Overview
Planning consent granted for the Netherton Hub
SSEN Transmission has received verbal confirmation of planning permission in principle from Aberdeenshire Council’s Infrastructure Services Committee for the proposed Netherton Hub.
This decision follows two years of development and extensive community and stakeholder engagement by SSEN Transmission. We want to thank everyone who took the time to engage with us throughout the planning and consultation process.
Community feedback has helped shape the hub’s design, addressing concerns about flooding and visual impact through measures like dedicated land for drainage, screening, bunding, and landscaping.
We will continue to engage closely with all our stakeholders as we progress through the next stages of development. Construction of the Netherton Hub is expected to commence early next year.
Click on the video to view a 3D visualisation of the Netherton Hub.
About the Project
The Netherton Hub is a key part of our Pathway to 2030 programme and is intended to:
- Enable the connection and transmission of renewable energy
- Strengthen the electricity network in the region
- Support Scotland’s transition to net zero
Netherton Hub is expected to deliver substantial economic and legacy benefits for the north-east of Scotland, including more than £2.5m in community benefit funding.
Once complete, the site will comprise:
- A 400kV substation to support offshore and onshore electricity generation
- A 132kV substation to support further future generation and storage connections from third party developers
- The Spittal to Peterhead High Voltage Direct Current (HVDC) converter station to support the transmission of renewable energy from new generators in the north of Scotland to demand centres throughout the UK
- The Eastern Green Link 3 HVDC converter station to support the transmission of renewable energy from generators in the north of Scotland to Norfolk and beyond
- A further transmission hall, with capacity for more infrastructure to future proof the growing network
- A spares warehouse and operations base.
Construction of the Netherton Hub is expected to commence early next year.
Find Out More About Spittal - Peterhead Subsea Cable Link
Find Out More About Beauly - Blackhillock - New Deer - Peterhead 400kV Connection
Find Out More About Netherton Hub 400kV Overhead Line Connection to New Deer and Peterhead - Tie-in Connection
Netherton Hub 400kV Overhead Line Connection to New Deer and Peterhead - Rebuild
This video outlines how the project contributes to our role in delivering Net Zero.
Unlocking local benefits, supporting jobs and delivering economic growth
The Netherton Hub forms a key part of SSEN Transmission’s plans to invest at least £22bn in the period until March 2031, potentially rising to £31.7bn. It represents one of the largest ever private investment programmes in Scotland and will act as a major driver of jobs and economic growth across the country.
Economic analysis, which has been independently peer reviewed by leading consultancy BiGGAR Economics, forecast that if delivered in full, the potential £31.7bn total investment could support up to 17,500 jobs in Scotland, including 8,400 in the north of Scotland. It would also add up to £7bn in value to the Scottish economy, including £3bn in the north of Scotland. A socio-economic assessment produced by ARUP has found the proposed development could contribute £54.7 million to the total Gross Value Added (GVA) in the Aberdeenshire Council area during construction, and £1.61m per year during operation.
Following the publication of the UK Government’s Community Benefit Guidance for new electricity transmission infrastructure, over £100m of community benefit funding is expected across the north of Scotland, with the Netherton Hub alone expected to deliver more than £2.5m of community benefit funding.
SSEN Transmission’s Pathway to 2030 programme is also expected to support the development of at least 1,000 new homes across the north of Scotland, creating a legacy in the communities that will host construction workers by delivering housing that will support local need once projects are completed. SSEN Transmission is currently exploring sites that will deliver legacy housing, including land for future housing development, across the north of Aberdeenshire.
Pathway to 2030
The Pathway to 2030, published by National Energy System Operator NESO, the electricity system operator for Great Britain, sets the blueprint for the electricity transmission network infrastructure required to enable the forecasted growth in renewable electricity across Great Britain.
The projects identified within the Pathway to 2030 are critical to delivering the UK and Scottish Government’s offshore wind targets. To deliver these targets, we are investing over £10bn to upgrade the network infrastructure across the north of Scotland as the region plays a leading role in the clean energy transition.
As part of this investment, there is a requirement for the Peterhead Zet Zero 2030 Developments.
Community Engagement
Throughout the life of our projects, we aim to work positively with the local communities and keep people informed about what we are doing. This is particularly important when we are developing a proposal and we want to understand what local people think about our plans.
We endeavour to take the time to discuss proposals with local community councils, encourage engagement from the wider community and listen to the feedback we receive.
We will do our best to answer any questions and address issues or concerns that are raised with us.
When our project progresses into construction, we will continue working closely with the local community to ensure that our work has as little impact on the lives of those living and working in the area and as many long term positive effects as possible.
How we’re embracing artificial intelligence (AI)
We intend to use AI to assist our experienced teams in the analysis of your feedback, so we can categorise key points raised more quickly. You can learn more about how we’re utilising AI on this dedicated web page.
Project Updates
Featured updates
Featured updates for this project
Project updates
Documents
Supplementary documentation submitted to Aberdeenshire Council
Planning Application - EIA Volumes
Pre- Application Consultation (PAC) Documents
-
Netherton PAC2 Large Banner
- Type:
- Date:
- 10 May 2024
- Size:
- 1.6 MB
This is a visualisation of how the main building components may look upon completion and/or in the future.
-
Netherton Hub PAC2 Booklet
- Type:
- Date:
- 10 May 2024
- Size:
- 14.5 MB
This document provides information to our stakeholders about the project and was provided during our consultation in May 2024.
-
Netherton Hub PAC1 Booklet
- Type:
- Date:
- 19 February 2024
- Size:
- 17.9 MB
This document provides information to our stakeholders about the project and was provided during our consultation in February 2024.
-
Netherton large banner
- Type:
- Date:
- 14 February 2024
- Size:
- 4 MB
This is a visualisation of how the main building components may look upon completion and/or in the future.
-
Netherton Poster
- Type:
- Date:
- 14 February 2024
- Size:
- 448.9 KB
This document provides information to our stakeholders about our consultation event in Longside in February 2024.
Report on Consultation
-
Report on Consultation - Netherton Hub
- Type:
- Date:
- 04 December 2023
- Size:
- 2.3 MB
This Report on Consultation (and associated appendices/maps) documents the consultation process which has been undertaken for the project at corridor, routeing, alignment or substation site selection stage. It describes the key responses received and provides detail on the actions proposed in response to the issues raised.
-
Summary ROC - Beauly to Peterhead
- Type:
- Date:
- 01 December 2023
- Size:
- 2.8 MB
This Report on Consultation (and associated appendices/maps) documents the consultation process which has been undertaken for the project at corridor, routeing, alignment or substation site selection stage. It describes the key responses received and provides detail on the actions proposed in response to the issues raised.
-
RoC - Netherton Hub - Figure 1 - Substation Site Selection Options
- Type:
- Image
- Date:
- 01 December 2023
- Size:
- 673.5 KB
This Report on Consultation (and associated appendices/maps) documents the consultation process which has been undertaken for the project at corridor, routeing, alignment or substation site selection stage. It describes the key responses received and provides detail on the actions proposed in response to the issues raised.
Pathway to 2030 Projects - Additional Information
Netherton Hub Documents
-
Traffic management map - September 2023
- Type:
- Date:
- 30 August 2023
- Size:
- 2.2 MB
This material provides information to our stakeholders about the project.
-
Geotechnical Investigation Layout
- Type:
- Date:
- 21 June 2023
- Size:
- 1 MB
This material provides information to our stakeholders about the project.
-
Peterhead Net Zero 2030 - Site Selection Map
- Type:
- Date:
- 22 April 2023
- Size:
- 11.7 MB
This material indicates the substation site selection exercise undertaken, the alternatives considered during the identification of search areas, and the identification of a number of potential sites.
-
Peterhead Net Zero 2030 Developments - Consultation Booklet April 2023
- Type:
- Date:
- 14 April 2023
- Size:
- 6.8 MB
This document provides information to our stakeholders about the project and was provided during our consultation in April 2023.
-
Peterhead Net Zero 2030 Development - Consultation Booklet - January 2023
- Type:
- Date:
- 19 January 2023
- Size:
- 7.3 MB
This document provides information to our stakeholders about the project and was provided during our consultation in January 2023.
-
Peterhead Net Zero 2030 Developments - Consultation Poster
- Type:
- Date:
- 18 January 2023
- Size:
- 113.1 KB
This document provides information to our stakeholders about our consultation events in January 2023.
FAQs
Who we are
About the Pathway to 2030 projects
Our approach to routeing and public consultation
Environmental considerations
Community and landowner considerations
Cost and engineering considerations
Recite me
To make use of this function please click on the 3 'A's' button at the bottom left of the website.

Latest Links
-
Report on Consultation
Our Reports on Consultation across our three new overhead line projects and associated substation and convertor station developments have now been published. These reports provide a summary of the extensive feedback received during consultation, how this has been considered and confirmation of which routes and substations are now being taken forward to the next stage of development.
Our Reports on Consultation are now available to download from the Project Documentation tab.
Summary Reports on Consultation are also available for each of the three schemes and can be downloaded below:
- Summary Report on Consultation Spittal to Beauly
- Summary Report on Consultation Beauly to Peterhead
- Summary Report on Consultation Kintore to Tealing
A stakeholder webinar available for all to join will be held in the coming weeks to share the changes informed by the feedback. More information about the forthcoming webinar will be shared on our events page shortly.
In further recognition of community feedback, we will seek to rationalise cumulative infrastructure impacts through the removal and undergrounding of existing transmission lines, where technically practical and appropriate, and subject to all necessary planning consents and landowner agreements.
Work to identify and assess potential sections of existing overhead line where their removal will reduce cumulative impacts is ongoing, with an update expected as part of the next round of public consultation on overhead line alignments and more detailed substation designs in early 2024.
We would once again like to thank all stakeholders who took the time to engage with our early consultation process. We will continue to engage with stakeholders ahead of consulting further with local communities and stakeholders in the new year, as we look to refine our proposals.
-
Report on Consultation
Over the course of this year, we have undertaken extensive consultation on plans to upgrade the electricity transmission network across the north of Scotland and have received a considerable amount of feedback from a wide range of stakeholders regarding our proposals.
We recently advised in our next steps for 2030 network developments update that following assessment of consultation feedback and additional options analysis, we would publish our Report on Consultations (RoCs). These reports provide a summary of the feedback received and how it has been considered, which options we will take forward to the next stage of the development process and any changes to options initially consulted on.
It is our intention to publish the RoCs during the week commencing 27 November. All stakeholders signed up for updates on the project will receive a link to the report and we will also issue Summary Reports to help ensure accessibility.
These Report on Consultations mark the completion of the first round of non-statutory consultation, where we sought feedback on the corridor, route, and substation locations. We will be consulting further with local communities and stakeholders in the new year, as we look to refine the projects, therefore we welcome an open channel of communication and would like to reassure all stakeholders that there will be further opportunities to engage on this project.
Our Reports on Consultation and Summary Reports on Consultation are now available to download from the Project Documentation tab. -
SSEN Transmission sets out next steps for Pathway to 2030 network developments
We have announced our next steps for our Pathway to 2030 programme of projects. We would like to thank everyone who has engaged with our teams and kindly taken the time to respond to our consultations.
Full details of the announcement can be found here:
Next steps for Pathway to 2030