Overview
Planning Application Submission
Following the second pre application consultation feedback event that we hosted in June 2024 at Braco Hall we can confirm that we have submitted our planning application to Perth and Kinross Council for the Cambushinnie 400kV substation.
The Cambushinnie 400kV substation is part of a wider upgrade to the transmission network in the north of Scotland, helping deliver high voltage, clean renewable power for connection to homes and businesses across the UK – helping meet national net zero and energy security ambitions.
Our planning application regarding our proposal to construct and operate a 400kV AC substation, located immediately west of the existing Braco West 275kV substation has been made to Perth and Kinross Council under reference 25/00490/FLN.
Should you wish to view our application in full and submit formal comment to the council our application is available to be viewed via the Perth and Kinross Council planning portal, using the above reference.
All the documentation submitted as part of the application can also be viewed and downloaded from the documents section of this webpage.
We would like to thank those who provided feedback as part of our pre-application consultation events, which have been key in helping us shape our proposals and we now look forward to working with Perth and Kinross Council and other key stakeholders as part of the consenting process.
Please see below for a flythrough video of the substation and haul road proposals at this stage.
About the Project
In order to support the continued growth in onshore and offshore renewables across the north of Scotland, supporting the country's drive towards Net Zero, investment in network infrastructure is needed to connect this renewable power and transport it from source to areas of demand across the country.
Extensive studies have confirmed the need to upgrade the second circuit of the Beauly – Denny overhead line (OHL) from 275kV to 400kV. To do this, we require two new 400kV substations as well as modifications or extensions to other substations along the Beauly – Denny route.
The proposed Cambushinnie 400kV substation is located immediately west of the existing Braco West 275kV substation. The new substation will house more sophisticated switching capability than is present in the existing 275kV substation, which requires significantly more space than either existing substation can currently accommodate.
Why is the Project Required?
As part of its statutory and transmission licence obligations, SSEN Transmission has a number of duties including:
- the development and maintenance of an efficient, coordinated and economical system of electricity transmission
- to facilitate competition in the supply and generation of electricity
- to ensure that the security of the network is maintained as the demand and/or generation connections change over time
SSEN Transmission has a licence obligation to invest in its existing assets to maintain network health and condition. SSEN Transmission also has a statutory duty under the Electricity Safety, Quality and Continuity Regulations 2002 to ensure that the electricity transmission network is fit for purpose.
Pathway to 2030
The Pathway to 2030, published by National Energy System Operator NESO, the electricity system operator for Great Britain, sets the blueprint for the electricity transmission network infrastructure required to enable the forecasted growth in renewable electricity across Great Britain.
The projects identified within the Pathway to 2030 are critical to delivering the UK and Scottish Government’s offshore wind targets. To deliver these targets, we are investing over £10bn to upgrade the network infrastructure across the north of Scotland as the region plays a leading role in the clean energy transition.
As part of this investment, there is a requirement for a new 400kV substation near the existing Braco West substation.
Community Engagement
Throughout the life of our projects, we aim to work positively with local communities and keep people informed about what we are doing. This is particularly important when we are developing a proposal and we want to understand what local people think about our plans.
We endeavour to take the time to discuss proposals with local community councils, encourage engagement from the wider community and listen to the feedback we receive.
We will do our best to answer any questions and address issues or concerns that are raised with us.
When our project progresses into construction, we will continue working closely with the local community to ensure that our work has as little impact on the lives of those living and working in the area and as many long term positive effects as possible.
How we’re embracing artificial intelligence (AI)
We intend to use AI to assist our experienced teams in the analysis of your feedback, so we can categorise key points raised more quickly. You can learn more about how we’re utilising AI on this dedicated web page.
Project Updates
Featured updates
Featured updates for this project

Cambushinnie 400 kV Overhead Line Tie-in section 37 application

Cambushinnie 400kV Substation – Planning Application
Project updates
Documents
Planning Application - Covering Letter
This document is the cover letter to Perth and Kinross Council that accompanied the planning application for the proposed Cambushinnie 400Kv substation.
Planning Application – Environmental Appraisal (includes appendices)
This report provides a description of the Proposed Development, including details of the key components and information regarding the construction, operation and maintenance of the Proposed Development. This report also includes an environmental assessment that assesses the level of effect the Proposed Development is predicted to have on the environment, as well as identifying relevant mitigation measures. The report includes supporting appendices which include further detailed reporting, information and / or technical assessments to support the EA Report.
Planning Application – Planning Statement
Planning Application – Planning Drawings
The drawings provide an overview of the Proposed Development.
Planning Application – Design and Access Statement
This Design and Access Statement (DAS) has been prepared to support the planning application. It sets out design considerations in developing the Proposed Development.
Planning Application – Pre-Application Consultation (PAC) Report
Planning Application – Substation Lighting Mitigation Strategy
This plan outlines the strategy that will inform the detailed lighting design to ensure that the lighting at the new substation does not adversely impact on the local environment or neighbouring properties.
Planning Application – Drainage Impact Assessment
This Drainage Strategy Report sets out proposed arrangements of disposal for both foul water and surface water for the proposed development.
Planning Application - Flood Risk Assessment
The aim of the FRA is to outline and assess the flood risk related to the Proposed Development and set out the proposed measures which are incorporated into the design to mitigate any identified risks.
Planning Application – HRA Memorandum
This memorandum sets out details in regard to Habitats Regulations Appraisal (HRA) for the Proposed Development.
Planning Application – Geotechnical Synopsis
This Technical Note presents the findings of Ground Investigation for the proposed site.
Cambushinnie 400 kV Overhead Line Tie-in section 37 covering letter
Cambushinnie 400 kV Overhead Line Tie-in section 37 drawings
Cambushinnie 400 kV Overhead Line Tie-in section 37 Environmental Appraisal
Cambushinnie 400 kV Overhead Line Tie-in section 37 Environmental Appraisal Appendices A-L
Cambushinnie 400 kV Overhead Line Tie-in section 37 Tie In HRA Memorandum
Cambushinnie 400 kV Overhead Line Tie-in section 37 Tie in planning statement
Cambushinnie 400 kV Overhead Line Tie-in section 37 – Figures 1-3
Project Documents
-
Cambushinnie Haul Road Map.pdf
- Type:
- Date:
- 11 March 2025
- Size:
- 1.5 MB
This map provides information to our stakeholders on the Haul Road during the construction of Cambushinnie Substation.
-
Cambushinnie Red Line Boundary Map.pdf
- Type:
- Date:
- 11 March 2025
- Size:
- 1.4 MB
This map provides information to our stakeholders on the works associated with the construction of the Haul Road.
-
Cambushinnie Haul Road March 2025 Pre-application Consultation Booklet.pdf
- Type:
- Date:
- 05 March 2025
- Size:
- 9 MB
This document provides information to our stakeholders about the proposed Cambushinnie Haul Road and was provided during our consultation in March 2025.
-
Cambushinnie Haul Road Pre-application Consultation Booklet.pdf
- Type:
- Date:
- 05 November 2024
- Size:
- 8.6 MB
This document provides information to our stakeholders about the proposed Cambushinnie Haul Road and was provided during our consultation in November 2024.
-
Cambushinnie Pre-application Consultation Feedback Booklet.pdf
- Type:
- Date:
- 29 May 2024
- Size:
- 4.3 MB
This document provides information to our stakeholders about the project and was provided during our consultation in June 2024
-
Braco area (Cambushinnie) Pre-application Consultation Booklet
- Type:
- Date:
- 07 March 2024
- Size:
- 4.9 MB
This document provides information to our stakeholders about the project and was provided during our consultation in March 2024
-
Braco area (Cambushinnie) Pre-application Consultation Poster
- Type:
- Date:
- 07 March 2024
- Size:
- 451.9 KB
This document provides information to our stakeholders about our consultation events in March 2024
-
Report on Consultation - Braco West Substation.pdf
- Type:
- Date:
- 08 February 2024
- Size:
- 7.5 MB
This Report on Consultation (and associated appendices/maps) documents the consultation process which has been undertaken for the project at corridor, routeing, alignment or substation site selection stage. It describes the key responses received and provides detail on the actions proposed in response to the issues raised.
-
Braco West Site Selection Consultation Document
- Type:
- Date:
- 18 August 2023
- Size:
- 2.2 MB
-
Braco West 400kV Substation August 2023 Public Consultation Booklet
- Type:
- Date:
- 11 August 2023
- Size:
- 3.7 MB
-
Environmental Considerations
- Type:
- Date:
- 11 August 2023
- Size:
- 5 MB
-
Potential Substation Site Map
- Type:
- Date:
- 11 August 2023
- Size:
- 8.6 MB
-
Stage 2 Site Options Appraised Map
- Type:
- Date:
- 11 August 2023
- Size:
- 9 MB
-
Substation Site Selection Options Considered Map
- Type:
- Date:
- 11 August 2023
- Size:
- 10.4 MB
-
New Braco West 400kV Substation Public Consultation Poster
- Type:
- Date:
- 09 August 2023
- Size:
- 79.8 KB
Pathway to 2030 Projects - Additional Information
FAQs
Who we are
About the Pathway to 2030 projects
Our approach to routeing and public consultation
Environmental considerations
Community and landowner considerations
Cost and engineering considerations
Recite me
To make use of this function please click on the 3 'A's' button at the bottom left of the website.

Latest Links
-
Report on Consultation
Our Reports on Consultation across our three new overhead line projects and associated substation and convertor station developments have now been published. These reports provide a summary of the extensive feedback received during consultation, how this has been considered and confirmation of which routes and substations are now being taken forward to the next stage of development.
Our Reports on Consultation are now available to download from the Project Documentation tab.
Summary Reports on Consultation are also available for each of the three schemes and can be downloaded below:
- Summary Report on Consultation Spittal to Beauly
- Summary Report on Consultation Beauly to Peterhead
- Summary Report on Consultation Kintore to Tealing
A stakeholder webinar available for all to join will be held in the coming weeks to share the changes informed by the feedback. More information about the forthcoming webinar will be shared on our events page shortly.
In further recognition of community feedback, we will seek to rationalise cumulative infrastructure impacts through the removal and undergrounding of existing transmission lines, where technically practical and appropriate, and subject to all necessary planning consents and landowner agreements.
Work to identify and assess potential sections of existing overhead line where their removal will reduce cumulative impacts is ongoing, with an update expected as part of the next round of public consultation on overhead line alignments and more detailed substation designs in early 2024.
We would once again like to thank all stakeholders who took the time to engage with our early consultation process. We will continue to engage with stakeholders ahead of consulting further with local communities and stakeholders in the new year, as we look to refine our proposals.
-
Report on Consultation
Over the course of this year, we have undertaken extensive consultation on plans to upgrade the electricity transmission network across the north of Scotland and have received a considerable amount of feedback from a wide range of stakeholders regarding our proposals.
We recently advised in our next steps for 2030 network developments update that following assessment of consultation feedback and additional options analysis, we would publish our Report on Consultations (RoCs). These reports provide a summary of the feedback received and how it has been considered, which options we will take forward to the next stage of the development process and any changes to options initially consulted on.
It is our intention to publish the RoCs during the week commencing 27 November. All stakeholders signed up for updates on the project will receive a link to the report and we will also issue Summary Reports to help ensure accessibility.
These Report on Consultations mark the completion of the first round of non-statutory consultation, where we sought feedback on the corridor, route, and substation locations. We will be consulting further with local communities and stakeholders in the new year, as we look to refine the projects, therefore we welcome an open channel of communication and would like to reassure all stakeholders that there will be further opportunities to engage on this project.
Our Reports on Consultation and Summary Reports on Consultation are now available to download from the Project Documentation tab. -
SSEN Transmission sets out next steps for Pathway to 2030 network developments
We have announced our next steps for our Pathway to 2030 programme of projects. We would like to thank everyone who has engaged with our teams and kindly taken the time to respond to our consultations.
Full details of the announcement can be found here:
Next steps for Pathway to 2030