Overview
Marine Licence application submitted
Our Marine Licence application for the Eastern Green Link 3 subsea cable is now open for public consultation.
The application follows two years of development and marine surveying, as well as extensive engagement with marine users, offshore developers, and other stakeholders.
You can view our application via this link Marine Licence Application - EGL3 Cable - Sandford Bay, Peterhead to the English Border - 00011429 | marine.gov.scot
For convenience, we have also made the application documents available to view via the Documents tab at the top of this page and a hard copy is available at Peterhead Library.
Further information
A booklet containing information about the project is available for download via the ‘Documents’ tab on this webpage. Please register for project updates to keep up to date with this project if it interests you.
Please explore this webpage for more information about the Eastern Green Link 3 project.
- For more information on the Netherton Hub, where the Eastern Green Link 3 HVDC converter station is proposed to be located, click here.
- For more information on the proposed overhead line tie-in between the Netherton Hub and existing New Deer-Peterhead 400kV overhead line, click here.
- For more information on the proposed rebuild of a section of the overhead line section between Netherton Hub and the Peterhead 400kV substation, click here.
Project Updates
Featured updates
Featured updates for this project
Marine Licence application submitted
Project updates
Documents
Marine Licence Application
-
00011429 - Gis Chart Pdf.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 1.2 MB
-
Appendix 3a Emf Assessment Egl 3 Meap.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 741.9 KB
-
Appendix 3b Outline Cemp Egl 3 Meap Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 11.9 MB
-
Appendix 3c Egl3 Heat Calculations Egl 3 Meap.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 819.7 KB
-
Appendix 5a Hra Screening Egl 3 Meap Redacted Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 33.6 MB
-
Appendix 5c Mpa Assessment Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 13.3 MB
-
Appendix 6a Pu061 Tn03v1 Spreadsheetmodel Mea Egl3 Reviewed Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 389.7 KB
-
Appendix 6b Wfd Assessment Report Egl3 Meap Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 1.5 MB
-
Appendix 10a Underwater Noise Modelling Technical Assessment Egl 3 Meap.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 1.9 MB
-
Appendix 11a Nra Egl 3 Meap Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 16.2 MB
-
Appendix 12a Outline Fmmp Egl 3 Meap Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 1.5 MB
-
Appendix 14a Marine Archaeological Technical Report Egl 3 Meap Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 7.9 MB
-
Appendix 14b Egl 3 Meap Marine Archaeology Wsi Pad Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 2.2 MB
-
C01494 Egl3 Mea Loc 018 A.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 12.6 MB
-
Chapter 1 - Introduction To Eastern Green Link 3 Egl 3 Meap Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 867 KB
-
Chapter 2 - Project Need And Alternatives Egl3 Meap Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 4.5 MB
-
Chapter 3 - Project Description Egl 3 Meap 1 Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 12.4 MB
-
Chapter 4 - Marine Environmental Appraisal Scope And Methodology Egl 3 Meap Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 1007.4 KB
-
Chapter 5 - Designated Sites Egl 3 Meap Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 842.7 KB
-
Chapter 7 - Intertidal And Subtidal Benthic Ecology Egl3 Meap Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 10.7 MB
-
Chapter_6_-_Marine_Physical_Processes_Egl3_Meap_Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 12.8 MB
-
Chapter 10 - Marine Mammals And Marine Reptiles Egl3 Meap Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 67.9 MB
-
Chapter 11 - Shipping And Navigation Egl3 Meap Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 10.6 MB
-
Chapter 12 - Commercial Fisheries Egl 3 Meap 1 Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 18.2 MB
-
Chapter 13 - Other Marine Users And Activities Egl 3 Meap Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 26.9 MB
-
Chapter 14 - Marine Archaeology Egl 3 Meap Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 4.8 MB
-
Chapter 15 - Schedule Of Mitigation Egl 3 Meap Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 876.8 KB
-
Chapter 16 - Conclusions Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 1.2 MB
-
Chapter 8 - Fish And Shellfish Egl3 Meap Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 50 MB
-
Chapter 9 - Intertidal And Offshore Ornithology Egl 3 Meap Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 16.5 MB
-
Egl3 Coordinates.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 79.3 KB
-
Egl3 Meap Memo - Response To Md-Lot 012026.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 899.1 KB
-
Egl3 Sandford Bay Landfall Photographs.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 915.8 KB
-
Egl3 Stakeholder Engagement.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 350.8 KB
-
Ml Application Inshore Egl3hvdc Signed Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 4.4 MB
-
Ml Application Offshore Egl3hvdc Signed Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 4.3 MB
-
Non-Technical Summary Egl3 Meap Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 13.2 MB
-
Pre Application Consultation Report Egl 3 Meap Redacted Compressed Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 48.5 MB
-
Appendix 2a Nmp Assessment Egl 3 Meap Redacted.pdf
- Type:
- Date:
- 13 February 2026
- Size:
- 11.8 MB
Consultation and information materials
-
EGL3-1-Marine Consultation Booklet
- Type:
- Date:
- 09 May 2025
- Size:
- 19.6 MB
This document provides information to our stakeholders about the project and was provided during our consultation in March 2025
-
EGL3-2-Marine Banners
- Type:
- Date:
- 09 May 2025
- Size:
- 59.6 MB
This material provides information to our stakeholders about the project and/or consultation events.
-
EGL3-3-Land Cable Booklet
- Type:
- Date:
- 09 May 2025
- Size:
- 28.9 MB
This document provides information to our stakeholders about the project and was provided during our consultation in May 2025
Previous consultation materials
-
EGL3 alignment March 2025
- Type:
- Date:
- 28 February 2025
- Size:
- 1.2 MB
This map provides information to our stakeholders about the alignment options within Netherton Hub , produced 24 February 2025.
-
EGL3 Land Cable Booklet
- Type:
- Date:
- 27 February 2025
- Size:
- 28.9 MB
This document provides information to our stakeholders about our land cable, presented during our information events in March 2025.
-
Eastern Green Link 3 Cable Map
- Type:
- Date:
- 29 June 2023
- Size:
- 1.5 MB
This material provides information to our stakeholders about the project and/or consultation events.
-
EGL3 HVDC Cable Scheme - Consultation Booklet - June 2023
- Type:
- Date:
- 13 June 2023
- Size:
- 12.1 MB
This material provides information to our stakeholders about the project and/or consultation events.
Pathway to 2030 Projects - Additional Information
FAQs
Who we are
About the Pathway to 2030 projects
Our approach to routeing and public consultation
Environmental considerations
Community and landowner considerations
Cost and engineering considerations
Eastern Green Link 3
To meet the requirements of increasing renewable energy generation multiple projects are being developed by SSEN Transmission and others are being jointly developed with between SSEN Transmission and National Grid. Extensive system studies have been completed to inform the ESO’s ‘Pathway to 2030 Holistic Network Design’, confirming the requirement to develop new direct connections between the networks in Scotland and England.
To transfer the renewable power generated in the North of Scotland to demand centres in the South a 525kV HVDC link, via a subsea cable from Peterhead to the Lincolnshire area is required and will be known as Eastern Green Link 3.
The Eastern Green Link 3 project will use the latest technology to provide a 2GW bi-pole, 525kV HVDC link between Peterhead in Aberdeenshire and the Lincolnshire area in England. This will enable the efficient transmission of high volumes of power which can then be further distributed to demand centres throughout the UK.
At each end of the HVDC link, 400kV AC substations will supply power to (or receive power from) newly constructed high voltage AC/DC converter stations at Peterhead and Lincolnshire, depending on the directional flow of power. Consultations for the converter station sites have begun and future consultations will be held in 2024.
Connections between these assets will be via HVDC cables buried either underground or below the seabed. In Peterhead, the land cable corridor could stretch up to 12km between the Peterhead Net Zero 2030 Development site and the associated landfall. The cables will also pass through a neighbouring HVDC switching station which will provide further resilience to the network. The subsea cable route is currently being developed, including making a final determination of preferred landfalls in Scotland and England however the subsea cable may cover up to 550km before making the transition back to land cable again. The length of the land cable corridor to grid connection in England will also depend on the final landfall location.
Community Engagement
Throughout the life of our projects, we aim to work positively with local communities and keep people informed about what we are doing. This is particularly important when we are developing a proposal and we want to understand what local people think about our plans.We endeavour to take the time to discuss proposals with local community councils, encourage engagement from the wider community and listen to the feedback we receive. We will do our best to answer any questions and address issues or concerns that are raised with us.
When our project progresses into construction, we will continue working closely with the local community to ensure that our work has as little impact on the lives of those living and working in the area and as many long term positive effects as possible.
How we’re embracing artificial intelligence (AI)
We intend to use AI to assist our experienced teams in the analysis of your feedback, so we can categorise key points raised more quickly. You can learn more about how we’re utilising AI on this dedicated web page.
Recite me
To make use of this function please click on the 3 'A's' button at the bottom left of the website.
Latest Links
-
Report on Consultation
Our Reports on Consultation across our three new overhead line projects and associated substation and convertor station developments have now been published. These reports provide a summary of the extensive feedback received during consultation, how this has been considered and confirmation of which routes and substations are now being taken forward to the next stage of development.
Our Reports on Consultation are now available to download from the Project Documentation tab.
Summary Reports on Consultation are also available for each of the three schemes and can be downloaded below:
- Summary Report on Consultation Spittal to Beauly
- Summary Report on Consultation Beauly to Peterhead
- Summary Report on Consultation Kintore to Tealing
A stakeholder webinar available for all to join will be held in the coming weeks to share the changes informed by the feedback. More information about the forthcoming webinar will be shared on our events page shortly.
In further recognition of community feedback, we will seek to rationalise cumulative infrastructure impacts through the removal and undergrounding of existing transmission lines, where technically practical and appropriate, and subject to all necessary planning consents and landowner agreements.
Work to identify and assess potential sections of existing overhead line where their removal will reduce cumulative impacts is ongoing, with an update expected as part of the next round of public consultation on overhead line alignments and more detailed substation designs in early 2024.
We would once again like to thank all stakeholders who took the time to engage with our early consultation process. We will continue to engage with stakeholders ahead of consulting further with local communities and stakeholders in the new year, as we look to refine our proposals.
-
Report on Consultation
Over the course of this year, we have undertaken extensive consultation on plans to upgrade the electricity transmission network across the north of Scotland and have received a considerable amount of feedback from a wide range of stakeholders regarding our proposals.
We recently advised in our next steps for 2030 network developments update that following assessment of consultation feedback and additional options analysis, we would publish our Report on Consultations (RoCs). These reports provide a summary of the feedback received and how it has been considered, which options we will take forward to the next stage of the development process and any changes to options initially consulted on.
It is our intention to publish the RoCs during the week commencing 27 November. All stakeholders signed up for updates on the project will receive a link to the report and we will also issue Summary Reports to help ensure accessibility.
These Report on Consultations mark the completion of the first round of non-statutory consultation, where we sought feedback on the corridor, route, and substation locations. We will be consulting further with local communities and stakeholders in the new year, as we look to refine the projects, therefore we welcome an open channel of communication and would like to reassure all stakeholders that there will be further opportunities to engage on this project.
Our Reports on Consultation and Summary Reports on Consultation are now available to download from the Project Documentation tab. -
SSEN Transmission sets out next steps for Pathway to 2030 network developments
We have announced our next steps for our Pathway to 2030 programme of projects. We would like to thank everyone who has engaged with our teams and kindly taken the time to respond to our consultations.
Full details of the announcement can be found here:
Next steps for Pathway to 2030