periods of overnight work.
In a project update issued earlier in the year, we set out our plans for creating the walls for the building that will house the converter station’s transformer technology. We have now scheduled this work to commence in the new year.
We will construct the walls from concrete using a ‘slipform’ pouring system. This method of concrete pour must be carried out continuously as any pause would create joints in the concrete walls that could compromise structural integrity.
Overnight working
We are therefore proposing to carry out overnight works on the dates below, subject to weather conditions:
Thursday 8 to Friday 9 January 2026
Monday 19 to Sunday 1 February 2026
During that time, we are expecting an average of 3-4 concrete deliveries per hour. As this activity does not generate excessive noise, we don’t anticipate local impacts. However, we will require the site to be illuminated to ensure safe working conditions for our construction team.
Further works
Additional slipform concrete pours requiring overnight works will be carried out in March, and we will advise of dates nearer the time.
Thank you
We will continue to carry out the work with least disruption possible. We apologise for any inconvenience we may cause, and we thank you for your patience as we build this nationally significant energy infrastructure project.
About Eastern Green Link 2
We are constructing a new high voltage direct current (HVDC) converter station near Boddam in Peterhead as part of the Eastern Green Link 2 project. The joint venture project between SSEN Transmission and National Grid Electricity Transmission will see around 500km of subsea high voltage direct current (HVDC) cable connecting the Peterhead converter station to another one in Yorkshire. -
Preparations begin at Peterhead landfall site
Eastern Green Link 2 (EGL2) has reached another milestone in its construction programme with the start of works at our landfall site above Sandford Bay near Peterhead due to start later this month.
After a series of soil and ecology surveys and ground investigation works over the summer, we are now ready to begin the landfall enabling works at the Sandford Bay site.
About Eastern Green Link 2
We are constructing a new High Voltage Direct Current (HVDC) converter station near Boddam in Peterhead as part of the Eastern Green Link 2 project. The joint venture project between SSEN Transmission and National Grid Electricity Transmission will see around 436km of subsea HVDC cable connecting the Peterhead converter station to another one in Yorkshire.
The landfall at Sandford Bay is where our underground cable from the converter station transitions to a subsea cable, which then carries renewable energy through Scottish and English waters to a landfall point at Fraisthorpe Sands in Yorkshire. Horizontal directional drilling (HDD) is used to create ducts underneath the beach through which the cables are pulled and connected to the converter station.
Landfall enabling works – initial site establishment
Before the HDD drilling can commence next year, enabling works will be carried out to create the fenced HDD compound area, create the HDD hardstanding platform on which the drill will be positioned, and establish temporary welfare cabins and site offices. Access will be taken from an existing entrance point from the A90. These enabling works are due to begin on 17 October 2025.
Landfall enabling works – new access point off the A90
Ahead of the arrival of the HDD drilling rig on site next year, the existing entrance point from the A90 will require upgrading, specifically widening of the bellmouth junction. Subject to Planning Approval, this activity will commence towards the end of 2025.
Refer to the maps below showing the proposed location of the landfall site to the east of the A90.
Maintaining public rights of way
Pedestrian access along the adjacent A90 footpath will be maintained at all times. Public safety will be ensured through the use of barricades and fencing to separate pedestrians from the construction zones, as well as traffic and pedestrian signage. There will be no impact to the beach at Sandford Bay, and beach access will be maintained at all times.
Traffic managementNo traffic management is planned for the initial enabling works to site. Some traffic management will be required for the widening of the bellmouth later in the year, and details on this will follow in due course.
Working hours
Initial enabling works will take place between 7am and 6pm on weekdays. We don’t anticipate the need for weekend working during this phase. Additional hours may be required for the bellmouth widening activity, and this will be communicated in due course.

Map showing location of the HDD compound at the landfall site to the east of the A90.

Map showing access road and location of bellmouth
Thank you
We will continue to carry out the work with least disruption possible. We apologise for any inconvenience we may cause, and we thank you for your patience as we build this nationally significant energy infrastructure project.
More information about Eastern Green Link 2 can be found on the project website at www.easterngreenlink2.co.uk.
-
Supporting a celebration of seafood at Peterhead SeaFest
Community spirit was on display in September, with around 20,000 people gathering at SeaFest to celebrate Peterhead’s fishing heritage and sample the region’s seafood.
SSEN Transmission was proud to sponsor the event, and we joined exhibitors at the harbour to share information with the community about our offshore transmission projects: Spittal to Peterhead HVDC, Eastern Green Link 2 and Eastern Green Link 3.
Our team enjoyed speaking about local career opportunities in the energy industry and sharing information about our local community benefit fund, which has already begun to make a positive impact in the area.
A huge congratulations to the organisers and volunteers for staging such a successful – and delicious – event!
A cleaner future – onshore and offshore – for EGL2
More than 50 volunteers from SSEN Transmission, National Grid, and their contract partners for the Eastern Green Link 2 (EGL2) project rolled up their sleeves last week to take part in a hugely successful simultaneous beach clean at either end of the UK’s biggest ever electricity transmission project.
Beach cleans took place at Sandford Bay in Aberdeenshire and Fraisthorpe in the East Riding of Yorkshire, with the 50+ strong team – working in the sunshine – managing to remove more than five tonnes of rubbish from the coastline.
Following on from a similar clean-up at Sandford Bay last year, last week’s effort is the latest in a series of environmental initiatives by the EGL2 project, demonstrating the team’s continued commitment to making a positive difference in the communities where it operates.
Partnership in action
The day was made possible thanks to strong collaboration across the EGL2 joint venture team and its supply chain partners. BAM, David Smith Contractors, Prysmian and Balfour Beatty provided on-the-ground support to ensure the smooth running of the event.The group at Sandford Bay was again joined by Dr Lauren Smith from the East Grampian Coastal Partnership, who praised EGL2’s ongoing dedication to protecting Sandford Bay and the wider coastal environment:
“I was absolutely delighted to join the EGL2 team again this year for their clean-up of Sandford Bay, all of the volunteers put in an excellent effort and are committed to improving the Bay by removing the accumulating litter for the benefit of both the community and wildlife.”
A positive local impact
Speaking after the event, EGL2’s Project Director, Fionán Doonan said:
“We are committed to looking after the communities that we work and operate in and clearing more than five tonnes of rubbish from the beaches at either end of the EGL2 project is a fantastic achievement.
“Just as important, though, was the opportunity for our project teams and contract partners to come together outdoors, away from screens, and contribute to something that has a lasting benefit for the local environment. I’m already looking forward to next year’s beach clean!” -
EGL2 joins the fun at Peterhead’s Picnic in the Park
On a sunny day in July, we joined Peterhead families at the popular Picnic in the Park, part of the town’s Scottish Week celebrations.
It was great to meet residents, answer their questions and share information on how this critical project will support the UK’s energy transition.
We welcomed visitors of all ages to our stand, from those curious about how Eastern Green Link 2 is being built, to young people eager to explore careers in the energy sector. Our STEM circuit activities were a big hit, and some lucky residents won tickets to Aberdeen Science Centre in our colouring competition. We were delighted to support this community event.
SSEN Transmission sponsors Drone Light Show at Peterhead Scottish Week
We were delighted to sponsor the Drone Light Show for its debut outing at Peterhead Scottish Week this year. The spectacle drew huge crowds to Peterhead’s Lido, offering the best views as the 100 drones lit up the sky with images celebrating the town’s fishing heritage and community spirit, all synchronised to a soundtrack.Drones play an increasingly important role in our business at SSEN Transmission, as we innovate to deliver our projects more safely and efficiently than ever. That includes everything from inspecting overhead lines as part of our winter preparation, to deploying new technology to make the electricity grid more efficient, to installing bird flight diverters in support of a nature-friendly energy transition. Sponsoring this event was a great fit for us.
Peterhead Scottish Week ran from Saturday 12 July to Sunday 20 July and this year had 50 separate events. We’d like to offer our congratulations to the organising committee who work tirelessly to put on a fun and low-cost range of entertainment for the town.
We’re already looking forward to next year’s event.
Watch the show on Peterhead Scottish Week’s page here https://www.facebook.com/share/v/19G5XFGYz6/?mibextid=wwXIfr
Extended weekend working hours
We are writing to notify nearby residents and businesses that we require to extend our usual hours of construction to deliver some upcoming activities in connection with the Eastern Green Link 2 (EGL2) project.
Under the terms of our planning permission, working hours are restricted to between 07:00 to 19:00 Monday to Friday; and 07:00 to 13:00 Saturday unless otherwise agreed in writing with the planning authority. We have reached agreement with the planning authority that necessary operations outwith these stated times are required and can be undertaken. We will be undertaking these activities over the period between Saturday 19 July until March 2026. Please note that not all the activities detailed below will be undertaken for this entire period. Some activities will be undertaken for a short duration only.
Over this period it is necessary for us to extend our weekend working hours to:
07:00 to 17:00 Saturday
08:00 to 17:00 Sunday.
Why we are moving to a 7-day work schedule
We are extending weekend working hours to deliver some time-critical activities on site between now and March 2026:
1. Formwork and foundations: We will commence continuous concrete pours to create the formwork and foundations for the HVDC converter building. This activity involves multiple sequential activities, and quality and safety can be compromised by disruptions caused by non-continuous work schedules. It is therefore more efficient and safer to complete the works with fewer disruptions.
As this activity does not generate excessive noise, we anticipate only minimal local impacts primarily from concrete deliveries to our site.
2. Slipform Transformer Walls: We will commence concrete pours to construct the walls that will house the converter station’s transformers. This will be carried out using a ‘slipform’ pouring system, which must operate continuously as any pause would create joints in the concrete walls that could compromise structural integrity.
As this activity does not generate excessive noise, we anticipate only minimal local impacts primarily from concrete deliveries to our site.
3. Piling: Piling has been underway for several weeks to create the foundations for the converter station. It involves drilling and concreting reinforced piles into the ground. We are seeking to extend this to weekends to reduce interruptions which can lead to risks of concrete setting, equipment strain and potential instability in partially completed piles.
The piling technology that we are using (continuous flight auger piling) is low noise with no vibration, and therefore we do not expect our neighbours to be impacted by noise associated with this weekend working. Residents may notice some associated vehicle movements on site and concrete deliveries.
4. HDD installation: To prepare for the future connection of the 400kV AC cable from the new converter station to Peterhead Substation, Horizontal Directional Drilling (HDD) will commence from August. To reduce the risks caused by extended periods of inactivity including ground instability and equipment set up/fatigue the extended working hours will allow for continuous monitoring and workflow which will enhance site stability and operational safety and shorten the duration of this activity.
The HDD installation works will not generate excessive noise, but nearby residents will be aware of increased activity, deliveries and vehicle movements.
Duration of weekend working
Extended weekend working will be required for approximately eight months, commencing from Saturday 19 July until March 2026. However, not all activities listed above will occur over the entire period.
Advance notice of two weeks of 24-hour working
During the slipform concrete works mentioned above, it will be necessary to operate on a 24-hour basis for a period of two weeks. The exact dates will be weather dependent and will be communicated closer to the time, but the works are likely to take place towards the end of the year.
Thank you
We will continue to carry out the work with least disruption possible. We apologise for any inconvenience we may cause, and we thank you for your patience as we build this nationally significant energy infrastructure project.
About Eastern Green Link 2
We are constructing a new high voltage direct current (HVDC) converter station near Boddam in Peterhead as part of the Eastern Green Link 2 project. The joint venture project between SSEN Transmission and National Grid Electricity Transmission will see around 500km of subsea high voltage direct current (HVDC) cable connecting the Peterhead converter station to another one in Yorkshire.
More information about Eastern Green Link 2 can be found on the project website at www.easterngreenlink2.co.uk -
EGL2 team attend successful ‘Engage with Engineers’ event in Peterhead
On Saturday 10 May, the Eastern Green Link 2 (EGL2) team attended the 'Engage with Engineers' event hosted by the 2nd Battalion The Highlanders Army Cadet Force (ACF) in Boddam, near Peterhead, with the goal of inspiring the next generation of engineers.
The EGL2 team in conjunction with SSEN Transmission who are delivering the project in a joint venture with National Grid Electricity Transmission, were among 25 companies in attendance and they showcased an engaging stand focused on opportunities in the energy sector. The event was a great success, attracting over 120 attendees and receiving highly positive feedback.
Events like this allow EGL2 to engage with young people about careers in the renewable energy industry and answer questions about the project. This is particularly important in Boddam and Peterhead, where the Peterhead Convertor Station is being constructed and where the planned marine cable route will make landfall.
The event’s organiser, Major Stuart Eddie of 2nd Battalion The Highlanders ACF, echoed the importance of encouraging future engineers:
“The energy sector in north-east Scotland is a big sector for us, and it’s moving into a new era. I think it’s really important to start looking at future workforce and where it’s going to come from. You need to start building that interest now. It’s important for people to come along, it’s important for [EGL2] as an employer, as these youngsters are going to be your future workers’’.
Gillian Doig, Community Liaison Manager for EGL2, said there was a lot of interest in energy sector opportunities at the event:
“We were proud to stand alongside other local organisations who shared our goal of connecting with young people around the career opportunities on their doorstep. The students left with an understanding of why clean energy projects like EGL2 are so critical, the benefits they can bring to the local area in terms of skills and jobs, and hopefully they felt inspired to study engineering or take up an apprenticeship and return to their hometown for work. We were delighted to accept the invitation to attend this event at Boddam Army Cadet Centre.”
Final call for nominations for the Eastern Green Link 2 Peterhead Local Fund
Communities in Peterhead and the surrounding area are being urged to bid for a share of a new community benefit fund delivered as part of the UK’s biggest ever electricity transmission project, ahead of the application deadline on Thursday, 12 June.
The Eastern Green Link 2 (EGL2) Peterhead Local Fund will provide a total of £2,159,444 to communities in and around the Blue Toon over a five-year period.
The funding is intended to support projects and initiatives covering several priority areas that have been shaped by input from the local community.
EGL2 is a 525 kV, 2 GW high voltage direct current (HVDC) subsea transmission cable from Peterhead to Drax in Yorkshire delivered as a joint venture by SSEN Transmission and National Grid Electricity Transmission (NGET). The fund marks the latest step in progress on the £4.3bn project, which is due for completion in 2029.
The EGL2 Peterhead Local Fund includes a large project fund which will provide £410,294 per year in support for local projects, over a five-year period.
Priorities for the fund have been identified in consultation with the local community and include:
• Education, employment and skills
• Protection and enhancement of the natural environment (including land and sea, natural habitats, and biodiversity)
• Transport and connectivity (including path/cycle networks and community transport)
• Community infrastructure and regeneration
• Heritage and culture
• Community action planning and capacity building
A separate micro-grant scheme will see five local community councils each award £4,319 a year over five years, to fund any projects that benefit the local community up to the value of £500.
These grants are designed to provide immediate support, for example, to help the high number of youth groups and other third sector organisations within Peterhead and the surrounding area.
Ricky Saez, EGL2 Project Director from SSEN Transmission, said:
“With construction underway on EGL2, the launch of our EGL2 Peterhead Local Fund is another significant milestone in this project that will bring economic benefit to Peterhead and surrounding communities, throughout the construction phase and beyond.
"We have had strong interest in the fund since its launch in April, and urge anyone considering applying to the fund to send their Expression of Interest before the deadline on Thursday, 12 June.
"This fund has been shaped by input from the local community to prioritise projects that can have a transformational impact, underlining our determination that EGL2 delivers a strong legacy for communities and for the country.
"It is vitally important that local people engage with us on how the fund can best support local initiatives, and we are looking forward to hearing ideas that ensure that funding meets the needs of communities in Peterhead.”
Further information on the Eastern Green Link 2 Peterhead Local Fund, including how to apply for funding is available here - Our Eastern Green Link 2 Peterhead Local Fund.
Questions about the fund can be directed to community.benefit@sse.com. -
Marine surveys at Sandford Bay
We are conducting a series of offshore and nearshore marine surveys in and around Sandford Bay near Boddam in Peterhead over the next few months in connection with the Eastern Green Link 2 (EGL2) project.
The marine surveys will include:
1. Geophysical surveys in Sandford Bay, starting late May to end of June.
2. Geotechnical surveys in Sandford Bay, due to start in early July to August.
3. Potential unexploded ordnance (pUXO) target investigation, due to start August.
We are also carrying out onshore ecology, ground investigation, noise and soil surveys on the land adjacent to Sandford Bay, from around mid-June.
These surveys are required to inform the route for the marine cable element of this essential clean energy project. We appreciate that residents and the fishing community may be interested in our offshore activities, and we are pleased to provide more detail on the marine surveys in the attached project document. Public access to the beach at Sandford Bay will not be impacted.
Notices to mariners will be issued ahead of all works. We are grateful for the cooperation of the local fishing community while we undertake these surveys, and we will continue to work with them and other marine users to understand how we can reduce any impact on their activities as we deliver this critical national infrastructure project.Overnight traffic management
We are writing to provide advance notice of some temporary night-time traffic
management on the A90 and U66 in connection with the Eastern Green Link 2 (EGL2) project near Boddam, Peterhead.
The traffic management is necessary to install poles for new construction access and speed limit road signage. Temporary traffic lights will be deployed at various locations on the A90 and U66 where the signs are being installed, near our site south of Invernettie Roundabout. The new signage will help keep road users and pedestrians safe.
We will undertake these works at night to reduce disturbance to the local community.
Traffic lights will be removed during the day. Details of the works:
Date: Monday 05 May to Friday 09 May 2025
Time: Overnight from 10pm to 6am
Please view the map below for details of the signage locations.
We will carry out the work with least disruption possible. We apologise for the
inconvenience we may cause, and we thank you for your patience as we build this nationally significant energy infrastructure.
-
EGL2 newsletter – March 2025 edition
Read the latest news from Eastern Green Link 2 in our March newsletter.
-
We're here to lend a helping hand
We are committed to supporting the communities in the north of Scotland where we operate, both now and in the future. As part of our ongoing efforts to make a difference and have a positive impact on local communities, we are proud to offer volunteering days to local groups and charities, particularly in the areas that host our electricity infrastructure or where our proposed projects are located.
This month, we’re excited to announce the launch of our new Volunteering Webpage, designed to make it easier for local communities to request volunteering support from us. To request our help, simply complete the ‘Volunteering Nomination Form’ linked at the bottom of our new webpage. Please note, as our team works on a voluntary basis, it may take us some time to coordinate our people and match them with opportunities. We kindly ask for your patience as we work to keep up with volunteering demand.
Thank you for considering SSEN Transmission as a partner in your community efforts. Together, we can leave a positive, lasting legacy and help transform communities across the north of Scotland.
-
EGL2 newsletter – October 2024 edition
Read the latest news from Eastern Green Link 2 in our October newsletter. -
Flower power as SSEN Transmission install plant pots in Aberdeenshire community
An Aberdeenshire community will enjoy some flower power this summer after receiving help to install four large flowerpots by staff working on SSEN Transmission’s Eastern Green Link 2 (EGL2) subsea transmission project.
Staff from SSEN Transmission and contractors Keltbray rolled their sleeves up to help manoeuvre the large planters into position around the village, following a call for assistance from Boddam Community Council.
The flowerpots were installed in support of the Boddam Brighter Villages initiative, in preparation for planting in June.
Please click here to find out more. -
EGL2 newsletter – April 2024 edition
Read the latest news from Eastern Green Link 2 in our April newsletter.
-
SSEN Transmission sets out next steps for Pathway to 2030 network developments
We have announced our next steps for our Pathway to 2030 programme of projects. We would like to thank everyone who has engaged with our teams and kindly taken the time to respond to our consultations.
Full details of the announcement can be found here:
Next steps for Pathway to 2030 -
Eastern Green Link 2 - New Website
SSEN Transmission and National Grid Electricity Transmission (NGET) have taken a big step forward in the development of a new subsea electricity superhighway project along the east coast of the UK after reaching agreement on the terms of their joint venture (JV).
To celebrate this milestone a newly launched project website has been created where you can find all information relating to the project.
Please view the new EGL2 website, please click on the below image:
-
Marine Licence Granted
A major milestone has been reached in SSEN Transmission’s proposed new subsea electricity superhighway project along the east coast of Scotland following approval of the scheme’s marine licence.
The ‘Eastern Green Link 2’ project, which will be delivered in partnership with National Grid Electricity Transmission (NGET), will see the creation of a 2GW subsea transmission cable from Peterhead in Scotland to Drax, Yorkshire in England, enabling the transportation of low-carbon electricity by addressing existing constraints on the transmission system. This, in turn, will play a critical role in supporting the UK’s future security of supply, reducing dependence and price exposure to volatile global wholesale gas markets.
High-voltage direct current (HVDC) technology provides the most efficient and reliable means of transmitting large amounts of power over long distances subsea. With a capacity of 2GW, the Eastern Green Link 2 subsea transmission link will help to alleviate existing constraints on the electricity network, supporting the growth of new renewable electricity generation and progression of further links, creating jobs and delivering a pathway to net zero emissions targets.
Marine Scotland’s approval of this licence applies to the 150km stretch of cable that sits within Scottish waters, which is being developed by SSEN Transmission and NGET. The licence gives permission to install infrastructure within a 500m-wide defined corridor of the seabed from where the proposed cable makes landfall at Peterhead, to the Scottish-English maritime border.
To read the article in full please click here -
Marine Licence Application Submitted
We are pleased to confirm that SSEN Transmission has applied to the Scottish Ministers of the Scottish Government for Marine Licences in respect of Eastern Green Link 2 (EGL2) HVDC Cable and Cable Protection from Peterhead, Aberdeenshire to Scotland-England Water Border, under Part 4 of the Marine (Scotland) Act 2010 and Part 4 of the Marine and Coastal Access Act 2009.Should you wish to view our application in full, it is available to be viewed via the Marine Scotland Information website, on the below link:https://marine.gov.scot/data/marine-licence-application-eastern-green-link-2-egl2-hvdc-cables-and-cable-protection-peterhead.Should you have any questions in relation to the project, please do not hesitate to contact me (dav.s.lynch@sse.com). Representations to the Marine Scotland Licencing Operations Team in respect of our application may also be made by email to: MS.MarineLicensing@gov.scot by the 22nd August 2022, quoting reference: 00009943 and Scottish Hydro Electric Transmission Plc.Our project partners, National Grid Electricity Transmission have submitted an associated Marine Licence application to the Marine Management Organisation for the elements of the EGL2 project located within English waters, with further information available at the National Grid Website. (https://www.nationalgrid.com/electricity-transmission/network-and-infrastructure/segl2) -
Closure of Feedback Period
The feedback period for providing comments following our consultation events that were held in April 2022 has now closed. The project team would like to extend thanks to all members of the public who took the time to provide feedback on our proposals. All responses received will now be reviewed ahead of the next stage of the project.
Feedback Period Open
The project team would like to extend thanks to all members of the public and interested parties who took the time to come along to our public consultation events that were held at Peterhead Football Club on the 6th of April and to those that visited our virtual online consultation and submitted questions to the team via the live text chat function on the 7th of April. We hope you found the consultations informative and beneficial. If you were unable to join any of the events, all the content that was presented on our proposals can be found within the project documentation tab of this website. We encourage those with an interest to share their views and feedback on our proposals by completing a feedback form. The feedback period is open until 21st of April 2022. -
Public Consultation Events - April 2022
Scottish Hydro Electric Transmission (SHE Transmission) and National Grid Energy Transmission (NGET) invite you to come and share your views with us.SHE Transmission and NGET, the prospective applicants, hereby give notice of our Pre-Application Consultation (PAC) events to be undertaken in advance of the submission to Marine Scotland of an application for Marine Licences for the installation of the Eastern Green Link 2 Marine Scheme in Scottish waters. The Marine Scheme includes approximately 440km of subsea High Voltage Direct Current (HVDC) cables, fibre optic cable and associated cable protection from Mean High Water Springs at Sandford Bay, Peterhead to Fraisthorpe Sands, England. These events will focus on the elements of the Marine Scheme which are located in Scottish waters.SHE Transmission would like to extend an invitation to local members of the community and all interested parties to attend an exhibition to discuss our plans with the project team and let us know your thoughts on our proposals.A face to face public exhibition will take place on Wednesday 6th April 2022 at Peterhead Football Club between 2pm-7pm. This is an open door drop in session open to all members of the public and interested parties. A further two online consultation events will take place on Thursday 7th April between 1pm-3pm & 5-7pm.The online virtual consultation events have been designed to be fully interactive, allowing for presentation of key project information and plans, as well as providing an opportunity to ask questions about the project. Visitors will be able to engage directly with the project team via an instant message function,where they can ask any questions they might have about the project and share their feedback on the current proposals.The link to the virtual consultation room will be available nearer the time on the project overview page. -
February 2022 - Update
Preparation for ground investigation works has begun in the field north of the Peterhead substation development and along a route to the coastline, prior to the investigations themselves commencing Monday the 21st of February 2022. Work is expected to take approximately 6 weeks and will also see welfare cabins and vehicles occupied within the field. The purpose of this ground investigation is to establish the soil and rock conditions to support the design for the converter station and cable routes. Once this work is complete the cabins will be demobilised and removed from the site. Monitoring of ground water levels will continue over the coming weeks following the removal of the cabins. Please see the document download section of this website for a map detailing the area of the work. We do not anticipate this will cause disturbance to anyone within the local area, however please do not hesitate to contact the Community Liaison Manager (Dav Lynch - dav.s.lynch@sse.com ) if you have queries relating to these works. -
Feedback Period Closed
The feedback period for providing comments following our virtual consultation events that we held on the 26th of August has now closed. The project team would like to extend thanks to all members of the public who took the time to provide feedback on our proposals. All responses received will now be reviewed.
Virtual Consultation Feedback
The project team would like to extend thanks to all members of the public and interested parties who took the time to visit our virtual online consultation and submitted questions to the team via the live chat function on 26 August 2021. We hope you found the consultation informative and beneficial. If you were unable to join one of the events, all the content that was presented online can be found within the project documentation tab of this website. The feedback period on our proposals is open until 24 September 2021. -
Virtual Consultation Event - August 2021
Scottish and Southern Electricity Networks Transmission (SSEN Transmission), are holding a virtual consultation session to engage and share feedback on our proposals for the new convertor station site and provide further details on the Eastern HVDC link project. In addition, we will also be introducing our wider plans and works for the Peterhead area which are expected to be delivered over the coming years.The virtual consultation events have been designed to be as interactive as face to face events, allowing presentation of key project information and plans, as well as providing the opportunity to ask questions about the project. Visitors will be able to engage directly with the project team, via a live text chat function, where they can ask any questions they might have about the project and share their feedback on the current proposals.The virtual consultation exhibition details are as follows:Thursday 26th August 2021, between 13:00 – 15:00 and 17:00 – 19:00The link to the virtual consultation room will be available nearer the time on the project overview page. -
Feedback Period Closed
The feedback period for providing comments following our virtual consultation that we held on the 28th of October has now closed. The project team would like to extend thanks to all members of the public who took the time to provide feedback on our proposals. All responses received will now be reviewed.
Virtual Consultation Feedback
The project team would like to extend thanks to all members of the public and interested parties who took the time to visit our virtual online exhibition and submitted questions to the team via the live text chat function on the 28th of October 2020. We hope you found the exhibition informative and beneficial. The online virtual consultation room can still be accessed via a link on the project overview page of this website, and will remain open until the feedback period closes on the 6th of November 2020. -
Virtual Consultation
In lieu of being able to hold face to face public consultations in the local area, we are hosting a virtual consultation exhibition to provide greater detail about this project and to re-introduce our proposals to the local community.The virtual consultation event has been designed to be fully interactive, allowing for presentation of key project information and plans, as well as providing an opportunity to ask questions about the project.Visitors will be able to engage directly with the project team, via a live text chat function, where you can ask any questions you might have about the project and share your feedback on the current proposals.The interactive session will be hosted via a consultation portal, the link to which will be made available on the project overview page on this website on Tuesday 27th October.
Documents
Additional Information
-
How we use profits to fund investment
- Type:
- Date:
- 03 June 2026
- Size:
- 225.4 KB
This booklet sets out how we use our profits to fund investment in the electricity network, and how our revenues and returns are tightly regulated by the GB energy regulator Ofgem.
-
Apprentice & Trainee Careers
- Type:
- Date:
- 10 February 2026
- Size:
- 2.9 MB
This booklet sets out apprentice and trainee career opportunities at SSEN Transmission.
-
Biodiversity Net Gain
- Type:
- Date:
- 10 February 2026
- Size:
- 4.8 MB
This booklet explains our approach to protecting and restoring nature.
-
Community Benefit
- Type:
- Date:
- 10 February 2026
- Size:
- 4.8 MB
This booklet provides information on our approach to Community Benefit including Community Benefit Funding, which is funding available to communities close to new transmission infrastructure.
-
Delivering a positive environmental legacy
- Type:
- Date:
- 10 February 2026
- Size:
- 869.3 KB
This booklet sets out our commitments to delivering a positive environmental legacy.
-
Delivering legacy benefits through our projects
- Type:
- Date:
- 10 February 2026
- Size:
- 12.1 MB
This booklet sets out the long term benefits our projects will bring to the North of Scotland.
-
Early Careers
- Type:
- Date:
- 10 February 2026
- Size:
- 5.4 MB
This booklet sets out the different early career opportunities at SSEN Transmission including our graduate, apprenticeship, trainee and summer placement programmes.
-
Electric and Magnetic Fields (EMF)
- Type:
- Date:
- 10 February 2026
- Size:
- 914.1 KB
This booklet explains Electric and Magnetic Fields (EMFs), the latest research, and how we strictly follow all health and safety legislation and guidance when we develop, build and operate our infrastructure.
-
Housing Strategy
- Type:
- Date:
- 10 February 2026
- Size:
- 14.8 MB
This booklet sets out how we will house our workers on upcoming projects and how we are contributing to the development of 1000 affordable homes in the North of Scotland.
-
How Stakeholder feedback influences our proposals
- Type:
- Date:
- 10 February 2026
- Size:
- 4 MB
This booklet sets out how we strive to be accessible to all stakeholders and keep them informed and consulted through a project's lifecycle.
-
HVDC vs HVAC
- Type:
- Date:
- 10 February 2026
- Size:
- 2 MB
This booklet explains why we propose using underground DC cables for our offshore projects but not for onshore AC 400kV overhead lines.
-
Protecting Private Water Supplies
- Type:
- Date:
- 10 February 2026
- Size:
- 5.1 MB
This booklet explains how we protect private water supplies (PWS) during construction and investigation works.
-
Routeing Overhead Lines
- Type:
- Date:
- 10 February 2026
- Size:
- 5.3 MB
This booklet explains our approach to routeing overhead lines to minimise the impacts of new infrastructure on both the environment and on communities who live, work and spend time in these areas.
-
Section 37 Consent
- Type:
- Date:
- 10 February 2026
- Size:
- 4.9 MB
This booklet sets out our Sustainability Strategy and how it is embedded in how we deliver projects.
-
Student and graduate programmes
- Type:
- Date:
- 10 February 2026
- Size:
- 2.4 MB
-
Sustainability Strategy
- Type:
- Date:
- 10 February 2026
- Size:
- 1.5 MB
-
The challenges with undergrounding at 400kv
- Type:
- Date:
- 10 February 2026
- Size:
- 19.1 MB
This booklet provides insight into the technical, operational, environmental and economic challenges in laying underground cables.
-
Tower Crossing Considerations
- Type:
- Date:
- 10 February 2026
- Size:
- 19.5 MB
This booklet explains what we do when new transmission routes need to cross over existing assets.
-
Town and Country Planning
- Type:
- Date:
- 10 February 2026
- Size:
- 5.3 MB
This booklet explains the Town and Country Planning (Scotland) Act 1997, the main legislation we use to apply for consent to deliver our substation and converter station projects.
-
What to expect during the delivery of our projects
- Type:
- Date:
- 10 February 2026
- Size:
- 11.1 MB
This booklet sets out what to expect during the delivery of our projects including pre-consent activity, traffic management, construction, housing, and how we engage with communities.
-
Why are these projects needed and how has this need been assessed
- Type:
- Date:
- 10 February 2026
- Size:
- 3.5 MB
This booklet outlines the policies and targets driving the need for new clean power and the transmission network required to enable it.
-
Why our projects require both onshore and offshore solutions
- Type:
- Date:
- 10 February 2026
- Size:
- 2.3 MB
This booklet sets out that to successfully deliver the Government’s ambition of 50GW of offshore wind by 2030, we require a combination of both new onshore and new offshore electricity transmission network.
-
Working with landowners and occupiers
- Type:
- Date:
- 10 February 2026
- Size:
- 8.9 MB
This booklet sets out to landowners and occupiers why we are asking them to work with us and make them aware of the processes we are required to follow as the licenced transmission operator in the north of Scotland.
-
Eastern Green Link 2 - Consultation Booklet - April 2022
- Type:
- Date:
- 18 September 2022
- Size:
- 3.4 MB
This document provides information to our stakeholders about the project and was provided during our consultation in April 2022.
-
Eastern HVDC - Consultation Booklet August 2021
- Type:
- Date:
- 18 September 2022
- Size:
- 2.1 MB
This document provides information to our stakeholders about the project and was provided during our consultation in August 2021.
-
Eastern HVDC - PAC Report
- Type:
- Date:
- 18 September 2022
- Size:
- 3.1 MB
This document provides information to our stakeholders about the project.
-
Eastern HVDC Ground investigation map
- Type:
- Date:
- 18 September 2022
- Size:
- 81.8 KB
This map provides information to our stakeholders about the ground investigations within the project.
-
Eastern HVDC link - Consultation Booklet - October 2020
- Type:
- Date:
- 18 September 2022
- Size:
- 2.1 MB
This document provides information to our stakeholders about the project and was provided during our consultation in October 2020.
Newsletters
-
EGL2 Newsletter March 2025
- Type:
- Date:
- 01 March 2025
- Size:
- 301.2 KB
This newsletter from March 2025 provides project updates, key dates and information on planned activities in the area.
-
EGL2 Newsletter October 2024
- Type:
- Date:
- 01 October 2024
- Size:
- 1.8 MB
This newsletter from October 2024 provides project updates, key dates and information on planned activities in the area.
-
EGL2 Newsletter April 2024
- Type:
- Date:
- 01 April 2024
- Size:
- 1.1 MB
This newsletter from April 2024 provides project updates, key dates and information on planned activities in the area.
FAQs
Who we are
-
SSEN Transmission operates, maintains, and improves the high voltage electricity transmission network in the north of Scotland.
Our network extends over a quarter of the UK’s land mass and some of its most challenging terrain. This area has a lot of renewable energy potential such as wind, solar, hydro and marine power.
We work with the National Grid Electricity Systems Operator so that electricity generated in the Highlands and Islands can reach homes and businesses across Britain.
-
SSEN Transmission is owned 75% by SSE plc and 25% by Ontario Teachers’ Pension Plan.
-
We are closely regulated by the independent energy regulator, Ofgem, for the work we do constructing, operating, and maintaining the transmission network in the north of Scotland.
The costs of constructing, operating, and maintaining the transmission network are shared between all those using the transmission system, including generation developers and electricity consumers.
Ofgem set how much money we invest, what return we make on this investment and how these costs are recovered from users of the electricity transmission system.
About the Pathway to 2030 projects
-
What is Pathway to 2030
The Pathway to 2030 is a series of projects to increase capacity of the transmission network in northern Scotland. It is part of a national effort to upgrade power lines across Great Britain to connect and transport renewable electricity, especially from offshore wind farms.These projects contribute towards meeting climate goals and renewable targets, ensuring energy security and supporting Scottish and UK Government targets for a just transition to a net zero future.
Why is it needed?
- Addressing Climate Change: The UK and Scottish Government have ambitious targets to combat climate change and guarantee a secure and reliable supply of energy. The UK is aiming for 50 gigawatts (GW)* of offshore wind-generated electricity by 2030. Our Pathway to 2030 projects have been identified as required to help achieve such targets by delivering the vital infrastructure required.
*For background, A GW is a unit of measurement of electrical power. It is equal to one billion watts. - Promoting Energy Independence: In 2022, the UK Government set out a strategy to reduce dependence on volatile global gas markets, moving to local, sustainable electricity sources instead. Establishing the necessary infrastructure for this is critical.
- Planning for future need: Experts with the National Grid Electricity System Operator carry out extensive analysis and research to predict the UK’s future energy needs. This information is then carefully considered to guide infrastructure upgrade decisions.
- Approved by Ofgem: Britain's independent energy regulator, Ofgem, granted approval for these projects in December 2022 as part of its strategy for accelerated network upgrades.
More information explaining the need for these projects can be found here, for more information on the Government policies that underpin this need and how the need has been identified and assessed please read our information leaflet.
- Addressing Climate Change: The UK and Scottish Government have ambitious targets to combat climate change and guarantee a secure and reliable supply of energy. The UK is aiming for 50 gigawatts (GW)* of offshore wind-generated electricity by 2030. Our Pathway to 2030 projects have been identified as required to help achieve such targets by delivering the vital infrastructure required.
-
To deliver energy security and net zero, further additional investment in new low carbon electricity generation and the enabling electricity transmission network infrastructure will be required across Great Britian, including the north of Scotland.
In March 2024, the independent National Energy System Operator’s (NESO) published its ‘Beyond 2030’ report, which confirmed the need for several new, replacement and upgraded transmission infrastructure projects in the north of Scotland. In December 2024, Ofgem approved the next phase of regulatory funding to take these projects through the development phase.
These additional investments will soon be subject to extensive public consultation and engagement to help inform their development, with early consultation and engagement expected to take place within 2025. Additional regional investments are also likely to be required to deliver the UK Government's Clean Power 2030 ambition. Further details on these will be communicated once the need and scope for these investments has been established.
More details on what this means for projects in the north of Scotland are included on our website here
-
SSEN Transmission is responsible for where and how the high voltage transmission network operates in the north of Scotland. However, we don't determine where energy is generated – nor where it is needed.
We have a legal obligation to provide electricity generators with access to our network, so that the electricity they generate can be transported across GB to meet the energy demand of homes and businesses.
The north of Scotland is rich in renewable energy, especially wind, water, and marine sources meaning this region is vital for the UK and Scotland's climate goals. Our area covers a quarter of the UK landmass and will be crucial in the move towards a low carbon future.
Our approach to routeing and public consultation
-
Our approach to optioneering (routes for overhead lines or sites for substations) is underpinned by our statutory obligations, as set out in the Electricity Act Schedule 9, to ‘develop and maintain an efficient, coordinated and economical electricity transmission system’. Having regard to the “desirability of preserving the natural beauty, of conserving flora, fauna and geological and physiographical features of special interest and protecting sites, buildings and objects of architectural, historic or archaeological interest; and do what we reasonably can to mitigate any effect which the proposals would have on the natural beauty of the countryside or on any such flora, fauna, features, sites buildings or objects’.
As a result, our optioneering process seeks to balance technical and cost considerations with environmental considerations. To select a proposed option which is economically viable, technically feasible, minimises impacts on important resources or features of the environment and reduces disturbance to those living in it, working in it, visiting it or using it for recreational purposes. The option must also be capable of being granted consent by either the Scottish Government (in the case of overhead line projects) or local planning authorities (in the case of substation projects).
To do this we consider specific topic areas within the environmental, technical and cost categories and assess each in terms of the potential for the option to be constrained. We allocate a Red/Amber/Green (RAG) rating to each topic to highlight where potential issues may be present and use this to help compare the different options. The appraisal seeks to compare the wider implications of each option on those topics (both individually and combined) and reach a reasoned conclusion, on balance across all topics, as to the ‘preferred option’ to take forward.
Any weighting of certain criteria as being of more importance than other criteria would depend on project specific considerations. For example, if a particular technical or environmental constraint has been identified as a priority consideration through stakeholder engagement (or engineering specification) and is unable to be overcome, this will inevitably carry greater weight in the comparison of options which may otherwise contain constraint that can be easily designed out or mitigated.
We follow this comparative approach through stages of refinement. For overhead lines this starts with wider corridors and progress to assessment of routes and alignments. For substations, we start with a long list of sites, which is refined through further assessment to identify one site. Consultation with stakeholders is essential throughout this process so that their views can be taken account of in our considerations prior to progressing to the next stage.
The culmination of this process identifies a ‘proposed option’ that will be taken forward to detailed design, environmental assessment and consent applications.
-
Consultations began at an early stage of project development, long before any decisions on power line routes or substation locations were made.
Tower locations were not shown because this information is not yet known. Early feedback is crucial, so potential route options were discussed with key stakeholders.
Our goal at this initial stage is to select routes approximately 1km wide that minimise physical or environmental obstacles and disturbances, while also being practical and cost-effective. We presented these routes to the public, statutory and non-statutory organisations to explain our current assessment and thoughts and listen to feedback.
Stakeholder feedback guides our projects from the start. All feedback is considered, and where possible and feasible, adjustments can be made, in which case we will ensure any changes are presented at future consultation events.
-
Feedback importance: SSEN Transmission values feedback from stakeholders and local communities and considers it throughout the project development process.
Whilst community feedback is not our only consideration, we wish to develop all projects sensitively and to reduce impacts on communities as much as possible. Community feedback provides an essential insight into local issues that helps to refine the design, routes, and substation locations.
What we can do: Following consideration of all feedback, we consider what opportunities there are to modify our project's design, route, and substation locations.
What we can't do: We don't decide on the overall need for the Pathway to 2030 projects; that's National Energy System Operator and Ofgem's role. Therefore, we can't consult on the core necessity of these 2030 plans.
-
In November 2020, SSE became the first company to produce a Just Transition Strategy, introducing 20 key principles to ensure fairness as we move away from carbon-heavy activities and embrace climate-friendly changes.
The Pathway to 2030 projects align with these principles, promoting job opportunities, local suppliers, and preserving cultural heritage. Early in project development, SSEN Transmission made sure to engage with communities for feedback and insight.
To read more about our principals click here
-
There will be no further consultation prior to the submission of the consent applications for the proposed new 400kV OHL’s. We have undertaken public consultations at the corridor, route and alignment stages of the project development. This includes completing two best practice consultation events as part of the pre-application process for Section 37 applications, please see Electricity Act 1989 - sections 36 and 37: applications guidance - gov.scot.
In March 2025 we concluded the alignment stage consultation for the proposed new 400kV overhead line (OHL) projects, where we presented the Proposed Alignments we will submit as part of a Section 37 applications for consent. The Proposed Alignments have been refined from the various options that we have investigated during the development of the project.
Our alignment proposals presented at these consultations were the result of extensive engagement and project design. We plan to submit our Section 37 applications to the Scottish Government’s Energy Consents Unit (ECU) in Spring 2025. Once an application for consent has been submitted, there will be an opportunity for the public to make formal representations to the ECU before it takes a decision.
For our substation proposals, most consultations concluded in May and June 2024, with applications for full planning permission, under the Town and Country Planning (Scotland) Act 1997, now submitted to the relevant local authorities for consideration. In accordance with the Town and Country Planning (Environmental Impact Assessment) (Scotland) Regulations 2017, applications were accompanied by an Environmental Impact Assessment (EIA) Reports, details of which can be viewed on the relevant project web pages.
Environmental considerations
-
Environmental Impact Assessment Reports (EIARs) for the Pathway to 2030 projects will be prepared for the chosen options, in line with the relevant legislation.
Once completed, the EIARs will be accessible online via our project website, the Scottish Government’s Energy Consents Unit applications portal, and relevant Local Authority planning portals (depending on the consent being applied for).
Hard copies will also be available to view locally and these will be advertised at the time.
-
When developing proposed project alignments, we seek to minimise impacts on woodlands and forestry where possible, however given the numerous environmental and technical constraints, some impacts are unavoidable.
Where the proposed alignment passes through woodland and forestry, an Operational Corridor is identified and trees are removed within the Operational Corridor to ensure the safe operation of the overhead line. Detailed forestry assessments are carried out as part of the Environmental Impact Assessment (EIA) reports that are submitted with Section 37 consent applications to Scottish Ministers, and these assessments are used to inform the Operational Corridor design through woodland.
The Operational Corridor width for a 400kV overhead line will typically be 45m either side of the centre line of the overhead line, but this width may vary depending on the type of woodland/forestry and local topography. In accordance with the Scottish Government’s Control of Woodland Removal Policy, we are committed to providing appropriate compensatory planting for any net loss of woodland.
-
We prioritise environmental protection in our infrastructure projects, strictly adhering to environmental policies and regulations.
We follow a mitigation hierarchy strategy of “avoid, minimise, mitigate and restore” to safeguard local, national and international designated environmentally protected areas.
As the first developer to consult upon and implement an award winning approach to deliver Biodiversity Net Gain (BNG) on all new sites, we’re committed to delivering a “greener grid”, focusing on habitat restoration and creating biodiversity growth as we invest in our network. We are committed to delivering 10% Biodiversity Net Gain on all sites gaining consent going forward. This ensures that we don’t just restore our natural habitats but actively improve them for the benefit of local communities, wildlife, flora and fauna.
During our assessments, comprehensive surveys identify potentially affected wildlife, guiding mitigation efforts. For example, bird surveys are ongoing, with winter surveys planned for 2023/24.
We also assess habitats and other species along our routes. Our consultation process to date has highlighted sensitive areas, and we continue to work with environmental experts and seek community feedback to refine our approach.
-
Scotland has protected areas that represent the very best of our landscapes, plants and animals, rocks, fossils, landforms and cultural heritage. These protected areas are also known as designated sites. The purpose of the designated site is to ensure that the features of special interest, for which the site is designated, remain in good health for all to enjoy, now and in the future.
Designated sites are usually identified by a site boundary and a definition explaining why the site has been designated. Designated sites have different levels of protection, some are protected by international and national legislation or through national and local planning policy. Some sites can have more than one designation e.g. A Site of Special Scientific Interest (SSSI) may also be designated as a Special Protection Area (SPA).
Statutory Authorities such as Nature Scot, Historic Environment Scotland (HES) and Local Authorities can identify and designate a site for its special feature(s).
Examples of designated sites are:
Dalroy and Clava Landforms SSSI - This SSSI is renowned for its “high-level shell beds”. These fossil rich marine clays occur at around 150m above present sea-level and were first recorded in the 1800’s. Clava is also noted as a particularly fine example of “flow tills”. The presence and composition of the till provides a key to understanding the location of glaciers during the last ice age as well as the direction in which they moved. SiteLink - Dalroy and Clava Landforms SSSI
Crathes Castle Garden & Designed Landscape (GDL) - Most famous for its outstanding gardens which were started in the early 17th century and were admired by Gertrude Jekyll in the 1930s. The wider 18th-century designed landscape of parkland and woodland makes an impressive setting for the A-listed castle. CRATHES CASTLE (GDL00119)
-
When planning our overhead line and substation projects, we thoroughly consider environmental, cultural, and built heritage factors in potential locations.
We make use of national archives and data sources as well as gathering data from Local Authorities and detailed site surveys to identify and assess the potential impact on archaeological sites, listed buildings, and other heritage assets.
Environmental Impact Assessment Reports (EIARs) detail these findings and recommend ways to lessen any potential adverse effects. We've received feedback about sensitive archaeological and cultural sites from a range of stakeholders, including local heritage and archaeological groups, all of which our environmental experts have considered.
-
We are committed to ensuring that all our access to land is subject to appropriate levels of biosecurity protocol in line with the relevant industry or Government biosecurity guidance, and to ensure that both practical and reasonable measures are adopted.
All of our contractors have been instructed to implement stringent biosecurity measures on taking access to properties for survey and investigation works and then for construction works, as and when our projects reach this stage, to minimise the risk of contamination and the spread of animal and plant diseases, parasites and non-native species. The guidance we provide contractors reflects a two-stage process.
- Stage 1:
- Clean footwear, vehicles, plant, tools, and temporary access materials to remove soil and debris with brush and water.
- Use facilities provided by landowners for cleaning footwear and machinery.
Stage 2:
- Clean footwear and machinery with suitable disinfectant if land is affected by disease or high risk of contamination.
- Clean between different areas within a property if requested by the landowner
Additional measures include soil sampling and testing for Potato Cyst Nematode and Clubroot where there are potato crops, transporting machinery via low-loader for thorough wash-down between properties and frequent internal team meetings to review and update biosecurity measures.
It is important that landowners take any opportunity to engage with our contractors and land managers on biosecurity concerns and inform them of any known disease on the property to allow for appropriate mitigation measures.
- Stage 1:
-
When planning routes for overhead lines and substations, we consider visual impacts and how this may affect the local scenery, visitor experience and communities.
For each project we develop, we conduct a Landscape and Visual Impact Assessment. This is one element of the Environmental Impact Assessment Reports that forms part of our application to the local authorities and Scottish Government. In this assessment, we consider visual impact from centres of population, popular spots, like walking paths and tourist sites, and where possible reduce any potential negative visual impacts.
-
When developing overhead lines and substations, we focus on having a minimal noise impact. Detailed noise assessments are conducted as part of our Environmental Impact Assessment, and include current noise levels, potential new noise as a result of our infrastructure, and mitigation measures where required, to ensure noise is within acceptable levels.
-
The impact of noise on people is heavily dependent on the nature of the noise, time of day and the noise receptor. As such, there is no single decibel level that can be applied. We engage with the relevant Local Authority’s Town and Country Planning Team to agree practical noise limits to ensure that there is no adverse impact on nearby residential properties.
Specifically, noise impacts for overhead lines are assessed having regard to external and internal noise impacts. The impact of external noise is determined by comparing the noise from the overhead line to the existing background noise levels combined with the noise sensitivity of the receptor. This is a complex assessment but dependent on context. An increase at the noise receptor of 10dB is likely to indicate a significant adverse impact and an increase of 5dB is likely to indicate an adverse impact. Internal noise resulting from external noise is calculated assuming a partially open window, that being in accordance with the guidance in BS 8233 (Guidance on sound insulation and noise reduction for buildings)
Construction noise has been assessed using BS 5228-1 (Code of practice for noise and vibration control on construction and open sites – Noise).
A detailed description of how noise impacts have been assessed is included in our submissions for consent under Section 37 of the Electricity Act 1989 to Scottish Ministers.
-
An aviation impact assessment, including engagement with key stakeholders, has determined there is no identified requirement for flashing lights on top of the towers.
In the UK, the lighting of obstacles is guided by two main documents:
- The Air Navigation Order (ANO) Article 222;
- Civil Aviation Publication (CAP) 168
CAP 168: Licensing of Aerodromes | UK Civil Aviation Authority
-
In our early project development, we consider flood risks and drainage. We aim to avoid areas prone to flooding and conduct assessments when necessary.
Our team includes a variety of water and flooding experts who help design systems to manage water flow around our sites. Before construction, we will have a plan in place to protect both surface and groundwater and reduce potential impacts.
-
The Pathway to 2030 and clean power depends upon a safe, reliable and resilient electricity transmission system that connects homes and businesses with renewable generators. The north of Scotland, with its vast renewable energy resource, plays a critical role in the energy transition. Our ambition is for our network to have the capability to meet 20% of Great Britain’s demand for clean power by 2030. This means investing to grow the network, while working with our stakeholders to ensure the transition is fair and sustainable. We recognise that the unprecedented pace and scale of network expansion will have impacts on communities, on the natural environment, and on the climate.
We are committed to leaving a positive legacy, for people, the environment, the economy, and our wider world.
Our Sustainability Strategy sets out our priorities for a transition that is fair and sustainable. Developed through an inclusive and evidence-based process, this Strategy informs our decision making and action up to and including 2030.
In 2024/25 alone, our existing network transmitted 17.1 TWh of renewable electricity, which displaced a total of 3.5 million tonnes of CO2e in one year. This is with 11GW of renewable generation capacity connected to our network. We estimate that our reinforcements out to 2030 will allow the connection of at least another 11GW, with corresponding increases to the amount of renewable electricity transmitted and associated carbon emissions displaced. In contrast, we estimate the total embodied carbon from our Pathway to 2030 construction programme to be around 2 million tonnes of CO2e. On this narrow basis, the carbon payback period for the network infrastructure would be less than a year. Read more here.
Community and landowner considerations
-
Following the publication of UK Government guidance, every transmission project with new substations or overhead line will provide a community benefit fund. Funding will consist of a strategic fund available to all communities across our network area and local funds for communities close to new infrastructure. If our planned projects go ahead, this funding is worth in excess of £100m to communities over the coming years.
Community Benefit Funds enable us to give back to the communities hosting our transmission network and to help fund projects that can leave a lasting, positive legacy in those areas.
Additionally, our projects will boost the economy, supporting local jobs and businesses. Independent studies show our Pathway to 2030 programme could contribute over £6bn to the UK's economy, support 20,000 jobs across the UK, and benefit Scotland by around £2.5bn, supporting 9,000 jobs.
-
The UK Government has confirmed that households living close to eligible new or significantly upgraded electricity transmission infrastructure will receive discounts on their electricity bills. The scheme is intended to ensure that communities hosting vital network infrastructure directly benefit from investment in the electricity grid.
Under the scheme, households located within 500 metres of eligible transmission infrastructure are expected to receive discounts of up to £2,500 over 10 years.
Pending final confirmation, the UK Government has announced the first projects expected to fall within the scope of the scheme, with payments anticipated to begin from 2027 for eligible households - once projects have secured the necessary consents and main construction works have started. Most eligible households are expected to receive the discount automatically through their electricity supplier.
More information about the scheme is available on the UK Government website: Households living near new pylons to save thousands on bills.
-
We value engaging with local communities and residents to gather feedback on our plans. While our projects can cause some uncertainty, we aim to be transparent and start these discussions early. We always welcome and encourage suggestions on improving our approach and work collaboratively with communities as our projects evolve.
-
We would like to reassure you that we develop, build and operate our infrastructure to meet all health and safety legislation, and guidance set by relevant bodies - including the UK Government, Scottish Government, the Health and Safety Executive and the industry regulator, Ofgem – including guidance associated with EMF exposure.
In respect of EMFs, we strictly follow the guidance set by the UK Government, which is informed by international guidance.
As well as setting exposure limits that protect against known, established effects of EMFs; the UK Government’s guidance includes precautionary measures to protect against possible effects below the exposure limits.
The UK Health Security Agency and Department of Health have a remit to review new research in this area and ensure that current guidelines and policies are reflective of that research.
There have been over four decades of research looking into whether EMFs associated with electricity transmission projects can cause health effects and there are no established effects below the exposure limits. When we design our overhead lines, substations and cables we do so to ensure they will not exceed those exposure limits, even when operating at 100% capacity, and we also ensure that precautionary measures are also applied to the design where required.
The guidance we follow, which remains subject to ongoing review as required, ensures that safety measures will be applied to our 400kV infrastructure protecting us all against EMF exposure, and keeping our network safe for the public.
More information is available in our EMF Leaflet.
-
We understand that there are concerns about the potential impact of our proposed developments on properties within the vicinity of SSEN Transmission’s proposed overhead line alignments and substations sites.
Throughout the development of projects SSEN Transmission has looked to mitigate impacts on residential properties as far as possible, and these impacts will be assessed as part of the Environmental Impact Assessments that accompany our applications for consent. Extensive surveys have been carried out at identified receptors, including selected residential properties so that we are able to model potential impacts on the wider area.
Concerns in relation to impacts on property are being noted by our team. However, as a regulated business, SSEN Transmission is obliged to follow a statutory legal framework under the Electricity Act 1989 and Land Compensation Act 1961. If you are entitled to compensation under the legal framework we will assess any claim on a case-by-case basis under the direction of this legal framework. If this is the case, we will recommend that you engage a professional adviser and SSEN Transmission will generally meet reasonably incurred professional fees in these circumstances. However, for the avoidance of doubt, we should advise that SSEN Transmission will not meet fees incurred in objecting to our proposed developments.
-
We aim to work cooperatively with stakeholders, including landowners, during the development of the projects.
While we might need to acquire land for substations or rights for overhead lines, our preference is to reach voluntary agreements. Using statutory powers is an absolute last resort.
If we do use them, we'll ensure fair compensation based on established industry standards.
-
A Notice of Intended Entry is a formal notice given to landowners and occupiers, based on the Electricity Act 1989.
It grants us and our contractors the right to enter land after 14 days to conduct surveys related to our project, including environmental assessments, engineering walkovers, and drone surveys.
It's essential to note that these letters are not linked to compulsory land purchase. If there are any concerns, recipients can contact us using the information provided in the letter.
-
We have statutory obligations to maintain a minimum ground clearance between conductors and other objects which are included in Regulation 17 of ESQCR 2002. Further guidance of standard clearances for the industry are set out in Energy Networks Association Technical Specification (ENA) TS 43-8.
The minimum clearance from the nearest line conductor to any object which is ordinarily accessible (including permanently mounted ladders and access platforms) or to any surface of a building is 5.3m. This includes temporary structures such as mobile and construction equipment. We provide guidance and information to third parties who intend to develop land near our electricity transmission assets, this includes overhead lines, pylons, substations, and underground cables. Find out more here.
Cost and engineering considerations
-
The required technology for the new 400kV overhead lines which form part of the Pathway to 2030 have been determined to be a new double circuit 400kV HVAC (High Voltage Alternating Current) overhead line.
The overhead line would consist of steel lattice towers with an average height of approx. 57m which would support six conductor bundles on six cross arms and an earth wire between the peaks for lightning protection. The average distance between towers is expected to be 338m. Tower height and the distance between them will vary dependent on several factors such as altitude, climatic conditions and topography.
This is similar to our Beauly—Denny line, where 80% of its 600-plus towers are below 57m, ranging from 42m to 65m in height.
-
The cost of improving the electricity network is covered by GB electricity consumers. It's to balance this cost with environmental, technical, and societal factors.
In April 2025, the Institution of Engineering and Technology published independent research undertaken to determine the difference in cost between different technology options for electricity transmission infrastructure, comparing the typical cost of overhead lines, underground and subsea cables. The study found that, typically:
- Undergroundcables cost around 4.5x more than comparable overhead lines; and
- Subsea cables cost up to 11x more than comparable overhead lines.
We conduct a Cost Benefit Analysis for our projects, but the cheapest options aren't always chosen. Factors like minimising environmental impact or ensuring technical viability also play an important part in this.
SSEN Transmission's return on investment is determined by Ofgem's regulations, no matter what the technology used.
-
In their assessment of the upgrades required to the GB Transmission Network to meet the UK Government’s 50GW of offshore wind 2030 target, National Electricity Operator assessed a number of potential solutions comprising both onshore and offshore schemes. Their Pathway to 2030 Holistic Network Design (HND), which was assessed and recommended as a single integrated GB wide network plan, concluded that a combination of both onshore and offshore schemes is required to transport the volumes of generation necessary to meet 2030 targets to key centres of demand across the country.
Overhead lines can carry roughly three times more power than subsea cables, making them more efficient and cost effective for energy bill payers.
These onshore reinforcements will also strengthen network reliability and security of supply for homes and businesses across the north of Scotland. -
Where a line exists, it doesn’t necessarily mean that it would be appropriate to build a new one next to it, there are many considerations as to why this may not be possible.
Sometimes, there is no space for new infrastructure due to existing constraints, including proximity to homes. However, in some areas, it is possible to place new lines near the old ones.
These aspects are considered in the optioneering phases of our projects for which we also seek stakeholder views.
-
The environmental, technical, and operational constraints associated with undergrounding at extra high voltages, particularly 400kV, make the option extremely challenging to deliver in many areas of Scotland.
Some of the challenges that contribute to this position:
- Technical Limitations: No underground cables for these high voltages (275kV or 400kV) currently exist in our area. Underground cables need specific ground conditions and present challenges in maintenance and power restoration, especially if faults occur.
- Environmental Impact: Undergrounding can have lasting environmental effects, for example impacts on habitats and hydrology, and the area required for laying cables needs to be clear from significant constructions or vegetation for easy access during construction and repairs.
- Terrain Concerns: The region's terrain often has slopes that are difficult to install and finding a suitable route for underground cables without challenges is extremely difficult.
- Infrastructure Needs: For underground cables longer than 1-2km, additional substation infrastructure would be needed, enlarging the project's footprint.
- Operational needs: Restoring power in the event of a cable fault can take significantly longer than for an overhead line. Faults on overhead electricity lines can typically take a few hours to a few days to repair and are generally easy to locate. Underground cable faults often require extensive works, specialist resource, tools and equipment to locate the fault, followed by significant civils work to expose the damage, replace the damaged section and then it can take up to a month to carry out the repairs. This presents significant risks to security of supply and network reliability. It also impacts on our ability to meet our licence obligations of maintaining an efficient transmission network.
- Cost: Underground cables at 400kV are estimated to be between 5 and 10 times more expensive than overhead lines, and since these costs are reflected in consumer bills, it's a factor that needs to be considered.
Even if technically feasible, undergrounding over a significant length of or the entirety of a project would be unreasonable as it would be contrary to our licence obligations to be economic and efficient in respect of additional costs to the end consumer and also have additional risk to the electricity transmission network in the event of cable failure and consequent outages.
Given these constraints and our responsibility for an economical and efficient transmission network, overhead lines are our main choice for the onshore ASTI projects. Where there is a clear evidence base to justify undergrounding, this will be carefully considered.
- Technical Limitations: No underground cables for these high voltages (275kV or 400kV) currently exist in our area. Underground cables need specific ground conditions and present challenges in maintenance and power restoration, especially if faults occur.
-
The choice between underground cables and overhead lines is based on the technology used and the power requirements:
- Technology Type: The Western Isles connection uses High Voltage Direct Current (HVDC) technology, suitable for connecting the Western Isles' power generation. This HVDC technology has low electrical losses and provides better control over the island's network conditions. It requires only two cables for a 1.8GW rating.
- Power Requirements: The Pathway to 2030 projects, including routes like Spittal-Beauly, requires a 400kV onshore overhead line to transport much more power, 5GW. This setup permits the connection of much more generation. Achieving this rating with HVDC would necessitate at least three subsea cables.
- Feasibility: Using underground cables for such high ratings isn't viable technically, economically, or environmentally due to the sheer number of cables needed.
While underground cables work for the Western Isles connection, they aren't practical for the larger Pathway to 2030 projects.
- Technology Type: The Western Isles connection uses High Voltage Direct Current (HVDC) technology, suitable for connecting the Western Isles' power generation. This HVDC technology has low electrical losses and provides better control over the island's network conditions. It requires only two cables for a 1.8GW rating.
-
While the T-Pylon has been developed for use in England and Wales, it is not currently deemed suitable for our projects in the north of Scotland for several reasons:
- Weather Impact: Our region experiences more severe weather conditions, with increased impact from wind and ice. Using T-Pylons would mean shorter spans between structures, resulting in more structures, thus increasing the visual impact, land occupation, and construction traffic.
- Material Lifespan: The composite material used for T-Pylon's diamond insulators might only last about 20 years. In contrast, the glass insulators on our lattice steel towers have a life expectancy of 40-50 years.
- Transport & Delivery: The T-Pylon's large steel sections need a large number of low-loaders for delivery, significantly affecting local traffic. Their design could also force new lines to be closer to major roads, impacting our ability to route away from properties. Lattice steel towers are more compact for transport, minimising traffic disturbance.
- Design Flexibility: T-Pylons can only turn up to 30° angles, while our lattice steel towers can turn up to 90°. This flexibility helps us avoid communities, viewpoints, and environmentally crucial sites. The limited direction change of T-Pylons would hinder our ability to minimise line impact.
- Reliability & Repair: T-Pylons support an entire circuit on a single diamond so in the unlikely event of a failure the entire circuit could be lost, whereas lattice steel pylons use a double circuit. Repairs would take significantly longer, delaying power restoration.
Given these factors, we've determined that T-Pylons aren't currently suitable for our projects, as they might result in greater community and environmental impact and increased construction traffic.
- Weather Impact: Our region experiences more severe weather conditions, with increased impact from wind and ice. Using T-Pylons would mean shorter spans between structures, resulting in more structures, thus increasing the visual impact, land occupation, and construction traffic.
-
The conductor types being utilised for the new overhead lines proposed between Spittal - Beauly, Beauly – Peterhead and Kintore – Tealing are conventional AAAC (All Aluminium Alloy Conductors). This technology is used extensively on our existing network and has a proven record of safe and reliable operation. A conductor selection exercise was carried out considering electrical performance, EMF (Electric and Magnetic Fields) and noise impacts, mechanical performance, reliability and cost. The key advantages over the other conductors considered was proven reliability, the ability to reduce conductor noise and reduce electrical losses.
-
High tension Low Sag (HTLS) conductors are particularly well suited for re-conductoring projects, where existing transmission lines are upgraded by replacing the current conductors with newer, higher capacity alternatives. These projects do not require new towers or structures, making HLTS conductors a practical option due to their reduced sag under load.
Despite these advantages, HTLS conductors also present several significant limitations. Their unique composition introduces challenges in construction, operation and maintenance. These challenges become more pronounced in areas with undulating or uneven terrain; conditions that are present along large sections of our proposed new 400kv overhead lines. Such topography places additional mechanical stress on the conductors, which HTLS types are less capable of handling compared to conventional conductors.
If these challenges are not carefully managed, they can lead to reduced asset lifespans and an increased risk of unplanned outages. In addition, addressing these issues typically extends installation timelines.
Another important consideration is that HTLS conductors tend to exhibit higher electrical losses than conventional conductors (AAACs) – particularly when operating near capacity. These losses reduce the amount of electricity delivered to end users, with the cost of this inefficiency ultimately reflected in consumer energy bills.
Given these factors, HTLS conductors were not considered appropriate for our proposed Pathway to 2030 new overhead line projects but are being utilised for one of our related re-conductoring projects.
-
Limits of Deviation (LoD) comprise an area which defines the practical limits within which movement of the Overhead Line (OHL) towers, conductors and access tracks can be sited and construction can be undertaken within the terms of the Section 37 planning consent.
A vertical and horizontal LoD is typically applied to OHL projects. The vertical LoD relates to the addition of a further section of a tower. It also applies should the foundation design change or the location of the tower move to a higher elevation. Whilst the structure height won’t change these activities can result in the tower height increasing.
The horizontal LoD is a distance either side of the OHL and access tracks. This is typically 100 – 200 metres for OHLs and 50 metres for access tracks. However, the distance applied on either side can vary and be project specific.
LoDs are required to provide the flexibility needed during construction to adapt to unforeseen circumstances. This helps ensure that the consented project design can still be implemented even if unexpected engineering or environmental challenges arise.
An example of where a LoD may be utilised is where poor ground conditions are identified that may make the planned location of infrastructure impractical or less suitable. In such cases, the infrastructure position, initially shown in the plans, can be adjusted to a new location within the LoD, allowing construction to proceed. Any movement of infrastructure within the LoD must be agreed by the project team and assessed against the Environmental Impact Assessment Report submitted with the Section 37 application, before the change in location can proceed.
-
All project documents, which include maps of the suggested routes for the overhead lines can be found on our project webpages. Contact details of your local Community Liaison Manager are also available.
-
The 3D models used at our consultation events are created by combining several datasets with the project's proposed infrastructure integrated into them. The base model consists of a 5m resolution Digital Terrain Model (DTM), overlaid with high quality 25cm aerial imagery and 1:25,000 scale Ordnance Survey mapping. It also includes detailed road layouts. On top of this, our consultants incorporate building shapes and tree locations using specialised national data.
Terrain
The model uses OS Terrain 5 data from Ordnance Survey to shape the group surface in the model.This dataset is created from high-resolution scans and simplified to a 5-metre resolution for use in 3D modelling. You can find more information about the dataset here.
Aerial Imagery
The model uses 25cm resolution aerial photos, also from Ordnance Survey. These images are collected on a rolling three-year cycle and matched to Terrain 5 data for accuracy. You can find more information about the dataset here.
TreesTree locations come from the National Tree Map, supplied by Bluesky. It shows vegetation over 3 metres tall, classifying it as either conifer or broadleaf, and represents them using typical tree shapes. You can find more information about the dataset here.
Buildings
The model uses Level of Detail 2 building data from Bluesky. This includes accurately shaped pitched and flat roof shapes, based on high-resolution stereo aerial imagery. You can find more information about the dataset here.
All of this information is georeferenced using the British National Grid Projection. This ensures that every part of the model lines up correctly , making it accurate when integrating proposed infrastructure.
The 3D models are based on geospatial data at the time of modeling. While the data is regularly reviewed and updated, the model may not reflect recent changes, such as newly constructed buildings, recently removed structures or vegetation. changes (e.g. felled trees). This model is intended to give a general visual impression and may not capture every detail of the current environment.
View our dedicated project website for Eastern Green Link 2
The project is being jointly developed by Scottish and Southern Electricity Networks Transmission (SSENT) and National Grid Electricity Transmission (NGET).
Currently in the development phase, construction work is planned to commence in 2024 with the new connection due to be operational in 2029.
EGL2 will unlock the rich renewable energy capacity of Scotland and significantly increase the UK’s capacity to deliver clean energy for around two million homes in the UK.
The Eastern Green link 2 project now has new dedicated project website that can be accessed by clicking on the below link:
Community Engagement
Throughout the life of our projects, we aim to work positively with local communities and keep people informed about what we are doing. This is particularly important when we are developing a proposal and we want to understand what local people think about our plans.We endeavour to take the time to discuss proposals with local community councils, encourage engagement from the wider community and listen to the feedback we receive. We will do our best to answer any questions and address issues or concerns that are raised with us.
When our project progresses into construction, we will continue working closely with the local community to ensure that our work has as little impact on the lives of those living and working in the area and as many long term positive effects as possible.
How we’re embracing artificial intelligence (AI)
We intend to use AI to assist our experienced teams in the analysis of your feedback, so we can categorise key points raised more quickly. You can learn more about how we’re utilising AI on this dedicated web page.
Project Contacts
Gillian Doig | Community Liaison Manager
Telephone: 07879 288666
Address: Grampian House, 200 Dunkeld Road, Perth, PH1 3GH
Hugh Maclean | Land Manager
Telephone: 07467 388490
Address: Grampian House, 200 Dunkeld Road, Perth, PH1 3GH
Recite me
To make use of this function please click on the 3 'A's' button at the bottom left of the website.