Overview
Announcement of new public engagement events for Coachford Overhead Line design changes
In May, SSEN Transmission confirmed the removal of the proposed Coachford Substation from the Beauly-Peterhead 400kV overhead line (OHL) project scope which resulted in design changes for the overhead line in the Keith area (Alignment Sections 19 & 20). Following this announcement, we will be hosting two consultation events in Keith and Cairnie to share the amended design and proposed alignment for the OHL within this area, including details on how this was developed.
Please see below the details for our upcoming consultation events:
• Tuesday 24 June, 3–7pm - Cairnie Memorial Hall, Cairnie, AB54 4TQ
• Thursday 26 June, 3–7pm - Longmore Community Hall, Banff Road, Keith, AB55 5ET
Interested parties can attend these drop-in events to discuss the design changes and share final comments ahead of the consent application later in 2025. Feedback can be provided via forms available at the events, the online form on our project webpage through the link above or via email to bbnp@sse.com.
These events will conclude our project engagement for the consent application that we now aim to submit for the Proposed Development to the Energy Consents Unit of the Scottish Government in Early Autumn 2025. The application will be submitted in line with the requirements of section 37 of the Electricity Act 1989.
Further documents relating to our most recent and previous engagement events can be found in the documents tab of the Beauly-Peterhead 400kV overhead line (OHL) project page.
This video provides a 3D visualization of the proposed changes to the alignment in this specific area.
Coachford Substation Update
Following detailed ground investigation works which revealed technical challenges at the site, we will no longer be proceeding with the construction of the proposed substation at Coachford as part of the Beauly to Peterhead 400kV overhead line project. The results of our ground investigation work created an opportunity to reassess how, when and where the objectives of Coachford could be delivered, taking future development opportunities in the area into consideration.
Coachford was identified as one of four substations proposed along the line’s route, to support the transmission of renewable electricity as part of the project. Following the decision to remove the substation from the Beauly to Peterhead project, we will now start exploring alternative options to deliver the initial needs of Coachford - informed by community feedback and development insights gathered so far – at a new site.
What does this mean for the Beauly to Peterhead 400kV?
The Beauly to Peterhead 400kV overhead line project will now comprise three new substations rather than four, alongside the overhead line infrastructure, and still fully deliver the power transmission and grid connectivity requirements identified under our Pathway to 2030 projects.
We will shortly begin engaging with our stakeholders to explain these changes. The project team will be reaching out to local communities, landowners, and developers in the area to provide detailed updates regarding the revised scope of the project and what it means for them.
This will include localised public engagement events relating to the changes in this section in Keith and Cairnie, the details of which will be shared soon.
For further updates on the Overhead Line project, please visit the project webpage here where you can also register for project updates.
Pre-Application Consultation (PAC) events - May 2024
We recently held the second of our statutory pre-application consultation events for our proposed Coachford 400kV substation project, on Tuesday 28 May at Cairnie Memorial Hall, Wednesday 29 May at Stewarts Hall, Huntly and Thursday 30 May at Longmore Community Hall, Keith.
We would like to thank those who took the time to attend our feedback events and discuss our proposals with the project team. Updated information relating to the proposals are also available to download from the 'Documents' tab of this webpage.
Our formal feedback period closed on 11 July. We will however welcome final comments from members of the public, statutory consultees, and other key stakeholders regarding our proposals until we submit our planning application, planned for Autumn 2024.
Click on the video to view a 3D visualisation of the Proposed Coachford 400kV Substation.
About the Project
In order to support the continued growth in onshore and offshore renewables across the north of Scotland, supporting the country's drive towards Net Zero, investment in network infrastructure is needed to connect this renewable power and transport it from source to areas of demand across the country.
Extensive studies have confirmed the need to reinforce the onshore transmission infrastructure between Beauly and Peterhead. To enable these reinforcements, a new 400kV substation is required in Coachford, near Blackhillock, to enable connection of the new 400kV overhead line between Beauly, Blackhillock, New Deer and Peterhead.
Find Out More About Beauly - Blackhillock - New Deer - Peterhead 400kV Connection
This video outlines how the project contributes to our role in delivering Net Zero.
Pathway to 2030
The Pathway to 2030, published by National Energy System Operator NESO, the electricity system operator for Great Britain, sets the blueprint for the electricity transmission network infrastructure required to enable the forecasted growth in renewable electricity across Great Britain.
The projects identified within the Pathway to 2030 are critical to delivering the UK and Scottish Government’s offshore wind targets. To deliver these targets, we are investing over £10bn to upgrade the network infrastructure across the north of Scotland as the region plays a leading role in the clean energy transition.
As part of this investment, there is a requirement for a new 400kV substation in Blackhillock.
Stakeholder Engagement
The Coachford 400kV Substation Project is currently in the development stages and is subject to extensive consultation with stakeholders. As this project is closely linked with the 400kV overhead line from Beauly to Peterhead, the project teams will aim to tie in consultation for both projects within each locality.
You can find out more about the Beauly - Blackhillock - New Deer - Peterhead 400kV Connection Project in this video, where Project Manager Catherine Swan and Community Liaison Manager Ryan Davidson describe the approach we are taking to develop our proposals, and the opportunities that are available for stakeholders to feed into the design process.
How we’re embracing artificial intelligence (AI)
We intend to use AI to assist our experienced teams in the analysis of your feedback, so we can categorise key points raised more quickly. You can learn more about how we’re utilising AI on this dedicated web page.
Project Updates
Featured updates
Featured updates for this project
Project updates
Documents
Pre-Application Consultation 2024 - Materials
-
Coachford PAC 2 Consultation Booklet - May 24
- Type:
- Date:
- 16 May 2024
- Size:
- 9 MB
This document provides information to our stakeholders about the project and was provided during our pre-application consultations in May 2024.
-
Coachford PAC 1 Booklet - Feb 2024
- Type:
- Date:
- 21 February 2024
- Size:
- 4.8 MB
This document provides information to our stakeholders about the project and was provided during our pre-application consultations in March 2024.
-
Coachford Landscape Proposals Plan.
- Type:
- Date:
- 15 February 2024
- Size:
- 7 MB
This map provides information to our stakeholders about the Coachford Landscape Proposals Plan, produced 16 January 2024.
-
Coachford Red Line Boundary
- Type:
- Date:
- 15 February 2024
- Size:
- 4 MB
This map provides information to our stakeholders about the Proposal of Application Notice (PAN) red line boundary for the site, produced 26 January 2024.
-
Coachford Landscape Proposals Plan.
- Type:
- Date:
- 15 February 2024
- Size:
- 5.4 MB
This map provides information to our stakeholders about the Coachford Substation Site Layout, produced 19 December 2023.
-
Coachford PAC 1 Postcard
- Type:
- Date:
- 15 February 2024
- Size:
- 626.6 KB
This document is the Coachford PAC 1 Postcard invite posted out to properties in 10km radius of substation site and provides information on our consultation events in March 2024.
Report on Consultation
-
Summary ROC - Beauly to Peterhead.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 2.8 MB
-
Report on Consultation - Blackhillock 2 400kV Substation.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 7.1 MB
-
RoC - Blackhillock 2 - Figure 2 - Proposed Site 4.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 9.8 MB
Pathway to 2030 Projects - Additional Information
March 2023 Consultation Materials
-
Consultation Event Postcard Invite
- Type:
- Date:
- 06 March 2023
- Size:
- 559.6 KB
-
New Blackhillock 2 400kV Substation Consultation Booklet
- Type:
- Date:
- 06 March 2023
- Size:
- 5.9 MB
FAQs
Who we are
About the Pathway to 2030 projects
Our approach to routeing and public consultation
Environmental considerations
Community and landowner considerations
Cost and engineering considerations
Recite me
To make use of this function please click on the 3 'A's' button at the bottom left of the website.

Latest Links
-
Report on Consultation
Our Reports on Consultation across our three new overhead line projects and associated substation and convertor station developments have now been published. These reports provide a summary of the extensive feedback received during consultation, how this has been considered and confirmation of which routes and substations are now being taken forward to the next stage of development.
Our Reports on Consultation are now available to download from the Project Documentation tab.
Summary Reports on Consultation are also available for each of the three schemes and can be downloaded below:
- Summary Report on Consultation Spittal to Beauly
- Summary Report on Consultation Beauly to Peterhead
- Summary Report on Consultation Kintore to Tealing
A stakeholder webinar available for all to join will be held in the coming weeks to share the changes informed by the feedback. More information about the forthcoming webinar will be shared on our events page shortly.
In further recognition of community feedback, we will seek to rationalise cumulative infrastructure impacts through the removal and undergrounding of existing transmission lines, where technically practical and appropriate, and subject to all necessary planning consents and landowner agreements.
Work to identify and assess potential sections of existing overhead line where their removal will reduce cumulative impacts is ongoing, with an update expected as part of the next round of public consultation on overhead line alignments and more detailed substation designs in early 2024.
We would once again like to thank all stakeholders who took the time to engage with our early consultation process. We will continue to engage with stakeholders ahead of consulting further with local communities and stakeholders in the new year, as we look to refine our proposals.
-
Report on Consultation
Over the course of this year, we have undertaken extensive consultation on plans to upgrade the electricity transmission network across the north of Scotland and have received a considerable amount of feedback from a wide range of stakeholders regarding our proposals.
We recently advised in our next steps for 2030 network developments update that following assessment of consultation feedback and additional options analysis, we would publish our Report on Consultations (RoCs). These reports provide a summary of the feedback received and how it has been considered, which options we will take forward to the next stage of the development process and any changes to options initially consulted on.
It is our intention to publish the RoCs during the week commencing 27 November. All stakeholders signed up for updates on the project will receive a link to the report and we will also issue Summary Reports to help ensure accessibility.
These Report on Consultations mark the completion of the first round of non-statutory consultation, where we sought feedback on the corridor, route, and substation locations. We will be consulting further with local communities and stakeholders in the new year, as we look to refine the projects, therefore we welcome an open channel of communication and would like to reassure all stakeholders that there will be further opportunities to engage on this project.
Our Reports on Consultation and Summary Reports on Consultation are now available to download from the Project Documentation tab. -
SSEN Transmission sets out next steps for Pathway to 2030 network developments
We have announced our next steps for our Pathway to 2030 programme of projects. We would like to thank everyone who has engaged with our teams and kindly taken the time to respond to our consultations.
Full details of the announcement can be found here:
Next steps for Pathway to 2030