Project Type: Transmission reinforcement
Location: Argyll & Bute

Contact Details

Liaison Manager

Kelly Scott
Title: Community Liaison Manager
Mobile: 07443 772 946
Address: Networks
1 Waterloo Street
Glasgow
G2 6AY

Land Manager

Grace Campbell
Title: Land Manager
Address: Scottish Hydro Electric Transmission Plc
Inveralmond House
200 Dunkeld Road
Perth
PH1 3AQ
Status: Early Development

September 2020 Virtual Consultation

What is happening?

SSEN Transmission are launching a Virtual Consultation Exhibition, to gain your views and feedback on our proposals to reinforce the existing transmission network connections in the region, to enable renewable energy projects to connect to the GB transmission network and ensure security of supply. 


What are you consulting on?

In recognition of the feedback received from previous consultation, about the potential for an additional overhead line at the head of Loch Awe, we committed to explore undergrounding across the Strath of Orchy.

Feedback concerning alternative overhead line routes and connection locations also led to a review of the connection options, and following assessment we have identified an alternative overhead line connection option.

The virtual consultation exhibition has been designed to be fully interactive, allowing for presentation of key project information and plans, as well as providing an opportunity to ask questions about the project. Visitors will be able to engage directly with the project team, via a live text chat function,where they can ask any questions they might have about the projectand share their feedback on the current proposals.

How can I get involved?

 

If you cannot participate in the virtual consultation, you can still complete a feedback form or contact the project Community Liaison Manager, who can also be contacted for any further information or queries.

 

For further information on how to operate the virtual consultation platform, please see our User Guide

 

About the project

The overall aim of the project is to reinforce the existing transmission network connections in the Argyll region, to enable renewable energy projects to connect to the GB transmission network and to ensure security of supply.

The existing transmission network for Argyll was originally designed to serve a rural area with low demand for electricity. Requests from renewable generation developers to connect to the network in this area exceed the current capacity of the existing transmission network, meaning a new transmission circuit is required to meet demand from generation developers and ensure security of supply.

We have been consulting locally on this project (formerly referred to as the North Argyll Project) since March 2016.

The original proposals consisted of a new 275/132kV substation (Creag Dhubh) near to the existing Inveraray to Taynuilt 132kV overhead line, with a new 275kV overhead line circuit between the proposed Creag Dhubh substation and the existing Dalmally Switching Station.

We presented our preferred overhead alignment from Creag Dhubh substation to the existing Dalmally Switching Station during a consultation event in March 2018.

In recognition of the feedback received (and in combination with previous comments dating back to 2016), we committed to explore underground cable options and assess the potential for alternative overhead line options that would avoid crossing the Strath of Orchy.

We have completed further studies to inform the options assessments and are now currenly considering three connection options for the project:

 

 

The data in this map is provided for indicative purposes only and may be subject to change. Scottish Hydro Electric Transmission plc do not accept responsibility for its accuracy, completeness or validity. The data should not be copied, reproduced or utilised externally without permission.

Autumn 2019 - Project Update

Following on from our previous update confirming Balfour Beatty as our design contractor appointed to carry out further in-depth feasibility studies for the proposed North Argyll project, SHE Transmission can now confirm that Balfour Beatty have completed these studies which involved investigative ground survey works, engagement with supply chain specialists and provision of outline cable design parameters for potential routes from the vicinity of the Duncan Ban monument to Dalmally switching station where undergrounding is being explored. Now that the studies have been concluded, we are currently in the process of internal review, considering the outputs against engineering, environmental and economic criterium and conducting further analysis which is anticipated to be completed in the upcoming weeks.

Contractor Appointed for Feasability Works

We are pleased to confirm the appointment of our design contractor, Balfour Beatty, to carry out further in-depth feasibility studies for the proposed North Argyll Transmission Reinforcement. The initial focus will be to conduct further in-depth studies of the proposed cable alignment. This includes investigative ground survey works from the vicinity of the Duncan Ban monument to Dalmally switching station where undergrounding is being explored. The commitment to explore the feasibility of undergrounding follows feedback and consultation with local stakeholders on options for the proposed project’s design. We will also be progressing surveys and ground investigation works along the remaining section of the alignment to the proposed Creag Dhubh substation where it is progressing a proposed overhead solution.

July 2018 - Project Update

Following our most recent consultation events in March this year, we have been busy reviewing all feedback received from the community and other stakeholders, as we continue to take forward the North Argyll project. In early May, following the conclusion of the consultation, we issued a press release confirming our intention to further explore undergrounding in places of particular local sensitivity, where it can be demonstrated to be technically and environmentally feasible, as well as economic to GB bill payers who will ultimately pay for the proposed reinforcement through their electricity bills. We have recently been active in this area, carrying out further walkover surveys with our environmental consultant and internal engineers ahead of engaging a specialist design and build contractor to further develop these possibilities, focussing on the area between the road to the Duncan Ban monument and the Dalmally substation. We aim to conclude final technical solution proposals by quarter 1 of next year. Considering the above and the timescales required to complete this work, we have an amended timeline for the project, still retaining the required completion date of October 2023 but with a revised date for submission of a consent application in quarter one 2020. Whilst this will result in a more intense construction phase it will allow us to develop and consider the further design studies being undertaken. We have also been working to complete our Report on Consultation which we expect to publish on the project website within the next few weeks. The purpose of this report is to inform stakeholders of how comments made during the Alignment Consultation have been responded to by SHE Transmission, prior to a request to Scottish Government Energy Consents Unit for an EIA (Environmental Impact Assessment) Scoping Opinion. Due to the main focus of the Alignment Consultation being the alignment of an overhead line, the Report on Consultation naturally references an overhead line solution. It is important to emphasise that underground cabling options are still being assessed and we have therefore not yet determined our proposed final solution. We will also shortly publish additional Frequently Asked Questions, providing answers to project specific questions posed to us during the consultation events. We remain committed to engaging openly and meaningfully with the local community, elected representatives and other stakeholders as we continue to take forward the project and would like to thank the community for their constructive engagement and feedback to date.

Further Underground Cable Feasability Study

In line with feedback recieved regarding the strong feeling in the Dalmally area about the potential for overhead transmission infrastructure, SSEN will be continuing to explore the feasability of undergrounding in areas of particular concern. To read more, please see the press release accessable via the following link: https://www.ssen-transmission.co.uk/news-views/articles/2018/5/ssen-to-take-forward-further-undergrounding-studies-following-feedback-received-during-north-argyll-consultation/

Consultation Deferment

Local community members may be aware that Scottish and Southern Electricity Networks had intended to hold public consultation events commencing from Monday 15th January 2018. Whilst the requirements for the reinforcements still exist, due to uncertainty surrounding key drivers we have decided to review the proposed delivery timescales. We have therefore taken the decision to defer the consultation events that were due to take place next week whilst we undertake this review. We anticipate that the events will be rescheduled for the next few months and will be sure to inform the community as soon as new dates are confirmed.

Document downloads

Option 1 Map - September 2020

Related Projects: Creag Dhubh - Dalmally 275kV Connection

File Type: pdf
Published: 28 Aug 2020
Option 2 Map - September 2020
File Type: pdf
Published: 28 Aug 2020
Option 3 Map - September 2020

Related Projects: Creag Dhubh - Dalmally 275kV Connection

File Type: pdf
Published: 28 Aug 2020
Project Overview Map (All Options) - September 2020
File Type: pdf
Published: 28 Aug 2020
Creag Dhubh to Dalmally 275kV Connection - Consultation Document 2020

Related Projects: Creag Dhubh - Dalmally 275kV Connection

File Type: pdf
Published: 31 Aug 2020
Virtual Consultation Boards - September 2020

Related Projects: Creag Dhubh - Dalmally 275kV Connection

File Type: pdf
Published: 28 Aug 2020
Creag Dhubh to Dalmally - Virtual Consultation Poster - Aug 2020
File Type: pdf
Published: 17 Aug 2020
Consultation Booklet - September 2020
File Type: pdf
Published: 17 Aug 2020
Consultation Booklet - March 2018
File Type: pdf
Published: 08 Jul 2020
Consultation Booklet - October 2016
File Type: pdf
Published: 08 Jul 2020
Consultation Booklet - March 2016
File Type: pdf
Published: 08 Jul 2020
Alignment Consultation Document - Creag Dhubh substation to Dalmally substation 275kV Overhead Line - 2018

Related Projects: Creag Dhubh - Dalmally 275kV Connection

File Type: pdf
Published: 01 Sep 2020
Virtual Consultation User Guide 2020
File Type: pdf
Published: 01 Sep 2020

Feedback

Creag Dhubh to Dalmally 275kV Connection- September 2020

Creag Dhubh to Dalmally 275kV Connection- September 2020

Share your views with us

Sign up for project updates

To keep informed of all that is happening on this project, please complete your details below and provide consent to enable us to send you updates via email

For information on how we collect and process your data, please see our privacy notice at www.ssen.co.uk/PrivacyNotice/. If you do not have access to our website, or would like to receive a hard copy, please contact us.