Beauly to Blackhillock to New Deer to Peterhead 400kV OHL
- Type
- Transmission reinforcement
- Location
- Aberdeenshire, Highland, Moray
Overview
Report on Consultation
Our Reports on Consultation across our three new overhead line projects and associated substation and convertor station developments have now been published. These reports provide a summary of the extensive feedback received during consultation, how this has been considered and confirmation of which routes and substations are now being taken forward to the next stage of development.
Our Reports on Consultation are now available to download from the Project Documents tab. Summary Reports on Consultation are also available here:
Summary Report on Consultation Spittal to Beauly
Summary Report on Consultation Beauly to Peterhead
Summary Report on Consultation Kintore to Tealing
A stakeholder webinar available for all to join will be held in the coming weeks to share the changes informed by the feedback. More information about the forthcoming webinar will be shared on our events page shortly.
In further recognition of community feedback, we will seek to rationalise cumulative infrastructure impacts through the removal and undergrounding of existing transmission lines, where technically practical and appropriate, and subject to all necessary planning consents and landowner agreements.
Work to identify and assess potential sections of existing overhead line where their removal will reduce cumulative impacts is ongoing, with an update expected as part of the next round of public consultation on overhead line alignments and more detailed substation designs in early 2024.
We would once again like to thank all stakeholders who took the time to engage with our early consultation process. We will continue to engage with stakeholders ahead of consulting further with local communities and stakeholders in the new year, as we look to refine our proposals.
About the Project
In order to support the continued growth in onshore and offshore renewables across the north of Scotland, supporting the country's drive towards Net Zero, investment in network infrastructure is needed to connect this renewable power and transport it from source to areas of demand across the country.
Extensive studies have confirmed the need for a new 400kV connection between Beauly and Peterhead, connecting into substation sites at Blackhillock and New Deer. The project includes the following elements:
- A new 400kV connection between Beauly and Blackhillock
- A new 400kV connection between Blackhillock and New Deer
- A new 400kV connection between New Deer and Peterhead
- New 400kV substations and associated infrastructure at Beauly, Blackhillock, New Deer and Peterhead
- Removal of the existing 132kV overhead line from Beauly to Knocknagael following establishment of the new 400kV connection
Find Out More About New Beauly Area 400kV Substation
Find Out More About New Blackhillock 400kV Substation
Find Out More About New Deer 2 400kV Substation
Find Out More About Peterhead 2030 Developments
This video outlines how the project contributes to our role in delivering Net Zero.
Pathway to 2030
The Pathway to 2030, published by National Grid ESO, the electricity system operator for Great Britain, sets the blueprint for the electricity transmission network infrastructure required to enable the forecasted growth in renewable electricity across Great Britain.
The projects identified within the Pathway to 2030 are critical to delivering the UK and Scottish Government’s offshore wind targets. To deliver these targets, we are investing over £10bn to upgrade the network infrastructure across the north of Scotland as the region plays a leading role in the clean energy transition.
As part of this investment, there is a requirement for a new 400kV connection between Beauly and Peterhead.
Beauly to Peterhead Story Map
Our Environmental Consultants, WSP, have created a story map where you can find out more information on the project.
Please let us know if you require information in an adapted format such as paper copy, large print or braille and we will work with you to accommodate your preferences. We are happy to accommodate all reasonable requests for adapted communications.
Stakeholder Engagement
The Beauly – Blackhillock – New Deer – Peterhead 400kV Project is currently in the development stages. Public consultations took place in April 2023 to inform the community on progress to date with the project and we sought feedback from all interested parties.
In this video, Project Manager Catherine Swan and Community Liaison Manager Ryan Davidson describe the approach we are taking to develop our proposals, and the opportunities that are available for stakeholders to feed into the design process.
Our Commitment to Restart
Several years ago, we were developing proposals for a new overhead 400 kV reinforcement between Beauly, Blackhillock and Kintore. However, it was concluded in 2017 that the project was not required at that point in time.
As a stakeholder-led business and following local feedback, we made a commitment to review options for the project should it be required in the future, and we are sticking to that commitment by revisiting the development process, allowing for a period of fresh public engagement. Due to wider changes in the energy system, particularly the development of Peterhead as a critical node on the transmission system, the project scope has also changed meaning the project will no longer connect into Kintore.
Webinar - North of Scotland: Delivering a Pathway to Net Zero
The project was featured in our Spring 2022 regional webinar 'North of Scotland: Delivering a Pathway to Net Zero', attended by over 180 stakeholders from across the region. The webinar provided an overview of our projects in construction and development across the north of Scotland (Highlands, Islands, Moray and Aberdeenshire) and described the role of the north of Scotland in delivering a Network for Net Zero. A recording of the event can be viewed here:
Project Updates

Report on Consultation
Our Reports on Consultation across our three new overhead line projects and associated substation and convertor station developments have now been published. These reports provide a summary of the extensive feedback received during consultation, how this has been considered and confirmation of which routes and substations are now being taken forward to the next stage of development.
Our Reports on Consultation are now available to download from the Project Documentation tab.
Summary Reports on Consultation are also available for each of the three schemes and can be downloaded below:
- Summary Report on Consultation Spittal to Beauly
- Summary Report on Consultation Beauly to Peterhead
- Summary Report on Consultation Kintore to Tealing
A stakeholder webinar available for all to join will be held in the coming weeks to share the changes informed by the feedback. More information about the forthcoming webinar will be shared on our events page shortly.
In further recognition of community feedback, we will seek to rationalise cumulative infrastructure impacts through the removal and undergrounding of existing transmission lines, where technically practical and appropriate, and subject to all necessary planning consents and landowner agreements.
Work to identify and assess potential sections of existing overhead line where their removal will reduce cumulative impacts is ongoing, with an update expected as part of the next round of public consultation on overhead line alignments and more detailed substation designs in early 2024.
We would once again like to thank all stakeholders who took the time to engage with our early consultation process. We will continue to engage with stakeholders ahead of consulting further with local communities and stakeholders in the new year, as we look to refine our proposals.

Report on Consultation
Over the course of this year, we have undertaken extensive consultation on plans to upgrade the electricity transmission network across the north of Scotland and have received a considerable amount of feedback from a wide range of stakeholders regarding our proposals.
We recently advised in our next steps for 2030 network developments update that following assessment of consultation feedback and additional options analysis, we would publish our Report on Consultations (RoCs). These reports provide a summary of the feedback received and how it has been considered, which options we will take forward to the next stage of the development process and any changes to options initially consulted on.
It is our intention to publish the RoCs for this project in the coming months. All stakeholders signed up for updates on the project will receive a link to the report and we will also issue Summary Reports to help ensure accessibility.
These Report on Consultations mark the completion of the first round of non-statutory consultation, where we sought feedback on the corridor, route, and substation locations. We will be consulting further with local communities and stakeholders in the new year, as we look to refine the projects, therefore we welcome an open channel of communication and would like to reassure all stakeholders that there will be further opportunities to engage on this project.
Our Reports on Consultation and Summary Reports on Consultation are now available to download from the Project Documentation tab.

SSEN Transmission sets out next steps for Pathway to 2030 network developments
We have announced our next steps for our Pathway to 2030 programme of projects. We would like to thank everyone who has engaged with our teams and kindly taken the time to respond to our consultations.
Full details of the announcement can be found here:
Next steps for Pathway to 2030

Public Consultation April - June 2023
Public consultation feedback period has now closed
Following our public consultation events in April 2023, the consultation feedback period has now closed. The project team will now collate and analyse the feedback before publishing our Report on Consultation.
Although the feedback period for this stage of the project has closed, we still welcome feedback and questions on an ongoing basis. Any feedback that come in outwith the feedback periods is logged and reviewed by the project team.
We will also publish an FAQ document which will provide information and answers to commonly asked questions.
Those that were unable to attend our face-to-face events can view our virtual consultation room below.
Should you have any questions regarding the consultation, or if you were unable to attend the public events and wish to be provided with more information, please contact the project email: BBNP@sse.com
Consultation materials including PDF maps and the Consultation Booklet are in the Project Documents section of this webpage.

Consultation Period Extended
Due to the extend of interest in our 2030 network development plans across the north of Scotland that are required to meet UK and Scottish Government climate change and energy security targets, we have extended the consultation period for our Beauly-Blackhillock-New Deer-Peterhead project by another week, until Friday 30th June. This follows similar extensions on our Spittal-Loch Buidhe-Beauly 400kV and Kintore-Fiddes-Tealing 400kV projects.
We would encourage anyone with an interest in the Beauly-Blackhillock-New Deer-Peterhead 400kV project to provide their feedback, which will be carefully considered as we continue to develop this project that will be key to help deliver Government net zero and energy independence targets.

Survey works to help inform next stages of development
We have recently started localised surveys, assessments and ground investigation works at various locations across the Pathway to 2030 projects which will be used to help gather information to inform the next stage of development for a major electricity transmission network upgrade in the north of Scotland.
Over the coming weeks and months, our project teams and contractors will undertake a series of site-specific assessments which include the likes of ground investigations, bird surveys, LiDAR flights, and ecological and archaeological walkovers and assessments.
Ground investigation works have either recently commenced or are set to begin throughout the Summer for the new 400kV substation and converter stations proposed as part of our Spittal – Loch Buidhe – Beauly 400kV connection, Western Isles connection, Beauly – Blackhillock – New Deer – Peterhead 400kV connection and East Coast 400kV phase 2 projects. Project teams and contractors will undertake a series of site-specific assessments which will help provide vital information and key data for the next phase of project development.
Some of the geo-technical ground investigations may involve drilling boreholes or digging trial pits, which will allow engineers to understand the geographical make-up and suitability of the ground in certain locations to help inform potential design options.
Site assessments and survey works are a key part of the project development process, and the results of these investigations will provide project teams with valuable information to help inform decisions regarding substation site selections and overhead line routes, which will be subject to further consultation later this year.
Initial surveys will prioritise sites and routes which performed the best based on our initial assessment of key environmental and people, technical, and economic factors, and there have been no decisions taken on locations as yet.
There may be more activity on the ground over the summer, and whilst most assessments are expected to cause very little local disruption, we would like to thank the local community for their patience whilst they are carried out. Where more evasive assessments are required such as ground investigation works, we will work to keep local disruption and environmental impacts to a minimum. Please contact your local Community Liaison Manager if you have any questions.

Virtual Consultation Room

Additional Consultation Event
We'll be at Nairn Community and Arts Centre on Weds 26th April between 10am - 12pm and would welcome local community members to drop in and meet the team to discuss our proposals.

Story Map Available Now
https://pinpointgis.wsp.com/portal/apps/storymaps/stories/7ba958a26c6a4da596e080cf3763aa23

Consultation events
We will be seeking feedback on these route options during an extended feedback period, which will close on 9th June 2023.
Out with the consultation feedback period, we will always accept feedback and any concerns or issues raised with regards to the project, our plans or our engagement.
Consultation materials will be available on the project web page under Project Documentation from Friday 14th April 2023.

Report on Consultation Published
The report includes an FAQ section, which contains responses to questions and concerns raised during the feedback period.
If you have any questions relating to this document, please contact the Community Liaison Manager.

Feedback forms
Public Consultation Events - September 2022

Country Shows
Project Documents
Report on Consultation
-
RoC - New Beauly Area 400kV Substation - Figure 2 - Proposed Site.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 1.6 MB
-
Report on Consultation - New Beauly Area 400kV Substation and HVDC Converter Station.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 2.3 MB
-
Summary ROC - Beauly to Peterhead.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 2.8 MB
-
Report on Consultation - Beauly to Blackhillock to New Deer to Peterhead 400kV OHL.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 3.9 MB
-
RoC - Beauly - Peterhead OHL - Figure 4.10 Proposed Route to be taken to Alignment.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 5.8 MB
-
RoC - Beauly - Peterhead OHL - Figure 1.1 - Route Options Shared at Consultations.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 10.6 MB
-
RoC - Beauly - Peterhead OHL - Preferred Route with Amendments.pdf
- Type:
- Date:
- 01 December 2023
- Size:
- 14.1 MB
Next steps for Pathway to 2030 network developments
-
The challenges with undergrounding at 400kV
- Type:
- Date:
- 01 December 2023
- Size:
- 347.9 KB
-
How has the need for Pathway to 2030 projects been assessed and determined
- Type:
- Date:
- 14 November 2023
- Size:
- 5.1 MB
-
SSEN Transmission sets out next steps for 2030 network developments .pdf
- Type:
- Date:
- 11 October 2023
- Size:
- 122.3 KB
April Consultation Event Materials
-
Consultation Booklet - April 2023
- Type:
- Date:
- 14 July 2023
- Size:
- 76.6 MB
-
Route Consultation Document - April 2023
- Type:
- Date:
- 15 April 2023
- Size:
- 44.2 MB
-
Section 1 - Constraints Map.pdf
- Type:
- Date:
- 13 April 2023
- Size:
- 2 MB
-
Section 2 - Constraints Map.pdf
- Type:
- Date:
- 13 April 2023
- Size:
- 20 MB
-
Section 3 - Constraints Map.pdf
- Type:
- Date:
- 13 April 2023
- Size:
- 4.6 MB
-
Section 4 - Constraints Map.pdf
- Type:
- Date:
- 13 April 2023
- Size:
- 24.4 MB
-
Section 5 - Constraints Map.pdf
- Type:
- Date:
- 13 April 2023
- Size:
- 3 MB
-
Section 6 - Constraints Map.pdf
- Type:
- Date:
- 13 April 2023
- Size:
- 15.5 MB
-
Section 7 - Constraints Map.pdf
- Type:
- Date:
- 13 April 2023
- Size:
- 8.7 MB
-
Section 8 - Constraints Map.pdf
- Type:
- Date:
- 13 April 2023
- Size:
- 21.2 MB
-
Section 9 - Constraints Map.pdf
- Type:
- Date:
- 13 April 2023
- Size:
- 24.2 MB
-
Section 10 - Constraints Map.pdf
- Type:
- Date:
- 13 April 2023
- Size:
- 3 MB
-
Section 11 - Constraints Map
- Type:
- Date:
- 12 April 2023
- Size:
- 6.6 MB
-
1. Sections 1-3
- Type:
- Date:
- 12 April 2023
- Size:
- 63.3 MB
-
2. Sections 3-5
- Type:
- Date:
- 12 April 2023
- Size:
- 18.4 MB
-
3. Sections 5-8
- Type:
- Date:
- 12 April 2023
- Size:
- 19.9 MB
-
4. Section 7-9
- Type:
- Date:
- 12 April 2023
- Size:
- 25.6 MB
-
5. Sections 9-11
- Type:
- Date:
- 12 April 2023
- Size:
- 17.5 MB
-
6. Section 11
- Type:
- Date:
- 12 April 2023
- Size:
- 15 MB
Project Documentation
-
Pathway to 2030 - areas surrounding Beauly - Options as of April 23.pdf
- Type:
- Date:
- 27 April 2023
- Size:
- 6.4 MB
-
BBNP Poster.jpg
- Type:
- Image
- Date:
- 12 April 2023
- Size:
- 1.5 MB
-
Beauly to Peterhead Report on Consultation
- Type:
- Date:
- 27 March 2023
- Size:
- 9.1 MB
-
North of Scotland Webinar March 2022 - Post-Webinar Q&A.pdf
- Type:
- Date:
- 30 October 2022
- Size:
- 306.8 KB
-
Beauly to Peterhead Consultation Document September 2022.pdf
- Type:
- Date:
- 07 October 2022
- Size:
- 510.5 KB
-
Consultation Booklet Sept 2022
- Type:
- Date:
- 07 October 2022
- Size:
- 14.3 MB
-
Consultation Poster Sept 2022
- Type:
- Date:
- 07 October 2022
- Size:
- 3 MB
-
All Beauly to Peterhead Consultation Document Figures.pdf
- Type:
- Date:
- 07 October 2022
- Size:
- 28.1 MB
Project Gallery
Project FAQs
FAQs
People/Local Businesses
We would like to send you relevant communications via email, such as invitations to stakeholder events, surveys, updates on projects and future developments. If you are happy to receive email updates, please opt-in by ticking the box. You can unsubscribe at any time by contacting us at unsubscribe@ssen.co.uk, or by clicking the 'unsubscribe' link which will be at the end of each of our emails.
Recite me
To make use of this function please click on the 3 'A's' button at the bottom left of the website.

Latest Links
-
Report on Consultation
Our Reports on Consultation across our three new overhead line projects and associated substation and convertor station developments have now been published. These reports provide a summary of the extensive feedback received during consultation, how this has been considered and confirmation of which routes and substations are now being taken forward to the next stage of development.
Our Reports on Consultation are now available to download from the Project Documentation tab.
Summary Reports on Consultation are also available for each of the three schemes and can be downloaded below:
- Summary Report on Consultation Spittal to Beauly
- Summary Report on Consultation Beauly to Peterhead
- Summary Report on Consultation Kintore to Tealing
A stakeholder webinar available for all to join will be held in the coming weeks to share the changes informed by the feedback. More information about the forthcoming webinar will be shared on our events page shortly.
In further recognition of community feedback, we will seek to rationalise cumulative infrastructure impacts through the removal and undergrounding of existing transmission lines, where technically practical and appropriate, and subject to all necessary planning consents and landowner agreements.
Work to identify and assess potential sections of existing overhead line where their removal will reduce cumulative impacts is ongoing, with an update expected as part of the next round of public consultation on overhead line alignments and more detailed substation designs in early 2024.
We would once again like to thank all stakeholders who took the time to engage with our early consultation process. We will continue to engage with stakeholders ahead of consulting further with local communities and stakeholders in the new year, as we look to refine our proposals.
-
Report on Consultation
Over the course of this year, we have undertaken extensive consultation on plans to upgrade the electricity transmission network across the north of Scotland and have received a considerable amount of feedback from a wide range of stakeholders regarding our proposals.
We recently advised in our next steps for 2030 network developments update that following assessment of consultation feedback and additional options analysis, we would publish our Report on Consultations (RoCs). These reports provide a summary of the feedback received and how it has been considered, which options we will take forward to the next stage of the development process and any changes to options initially consulted on.
It is our intention to publish the RoCs during the week commencing 27 November. All stakeholders signed up for updates on the project will receive a link to the report and we will also issue Summary Reports to help ensure accessibility.
These Report on Consultations mark the completion of the first round of non-statutory consultation, where we sought feedback on the corridor, route, and substation locations. We will be consulting further with local communities and stakeholders in the new year, as we look to refine the projects, therefore we welcome an open channel of communication and would like to reassure all stakeholders that there will be further opportunities to engage on this project.
Our Reports on Consultation and Summary Reports on Consultation are now available to download from the Project Documentation tab. -
SSEN Transmission sets out next steps for Pathway to 2030 network developments
We have announced our next steps for our Pathway to 2030 programme of projects. We would like to thank everyone who has engaged with our teams and kindly taken the time to respond to our consultations.
Full details of the announcement can be found here:
Next steps for Pathway to 2030