Spittal – Loch Buidhe – Beauly 400kV Connection
- Type
- Transmission reinforcement
- Location
- Highland
Overview
Report on Consultation
Our Reports on Consultation across our three new overhead line projects and associated substation and convertor station developments have now been published. These reports provide a summary of the extensive feedback received during consultation, how this has been considered and confirmation of which routes and substations are now being taken forward to the next stage of development.
Our Reports on Consultation are now available to download from the Project Documents tab. Summary Reports on Consultation are also available here:
Summary Report on Consultation Spittal to Beauly
Summary Report on Consultation Beauly to Peterhead
Summary Report on Consultation Kintore to Tealing
A stakeholder webinar available for all to join will be held in the coming weeks to share the changes informed by the feedback. More information about the forthcoming webinar will be shared on our events page shortly.
In further recognition of community feedback, we will seek to rationalise cumulative infrastructure impacts through the removal and undergrounding of existing transmission lines, where technically practical and appropriate, and subject to all necessary planning consents and landowner agreements.
Work to identify and assess potential sections of existing overhead line where their removal will reduce cumulative impacts is ongoing, with an update expected as part of the next round of public consultation on overhead line alignments and more detailed substation designs in early 2024.
We would once again like to thank all stakeholders who took the time to engage with our early consultation process. We will continue to engage with stakeholders ahead of consulting further with local communities and stakeholders in the new year, as we look to refine our proposals.
About the Project
In order to support the continued growth in onshore and offshore renewables across the north of Scotland, supporting the country's drive towards Net Zero, investment in network infrastructure is needed to connect this renewable power and transport it from source to areas of demand across the country.
Extensive studies have confirmed the need for a new 400kV connection between Spittal and Beauly, connecting into new 400kV substation sites at Spittal, Loch Buidhe and Beauly. The project includes the following elements:
- A new 400kV connection between Spittal and Loch Buidhe
- A new 400kV connection between Loch Buidhe and Beauly
- New 400kV substations at Spittal, Loch Buidhe and Beauly
Find Out More About New Spittal Area 400kV Substation
Find Out More About New Loch Buidhe Area 400kV Substation
Find Out More About New Beauly Area 400kV Substation
This video outlines how the project contributes to our role in delivering Net Zero.
Pathway to 2030
The Pathway to 2030, published by National Grid ESO, the electricity system operator for Great Britain, sets the blueprint for the electricity transmission network infrastructure required to enable the forecasted growth in renewable electricity across Great Britain.
The projects identified within the Pathway to 2030 are critical to delivering the UK and Scottish Government’s offshore wind targets. To deliver these targets, we are investing over £10bn to upgrade the network infrastructure across the north of Scotland as the region plays a leading role in the clean energy transition.
As part of this investment, there is a requirement for a new 400kV connection between Spittal and Beauly.
Stakeholder Engagement
The Spittal – Loch Buidhe – Beauly 400kV Project is currently in the development stages. In this video, Project Manager Rebecca Gay and Community Liaison Manager Martin Godwin describe the approach we are taking in developing our proposals, and the opportunities that are available for stakeholders to feed into the design process.
Webinar - North of Scotland: Delivering a Pathway to Net Zero
The project was featured in our Spring 2022 regional webinar 'North of Scotland: Delivering a Pathway to Net Zero', attended by over 180 stakeholders from across the region. The webinar provided an overview of our projects in construction and development across the north of Scotland (Highlands, Islands, Moray and Aberdeenshire) and described the role of the north of Scotland in delivering a Network for Net Zero. A recording of the event can be viewed here:
Project Updates

Report on Consultation
Our Reports on Consultation across our three new overhead line projects and associated substation and convertor station developments have now been published. These reports provide a summary of the extensive feedback received during consultation, how this has been considered and confirmation of which routes and substations are now being taken forward to the next stage of development.
Our Reports on Consultation are now available to download from the Project Documentation tab.
Summary Reports on Consultation are also available for each of the three schemes and can be downloaded below:
- Summary Report on Consultation Spittal to Beauly
- Summary Report on Consultation Beauly to Peterhead
- Summary Report on Consultation Kintore to Tealing
A stakeholder webinar available for all to join will be held in the coming weeks to share the changes informed by the feedback. More information about the forthcoming webinar will be shared on our events page shortly.
In further recognition of community feedback, we will seek to rationalise cumulative infrastructure impacts through the removal and undergrounding of existing transmission lines, where technically practical and appropriate, and subject to all necessary planning consents and landowner agreements.
Work to identify and assess potential sections of existing overhead line where their removal will reduce cumulative impacts is ongoing, with an update expected as part of the next round of public consultation on overhead line alignments and more detailed substation designs in early 2024.
We would once again like to thank all stakeholders who took the time to engage with our early consultation process. We will continue to engage with stakeholders ahead of consulting further with local communities and stakeholders in the new year, as we look to refine our proposals.

Report on Consultation
Over the course of this year, we have undertaken extensive consultation on plans to upgrade the electricity transmission network across the north of Scotland and have received a considerable amount of feedback from a wide range of stakeholders regarding our proposals.
We recently advised in our next steps for 2030 network developments update that following assessment of consultation feedback and additional options analysis, we would publish our Report on Consultations (RoCs). These reports provide a summary of the feedback received and how it has been considered, which options we will take forward to the next stage of the development process and any changes to options initially consulted on.
It is our intention to publish the RoCs for this project in the coming months. All stakeholders signed up for updates on the project will receive a link to the report and we will also issue Summary Reports to help ensure accessibility.
These Report on Consultations mark the completion of the first round of non-statutory consultation, where we sought feedback on the corridor, route, and substation locations. We will be consulting further with local communities and stakeholders in the new year, as we look to refine the projects, therefore we welcome an open channel of communication and would like to reassure all stakeholders that there will be further opportunities to engage on this project.
Our Reports on Consultation and Summary Reports on Consultation are now available to download from the Project Documentation tab.

SSEN Transmission sets out next steps for Pathway to 2030 network developments
We have announced our next steps for our Pathway to 2030 programme of projects. We would like to thank everyone who has engaged with our teams and kindly taken the time to respond to our consultations.
Full details of the announcement can be found here:
Next steps for Pathway to 2030

Public Consultation February - March 2023
Public consultation feedback period has now closed
We would like to thank all stakeholders who took the time to attend and respond to our recent public consultation regarding our identified route options and substation locations for the new Spittal – Loch Buidhe – Beauly 400kV Connection.
The in-person consultation events were held between 20th February and 6th March at 9 different locations between Halkirk and Beauly and supplemented with an online event. The consultation feedback period was extended by two weeks and closed on 14th April.
Our proposals received a particularly high level of interest with over 600 online feedback forms received and a large volume of email and letter feedback.
We look forward to engaging further with local communities and stakeholders as we begin detailed analysis on the feedback received and carrying out more targeted engagement to assist with refining proposals.
A Consultation Summary Report is available on the Project Documents tab of this webpage.

Survey works to help inform next stages of development
We have recently started localised surveys, assessments and ground investigation works at various locations across the Pathway to 2030 projects which will be used to help gather information to inform the next stage of development for a major electricity transmission network upgrade in the north of Scotland.
Over the coming weeks and months, our project teams and contractors will undertake a series of site-specific assessments which include the likes of ground investigations, bird surveys, LiDAR flights, and ecological and archaeological walkovers and assessments.
Ground investigation works have either recently commenced or are set to begin throughout the Summer for the new 400kV substation and converter stations proposed as part of our Spittal – Loch Buidhe – Beauly 400kV connection, Western Isles connection, Beauly – Blackhillock – New Deer – Peterhead 400kV connection and East Coast 400kV phase 2 projects. Project teams and contractors will undertake a series of site-specific assessments which will help provide vital information and key data for the next phase of project development.
Some of the geo-technical ground investigations may involve drilling boreholes or digging trial pits, which will allow engineers to understand the geographical make-up and suitability of the ground in certain locations to help inform potential design options.
Site assessments and survey works are a key part of the project development process, and the results of these investigations will provide project teams with valuable information to help inform decisions regarding substation site selections and overhead line routes, which will be subject to further consultation later this year.
Initial surveys will prioritise sites and routes which performed the best based on our initial assessment of key environmental and people, technical, and economic factors, and there have been no decisions taken on locations as yet.
There may be more activity on the ground over the summer, and whilst most assessments are expected to cause very little local disruption, we would like to thank the local community for their patience whilst they are carried out. Where more evasive assessments are required such as ground investigation works, we will work to keep local disruption and environmental impacts to a minimum. Please contact your local Community Liaison Manager if you have any questions.

Consultation feedback has now closed
We would like to thank all stakeholders who took the time to attend and respond to our recent public consultation regarding our identified route options and substation locations for the new Spittal – Loch Buidhe – Beauly 400kV Connection project.
The in-person consultation events were held between 20th February and 6th March at 9 different locations between Halkirk and Beauly and supplemented with an online event. The consultation feedback period was extended by two weeks and closed on 14th April.
Our proposals received a particularly high level of interest with over 600 online feedback forms received and a large volume of email and letter feedback.
We look forward to engaging further with local communities and stakeholders as we begin detailed analysis on the feedback received and carrying out more targeted engagement to assist with refining proposals. Our next public consultation event is currently scheduled for late 2023.
In the meantime, a Consultation Summary Report and a Frequently Asked Questions document will be published in the coming weeks.

Digital story maps
This story map outlines the new Spittal - Loch Buidhe - Beauly 400kV overhead line and includes an interactive map of the proposed routes.
Spittal - Loch Buidhe - Beauly OHL Connection Story Map

Virtual Public Consultation Event - 6th March 2023
Enter Virtual Exhibition Room
Join us on Monday 6th March 2023 from 5pm - 7pm for our live Virtual Consultation event.

Public Consultation Events
We will be holding initial drop-in public consultation events in February/March 2023 to share our approach to developing this project and the rationale behind our early proposals.
This will involve hosting multiple consultation events between Spittal and Beauly to hear stakeholder views regarding our preferred technology options, thoughts on our proposed route option for the new 400kV connection and, if there are further considerations you believe need to be taken in to account during the next stage of the development process.
The consultation events will be taking place on:
20th February (2.30–7pm) - Halkirk, Ross Institue
21st February (2.30–7pm) - Helmsdale, Bunilidh Social Club
22nd February (2.30–7pm) - Dunbeath, Dunbeath Hall
23rd February (2.30–7pm) - Golspie, Fountain Road Hall
27th February (3.30–7pm) - Bonar Bridge, Community Hall
28th February (2.30–7pm) - Ardross, Community Hall
1st March (2.30–7pm) - Dingwall – Legion Hall
2nd March (2.30–7pm) - Beauly – Kilmorack Hall
6th March (5–7pm) Virtual event (Joining details to follow on website)
Should you have any questions regarding the consultations please contact the Community Liaison Manager, Martin Godwin.
Project Documents
Report on Consultation
-
Report on Consultation - New Beauly Area 400kV Substation and HVDC Converter Station.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 2.3 MB
-
RoC - New Beauly Area 400kV Substation - Figure 2 - Proposed Site.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 1.6 MB
-
Summary ROC - Spittal to Beauly.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 4.8 MB
-
Report on Consultation - New Spittal Area 400kV Substation and HVDC Converter Station.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 1.5 MB
-
RoC - New Spittal Area 400kV Substation - Figure 1 - Site Selection Options.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 6.7 MB
-
RoC - New Spittal Area 400kV Substation - Figure 2 - Spittal Proposed Substation and HVDC Converter Station Site.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 4.1 MB
-
Report on Consultation - New Loch Buidhe Area 400kV Substation.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 1.6 MB
-
RoC - New Loch Buidhe 400kV Substation - Figure 1 -Site Selection Options.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 12 MB
-
RoC - New Loch Buidhe 400kV Substation - Figure 2 -Proposed Substation Site.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 3.2 MB
-
Report on Consultation - Spittal to Loch Buidhe to Beauly Overhead Line.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 3.2 MB
-
RoC - Spittal to Beauly OHL - Figure 1 - Route Options Presented at Consultation.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 6.7 MB
-
RoC - Spittal to Beauly OHL - Figure 2 - Proposed Route options to take forward to alignment phase.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 6.1 MB
Next steps for Pathway to 2030 network developments
-
The challenges with undergrounding at 400kV
- Type:
- Date:
- 01 December 2023
- Size:
- 347.9 KB
-
How has the need for Pathway to 2030 projects been assessed and determined
- Type:
- Date:
- 14 November 2023
- Size:
- 5.1 MB
-
SSEN Transmission sets out next steps for 2030 network developments .pdf
- Type:
- Date:
- 11 October 2023
- Size:
- 122.3 KB
Project Documents
-
Spittal-Loch Buidhe-Beauly 400kV OHL_Route Selection_Consultation Document Aug 2023.pdf
- Type:
- Date:
- 05 October 2023
- Size:
- 17.2 MB
-
Consultation Summary Report - Spittal - Loch Buidhe - Beauly - July 23.pdf
- Type:
- Date:
- 13 July 2023
- Size:
- 1.3 MB
-
Consultation response May 2023.pdf
- Type:
- Date:
- 17 May 2023
- Size:
- 166.2 KB
-
Spittal-Loch Buidhe-Beauly initial consultation feedback response 28.03.23.pdf
- Type:
- Date:
- 28 March 2023
- Size:
- 199.9 KB
-
Spittal to Loch Buidhe to Beauly Preferred Route Constraints Maps Sections A,B,C,D,E Feb/March 2023
- Type:
- Date:
- 22 February 2023
- Size:
- 34.3 MB
-
Consultation Booklet (Spittal - Loch Buidhe - Beauly 400kV) Feb/March 2023
- Type:
- Date:
- 17 February 2023
- Size:
- 67.3 MB
-
Public Consultation Poster - Feb/March 2023
- Type:
- Date:
- 06 February 2023
- Size:
- 101 KB
Project Gallery
Project FAQs
Frequently Asked Questions
People/Local Businesses
Recite me
To make use of this function please click on the 3 'A's' button at the bottom left of the website.

Latest Links
-
Report on Consultation
Our Reports on Consultation across our three new overhead line projects and associated substation and convertor station developments have now been published. These reports provide a summary of the extensive feedback received during consultation, how this has been considered and confirmation of which routes and substations are now being taken forward to the next stage of development.
Our Reports on Consultation are now available to download from the Project Documentation tab.
Summary Reports on Consultation are also available for each of the three schemes and can be downloaded below:
- Summary Report on Consultation Spittal to Beauly
- Summary Report on Consultation Beauly to Peterhead
- Summary Report on Consultation Kintore to Tealing
A stakeholder webinar available for all to join will be held in the coming weeks to share the changes informed by the feedback. More information about the forthcoming webinar will be shared on our events page shortly.
In further recognition of community feedback, we will seek to rationalise cumulative infrastructure impacts through the removal and undergrounding of existing transmission lines, where technically practical and appropriate, and subject to all necessary planning consents and landowner agreements.
Work to identify and assess potential sections of existing overhead line where their removal will reduce cumulative impacts is ongoing, with an update expected as part of the next round of public consultation on overhead line alignments and more detailed substation designs in early 2024.
We would once again like to thank all stakeholders who took the time to engage with our early consultation process. We will continue to engage with stakeholders ahead of consulting further with local communities and stakeholders in the new year, as we look to refine our proposals.
-
Report on Consultation
Over the course of this year, we have undertaken extensive consultation on plans to upgrade the electricity transmission network across the north of Scotland and have received a considerable amount of feedback from a wide range of stakeholders regarding our proposals.
We recently advised in our next steps for 2030 network developments update that following assessment of consultation feedback and additional options analysis, we would publish our Report on Consultations (RoCs). These reports provide a summary of the feedback received and how it has been considered, which options we will take forward to the next stage of the development process and any changes to options initially consulted on.
It is our intention to publish the RoCs during the week commencing 27 November. All stakeholders signed up for updates on the project will receive a link to the report and we will also issue Summary Reports to help ensure accessibility.
These Report on Consultations mark the completion of the first round of non-statutory consultation, where we sought feedback on the corridor, route, and substation locations. We will be consulting further with local communities and stakeholders in the new year, as we look to refine the projects, therefore we welcome an open channel of communication and would like to reassure all stakeholders that there will be further opportunities to engage on this project.
Our Reports on Consultation and Summary Reports on Consultation are now available to download from the Project Documentation tab. -
SSEN Transmission sets out next steps for Pathway to 2030 network developments
We have announced our next steps for our Pathway to 2030 programme of projects. We would like to thank everyone who has engaged with our teams and kindly taken the time to respond to our consultations.
Full details of the announcement can be found here:
Next steps for Pathway to 2030