Overview
Advance Notice of intention to submit section 37 (s37) application for the proposed Beauly to Blackhillock to New Deer to Peterhead 400 kV overhead line (OHL) Project
In accordance with the Priority Applications for Transmission Infrastructure guidance: Section 37 of the Electricity Act 1989, SSEN Transmission has held the Procedural Gatecheck meeting with the Energy Consents Unit (ECU) and is issuing this notice to provide advance notice to the statutory consultees, relevant Planning Authorities, affected landowners and local stakeholders of the date the s37 application is to be made.
We intend to submit the s37 application for the proposed Beauly to Blackhillock to New Deer to Peterhead 400 kV OHL Project by 03 October 2025.
Next Steps:
Following s37 submission, the ECU will undertake a validation process to confirm the application is complete. This may take approximately one to two weeks. Upon confirmation the application is complete, SSEN Transmission will issue statutory public notices in National and Local Press in accordance with The Electricity Works (Environmental Impact Assessment) (Scotland) Regulations 2017. In addition, we shall notify our stakeholders and issue a wider general press release.
Alongside the statutory notifications, the s37 application will be available on the ECU Website Scottish Government - Energy Consents Unit, SSEN Transmission Project Website (Beauly - Peterhead 400kV OHL - SSEN Transmission) and printed copies will be provided for members of the public to view at various locations along the length of the proposed OHL. Details of the viewing locations will be provided in the public notices, within the s37 application, provided to stakeholders on our mailing list and available on our website.
SSEN Transmission will issue further communications, after validation, providing information on how representations can be made to Scottish Ministers.
Further information on the s37 submission process can be found here: 2. Background - Priority Applications for Transmission Infrastructure guidance: Section 37 of the Electricity Act 1989 - gov.scot
Thank you for taking the time to read this notice.
Removal of Coachford Substation from Beauly-Peterhead project scope
We announced in May of this year that following detailed ground investigation works which revealed technical challenges at the site, we will no longer be proceeding with the construction of the proposed substation at Coachford as part of the Beauly to Peterhead 400kV overhead line project.
Whilst the Coachford site is no longer being progressed, the wider Beauly-Peterhead 400kV project, and its initial objectives, remain on track for 2030 delivery. In June we held engagement events on the subsequent design changes to the proposed alignment in the Keith and Cairnie area, presenting what we now plan to take forward in our Section 37 consent application.
We aim to submit our consent application for the Proposed Development to the Energy Consents Unit of the Scottish Government in Autumn 2025. The application will be submitted in line with the requirements of Section 37 of the Electricity Act 1989.
Further documents relating to our most recent and previous engagement events can be found in the documents tab of this project page.
You can read more about Coachford in our press release.
3D Model
We have a 3D model which allows users to view the overhead line from view points across the project route.
About the Project
In order to support the continued growth in onshore and offshore renewables across the north of Scotland, supporting the country's drive towards Net Zero, investment in network infrastructure is needed to connect this renewable power and transport it from source to areas of demand across the country.
Extensive studies have confirmed the need for a new 400kV connection between Beauly and Peterhead, connecting into a substation site at New Deer. The project includes the following elements:
- A new 400kV connection between Beauly and New Deer
- A new 400kV connection between New Deer and Peterhead
- New 400kV substations and associated infrastructure at Beauly, New Deer and Peterhead
- Removal of the existing 132kV overhead line from Beauly to Knocknagael following establishment of the new 400kV connection
Find Out More About New Beauly Area 400kV Substation
Pathway to 2030
The Pathway to 2030, published by National Energy System Operator NESO, the electricity system operator for Great Britain, sets the blueprint for the electricity transmission network infrastructure required to enable the forecasted growth in renewable electricity across Great Britain.
The projects identified within the Pathway to 2030 are critical to delivering the UK and Scottish Government’s offshore wind targets. To deliver these targets, we are investing over £20bn to upgrade the network infrastructure across the north of Scotland as the region plays a leading role in the clean energy transition.
As part of this investment, there is a requirement for a new 400kV connection between Beauly and Peterhead.
Explore Pathway to 2030 Projects
This video outlines how the project contributes to our role in delivering Net Zero.
How we’re embracing artificial intelligence (AI)
We intend to use AI to assist our experienced teams in the analysis of your feedback, so we can categorise key points raised more quickly. You can learn more about how we’re utilising AI on this dedicated web page.
Project Updates
Featured updates
Featured updates for this project

Thank you for your engagement at our recent public consultation events
Project updates
Documents
June Alignment Events - Sections 19 & 20
Proposed Alignment Consultation Materials 2025
Pathway to 2030 Projects - Additional Information
Turriff & District CC Public Meeting Presentation
Alignment Consultation Materials - May & June 2024
Alignment Consultation Document and Figures
Refined Routeing Stage - Update Event
Routeing Stage Report on Consultation
Routeing Stage Consultation Event Materials
Corridor Stage Consultation Materials
GI Works
Ground Investigation (GI) Works
Prior to the submission of our Section 37 Application for the proposed Beauly-Blackhillock-New Deer-Peterhead 400kV overhead line project, access to the proposed alignment route will be required to undertake more detailed ground investigations (GI) and inspections of the proposed tower locations. GI works are a necessary step in any new development with the results helping to establish final tower foundation designs, allowing engineers to understand the engineering properties of the soil and rock beneath potential tower locations and their ability to support the structures.
All works are carried out using Permitted Development rights available to SSEN Transmission under Class 40, (1), (c) of the Town and Country Planning (General Permitted Development) (Scotland) Order 1992 as amended. These are necessary survey works, and we will be working closely with relevant departments in the respective Local Authorities (e.g. Road, Planning, Access), Statutory Partners and Landowners.
We will communicate important updates through the ‘Project updates’ section of this webpage (see ‘Project Update’ tab above) where the works details will be available.
Our contractors will work to keep local disturbance to a minimum throughout the duration of these works. For any enquiries, please contact BBNP@sse.com.
More Information
FAQs
Who we are
About the Pathway to 2030 projects
Our approach to routeing and public consultation
Environmental considerations
Community and landowner considerations
Cost and engineering considerations
Recite me
To make use of this function please click on the 3 'A's' button at the bottom left of the website.

Latest Links
-
Report on Consultation
Our Reports on Consultation across our three new overhead line projects and associated substation and convertor station developments have now been published. These reports provide a summary of the extensive feedback received during consultation, how this has been considered and confirmation of which routes and substations are now being taken forward to the next stage of development.
Our Reports on Consultation are now available to download from the Project Documentation tab.
Summary Reports on Consultation are also available for each of the three schemes and can be downloaded below:
- Summary Report on Consultation Spittal to Beauly
- Summary Report on Consultation Beauly to Peterhead
- Summary Report on Consultation Kintore to Tealing
A stakeholder webinar available for all to join will be held in the coming weeks to share the changes informed by the feedback. More information about the forthcoming webinar will be shared on our events page shortly.
In further recognition of community feedback, we will seek to rationalise cumulative infrastructure impacts through the removal and undergrounding of existing transmission lines, where technically practical and appropriate, and subject to all necessary planning consents and landowner agreements.
Work to identify and assess potential sections of existing overhead line where their removal will reduce cumulative impacts is ongoing, with an update expected as part of the next round of public consultation on overhead line alignments and more detailed substation designs in early 2024.
We would once again like to thank all stakeholders who took the time to engage with our early consultation process. We will continue to engage with stakeholders ahead of consulting further with local communities and stakeholders in the new year, as we look to refine our proposals.
-
Report on Consultation
Over the course of this year, we have undertaken extensive consultation on plans to upgrade the electricity transmission network across the north of Scotland and have received a considerable amount of feedback from a wide range of stakeholders regarding our proposals.
We recently advised in our next steps for 2030 network developments update that following assessment of consultation feedback and additional options analysis, we would publish our Report on Consultations (RoCs). These reports provide a summary of the feedback received and how it has been considered, which options we will take forward to the next stage of the development process and any changes to options initially consulted on.
It is our intention to publish the RoCs during the week commencing 27 November. All stakeholders signed up for updates on the project will receive a link to the report and we will also issue Summary Reports to help ensure accessibility.
These Report on Consultations mark the completion of the first round of non-statutory consultation, where we sought feedback on the corridor, route, and substation locations. We will be consulting further with local communities and stakeholders in the new year, as we look to refine the projects, therefore we welcome an open channel of communication and would like to reassure all stakeholders that there will be further opportunities to engage on this project.
Our Reports on Consultation and Summary Reports on Consultation are now available to download from the Project Documentation tab. -
SSEN Transmission sets out next steps for Pathway to 2030 network developments
We have announced our next steps for our Pathway to 2030 programme of projects. We would like to thank everyone who has engaged with our teams and kindly taken the time to respond to our consultations.
Full details of the announcement can be found here:
Next steps for Pathway to 2030