Overview
About the Project
We are happy to share with our stakeholders that the Inveraray to Crossaig project is now energised with all associated works complete. These include;
- Construction of a new 275kV overhead line, initially operated at 132kV between Inveraray and Crossaig
- Extend the existing connection from Port Ann to the new overhead line
- Decommissioning/removal of the existing 132kV transmission line between Inveraray and Crossaig
This project has reinforced the existing transmission network between Inveraray and Crossaig to and will enable renewable energy projects to connect to the electricity network, and to ensure security of supply.
We want to thank stakeholders for working with us throughout the project development and construction phase.
Planning Consent
On 27th July 2018, we submitted a section 37 application to the Scottish Government for the Inveraray - Crossaig project, to install a 275kV overhead line (to be initially operated at 132kV) between Inveraray Substation and Crossaig Substation.
In Summer 2019, we welcomed the decision by Scottish Ministers to grant consent for the project - the full application can be viewed via the Energy Consents Unit website. Documentation relating to the application, such as the Enivronmental Impact Assesment (EIA) Report Non-Technical Summary and the Alignment Selection Consultation Document, can be downloaded from the Project Documents tab on this webpage. Interactive visualisations of the proposals are available online.
Access the Interactive EIA Report
Why is the Project Required?
Requests have been made to National Grid ESO by a number of wind farm developers for transmission grid connections in the Argyll and Kintyre area. We are responsible for providing the infrastructure required to connect the wind farms to the electricity network.
As the transmission licence holder in the north of Scotland, we have a duty under Section 9 of the Electricity Act 1989 to facilitate competition in the generation and supply of electricity. We have obligations to offer non-discriminatory terms for connection to the transmission system, both for new generation and for new sources of electricity demand.
The aim of the project is to enable renewable energy to connect to our transmission network. Under our Network Operators Licence this connection should be efficient, co-ordinated and economic, whilst having the least possible impact on the environment.
Community Engagement
Throughout the development of the Inveraray - Crossaig Project, we have endeavoured to ensure that local residents have been well informed of our plans and have held three sets of public consultation events. These were held to inform local residents and stakeholders of the project, and to seek review of our proposals, feedback, and any concerns as the final route was developed.
These events were held in October 2014, March 2016 and September 2017 across local areas such as Inveraray, Tarbert, Lochgilphead, Ardrishaig, Skipness and Carradale prior to submitting a section 37 application to the Scottish Government Energy Consents Unit in July 2018.
To view the consultation material from these events, please see the Project Documents tab on this webpage.
How we’re embracing artificial intelligence (AI)
We intend to use AI to assist our experienced teams in the analysis of your feedback, so we can categorise key points raised more quickly. You can learn more about how we’re utilising AI on this dedicated web page.
Project Updates
Project updates
Documents
-
CLG Minutes Inveraray to Crossaig November 2022.
- Type:
- Date:
- 28 November 2022
- Size:
- 174.3 KB
The minutes from Community Liaison Group meetings in Month Year.
-
Inveraray to Crossaig Newsletter Nov 22
- Type:
- Date:
- 28 November 2022
- Size:
- 681 KB
This material provides information to our stakeholders about the project and/or consultation events.
-
Inveraray crossaig advert.
- Type:
- Date:
- 16 September 2022
- Size:
- 1 MB
This material provides information to our stakeholders about the project and/or consultation events.
-
Argyl generation seminar slide pack.
- Type:
- Date:
- 16 September 2022
- Size:
- 1.7 MB
This material provides information to our stakeholders about the project and/or consultation events.
-
Argyll march 2016 advert.
- Type:
- Date:
- 16 September 2022
- Size:
- 80.1 KB
This material provides information to our stakeholders about the project and/or consultation events.
-
rgyll-region-sep-2017-update.
- Type:
- Date:
- 16 September 2022
- Size:
- 10.9 MB
This material provides information to our stakeholders about the project and/or consultation events.
-
CEP minutes February 2022.
- Type:
- Date:
- 16 September 2022
- Size:
- 178.4 KB
This material provides information to our stakeholders about the project and/or consultation events.
-
CLG minutes inveraray to Crossaig Dec 21.
- Type:
- Date:
- 16 September 2022
- Size:
- 185.3 KB
The minutes from Community Liaison Group meetings in December 2021
-
CLG minutes Inveraray-to-Crossaig January 2022.
- Type:
- Date:
- 16 September 2022
- Size:
- 185.1 KB
The minutes from Community Liaison Group meetings in Month Year.
-
CLG-minutes-Inveraray to Crossaig march 2022
- Type:
- Date:
- 16 September 2022
- Size:
- 186.4 KB
The minutes from Community Liaison Group meetings in March 2022
-
EIA report volume1 non technical summary.
- Type:
- Date:
- 16 September 2022
- Size:
- 9.6 MB
This Environmental Impact Assessment (and associated appendices/maps) is submitted as part of the Town and Country Planning or section 37 application.
-
Inveraray-cc-presentaton october 2019.
- Type:
- Date:
- 16 September 2022
- Size:
- 1.7 MB
This material provides information to our stakeholders about the project and/or consultation events.
-
Inveraray-Crossaig boards March 2016.
- Type:
- Date:
- 16 September 2022
- Size:
- 8.5 MB
This material provides information to our stakeholders about the project and/or consultation events.
-
Inveraray Crossaig brochure.
- Type:
- Date:
- 16 September 2022
- Size:
- 1.3 MB
This material provides information to our stakeholders about the project and/or consultation events.
-
Inveraray Port Ann transmission Link project update April 2020.
- Type:
- Date:
- 16 September 2022
- Size:
- 73.5 KB
This material provides information to our stakeholders about the project and/or consultation events.
-
Inveraray-to Crossaig-275-kv ohl report on consultation-alignment EIA scoping with figures.
- Type:
- Date:
- 16 September 2022
- Size:
- 5.9 MB
This Report on Consultation (and associated appendices/maps) documents the consultation process which has been undertaken for the project at corridor, routeing, alignment or substation site selection stage. It describes the key responses received and provides detail on the actions proposed in response to the issues raised.
-
Inveraray-to Crossaig environmental impact assessment scoping report revision 1.
- Type:
- Date:
- 16 September 2022
- Size:
- 1.1 MB
This Environmental Impact Assessment (and associated appendices/maps) is submitted as part of the Town and Country Planning or section 37 application.
-
Inveraray to Crossaig newsletter Feb 22.
- Type:
- Date:
- 16 September 2022
- Size:
- 1.8 MB
This material provides information to our stakeholders about the project and/or consultation events.
-
Inveraray to Crossaig reinforcement project newsletter
- Type:
- Date:
- 16 September 2022
- Size:
- 1.4 MB
This material provides information to our stakeholders about the project and/or consultation events.
-
Inverary Crossaig public notice Achnabreac
- Type:
- Date:
- 16 September 2022
- Size:
- 91.2 KB
This material provides information to our stakeholders about the project and/or consultation events.
-
Maki-Inveraray to Port Ann overhead line project update August 2020.
- Type:
- Date:
- 16 September 2022
- Size:
- 1 MB
This material provides information to our stakeholders about the project and/or consultation events.
-
mid Argyll clg-ssen bb presentation.
- Type:
- Date:
- 16 September 2022
- Size:
- 1.6 MB
This material provides information to our stakeholders about the project and/or consultation events.
-
Phase 2 CLG June minutes.
- Type:
- Date:
- 16 September 2022
- Size:
- 566.5 KB
The minutes from Community Liaison Group meetings
-
Phase 2 CLG October minutes.
- Type:
- Date:
- 16 September 2022
- Size:
- 497.2 KB
The minutes from Community Liaison Group meetings
-
Public notice temporary traffic lights Sept 2019.
- Type:
- Date:
- 16 September 2022
- Size:
- 572.5 KB
This material provides information to our stakeholders about the project and/or consultation events.
-
Tarbert Skipness c presentation 14th November 2019.
- Type:
- Date:
- 16 September 2022
- Size:
- 6.7 MB
This material provides information to our stakeholders about the project and/or consultation events.
FAQs
FAQ'S
Recite me
To make use of this function please click on the 3 'A's' button at the bottom left of the website.